Tampa General — Project Schedule
CUD-16 baseline · 2987 activities · read-only · updated 2026-06-02
2987 shown · tap a row for its activity ID
-
06/03→01/26
·
Other
Wall & Door Protection - Submittal
DIV-10-140 Wall & Door Protection - Submittal Wall & Door Protection
-
08/04→02/09
1
Electrical
UG Electrical RI (Includes UG Feeder to Fire Pump)
FL1-40 Floor 1 - UG Electrical RI (Includes UG Feeder to Fire Pump) Under slab Utilties & SOG
-
09/16→01/26
2A
Plumbing
In-Wall Plumbing Rough & QC
SC2A-N2-IR-130 Floor 2A - In-Wall Plumbing Rough & QC Floor 2A SC 2.N2 Sterile
-
10/01→02/13
3A
Plumbing
OH & In Wall MED Gas Rough In & QC
SC3A-N2-IR-230 Floor 3A - OH & In Wall MED Gas Rough In & QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
10/06→01/26
·
Flooring/Finishes
Millwork/Casework Lv-10 - Review & Approval
DIV-09-10-110 Millwork/Casework Lv-10 - Review & Approval Millwork/Casework Lv-10
-
10/06→01/30
·
Flooring/Finishes
Millwork/Casework Lv-11 - Review & Approval
DIV-09-11-120 Millwork/Casework Lv-11 - Review & Approval Millwork/Casework Lv-11
-
10/06→01/30
·
Flooring/Finishes
Millwork/Casework Lv-12 - Review & Approval
DIV-09-12-130 Millwork/Casework Lv-12 - Review & Approval Millwork/Casework Lv-12
-
10/06→01/30
·
Flooring/Finishes
Millwork/Casework Lv-13 - Review & Approval
DIV-09-13-140 Millwork/Casework Lv-13 - Review & Approval Millwork/Casework Lv-13
-
10/06→01/26
·
Flooring/Finishes
Millwork/Casework Lv-9 - Review & Approval
DIV-09-9-910 Millwork/Casework Lv-9 - Review & Approval Millwork/Casework Lv-9
-
10/13→01/26
2C
Plumbing
In-Wall Plumbing Rough QC
SC2C-N1-IR-140 Floor 2C - In-Wall Plumbing Rough QC Floor 2C SC 2.N1 In Wall Rough In
-
10/20→02/09
3A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC3A-N2-IR-190 Floor 3A - OH Duct/VAV Boxes Rough-In/Insulation Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
10/23→02/13
3A
Plumbing
OH Plumbing Rough In/Insulation & QC
SC3A-N2-IR-210 Floor 3A - OH Plumbing Rough In/Insulation & QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
11/03→01/27
·
Other
Bridge - Deck & Detail Level 2, 3 & Roof
BRIDGE-160 Bridge - Deck & Detail Level 2, 3 & Roof New Bridge
-
11/06→02/10
4A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC4A-N2-IR-290 Floor 4A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 4A SC 4.N2 Overhead Roughs
-
11/09→02/20
3A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC3A-N2-IR-220 Floor 3A - OH HVAC Piping/Controls/Insulation & QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
11/11→02/06
·
Flooring/Finishes
Millwork/Casework Lv-5 - Review & Approval
DIV-09-5-510 Millwork/Casework Lv-5 - Review & Approval Millwork/Casework Lv-5
-
11/12→02/05
2
Drywall/Framing
Floor 2 C - Layout, Frame & Insulate Walls
GBW-200 Floor 2 C - Layout, Frame & Insulate Walls Floor 2 Go Back Work
-
11/12→02/10
3C
Plumbing
OH Plumbing Rough In/Insulation & QC
SC3C-N1-IR-200 Floor 3C - OH Plumbing Rough In/Insulation & QC Floor 3C SC 3.N1 Overhead Roughs
-
11/18→02/06
3C
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC3C-N1-IR-210 Floor 3C - OH HVAC Piping/Controls/Insulation & QC Floor 3C SC 3.N1 Overhead Roughs
-
11/20→01/27
9
Other
Strip - Level 9, Pour 48 (2 day cure Drop & Reshore)
DP48-1050 Strip - Level 9, Pour 48 (2 day cure Drop & Reshore) Pour 48 (1)
-
11/24→02/13
3A
Electrical
OH Electrical & I.T. Rough In & QC
SC3A-N2-IR-200 Floor 3A - OH Electrical & I.T. Rough In & QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
12/01→02/06
4C
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC4C-N1-IR-100 Floor 4C - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 4C SC 4.N1 Overhead Roughs
-
12/03→01/30
·
Concrete/Structure
Bridge - Set New Bridge Steel on Existing
BRIDGE-150 Bridge - Set New Bridge Steel on Existing New Bridge
-
12/03→02/10
4A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC4A-N2-IR-190 Floor 4A - OH Duct/VAV Boxes Rough-In/Insulation Floor 4A SC 4.N2 Overhead Roughs
-
12/05→04/07
4C
Plumbing
In-Wall Plumbing Rough QC
SC4C-N1-IR-140 Floor 4C - In-Wall Plumbing Rough QC Floor 4C SC 4.N1 Framing & Interior Roughs
-
12/05→01/30
9
Other
Strip - Level 9, Pour 50 (2 day cure Drop & Reshore)
DP50-1050 Strip - Level 9, Pour 50 (2 day cure Drop & Reshore) Pour 50 (3)
-
12/08→02/13
·
Concrete/Structure
Install Precast Panels Levels 1-6 (Set 1 WS)
SE-700 Install Precast Panels Levels 1-6 (Set 1 WS) Precast
-
12/08→04/07
4C
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC4C-N1-IR-150 Floor 4C - In-Wall Electrical & I.T. Rough In & Control & QC Floor 4C SC 4.N1 Framing & Interior Roughs
-
12/08→02/05
4C
HVAC/Mechanical
OH Pneumatic Tube Stations Rough-In
SC4C-N1-IR-130 Floor 4C - OH Pneumatic Tube Stations Rough-In Floor 4C SC 4.N1 Overhead Roughs
-
12/11→01/29
9
Other
Strip - Level 9, Pour 51 (2 day cure Drop & Reshore)
DP51-1050 Strip - Level 9, Pour 51 (2 day cure Drop & Reshore) Pour 51 (4)
-
12/15→02/02
·
Other
Bridge - Temporary Handrails
BRIDGE-170 Bridge - Temporary Handrails New Bridge
-
12/15→01/29
3A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
SC3A-N2-IR-350 Floor 3A - Med Gas Zone Valve Boxes/Terminations to Headwall Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
12/15→02/05
5
Plumbing
OH Sanitary/Storm
FL5-1010 Floor 5 - OH Sanitary/Storm Floor 05 - Surgical Suite (11 OR's)
-
12/15→02/11
5A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC5A-N2-IR-135 Floor 5A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
12/15→02/05
5C
Other
Layout Walls & Trade Penetrations
SC5C-N1-IR-100 Floor 5C - Layout Walls & Trade Penetrations Floor 5C SC 5.N1 Overhead Roughs
-
01/07→02/16
·
Flooring/Finishes
Interior Signage - Submittal (Revise/Resubmit)
DIV-10-220 Interior Signage - Submittal (Revise/Resubmit) Interior Signage
-
01/12→01/26
6
Concrete/Structure
Prep/Grind/Float Sill Curbs
6EXT-170 Floor 06 - Prep/Grind/Float Sill Curbs 6th Floor
-
01/14→01/28
CEP
Concrete/Structure
Trade Contractor Sources New Louver Vendor
RFI-0820.20 Trade Contractor Sources New Louver Vendor RFI-0820 Generator Louver Revisions
-
01/15→01/27
2B
Data
Low Voltage Rough-In Piping
SC2B-N3-F-100 Floor 2B - Low Voltage Rough-In Piping Floor 2B SC 2.N3
-
01/16→01/30
·
Other
IMRIS R10 - TGH/AE Review & Approve Shops
REV10-1240 IMRIS R10 - TGH/AE Review & Approve Shops IMRIS Procurement - Rev. 10
-
01/19→02/18
·
Concrete/Structure
CMU Level 1-5 Stair 28
STR-26-200 CMU Level 1-5 Stair 28 CMU Stairs 26 & 28
-
01/19→02/13
·
Concrete/Structure
Install Scaffold For CMU 1-5 Stair 28
STR-26-230 Install Scaffold For CMU 1-5 Stair 28 CMU Stairs 26 & 28
-
01/19→02/06
2A
Drywall/Framing
Blocking/Backing/Plywood
SC2A-N2-IR-230 Floor 2A - Blocking/Backing/Plywood Floor 2A SC 2.N2 Sterile
-
01/19→02/06
2C
Drywall/Framing
Blocking/Backing/Plywood
SC2C-N1-IR-220 Floor 2C - Blocking/Backing/Plywood Floor 2C SC 2.N1 In Wall Rough In
-
01/20→01/27
·
Concrete/Structure
Install Steel Pan Stairs Level 1-4 Stair 27
ST27EL-120 Install Steel Pan Stairs Level 1-4 Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
01/20→01/26
4
Concrete/Structure
Sheath/Inspect CW Box Beam Header
4EXT-120 Floor 04 - Sheath/Inspect CW Box Beam Header 4th Floor
-
01/22→01/26
11
Other
FRP Columns & Shearwalls - Level 11, Pour 57
DP57-1000 FRP Columns & Shearwalls - Level 11, Pour 57 Pour 57 (2)
-
01/22→01/26
12
Other
MEP Rough-In - Level 12,Pour 60
DP60-1020 MEP Rough-In - Level 12,Pour 60 Pour 60 (1)
-
01/26→02/06
·
Concrete/Structure
Bridge - Build Temporary Weather Barrier on Level 3
D-1070 Bridge - Build Temporary Weather Barrier on Level 3 Demo
-
01/26→01/30
·
Concrete/Structure
Bridge - Remove Existing Concrete Columns Down to Existing Foundations
D-1140 Bridge - Remove Existing Concrete Columns Down to Existing Foundations Demo
-
01/26→01/30
·
Other
IMRIS R10 - IMRIS Vendor Kickoff + Coordination Mtgs
REV10-1150 IMRIS R10 - IMRIS Vendor Kickoff + Coordination Mtgs IMRIS - Trade Coordination - Rev. 10
-
01/26→01/30
·
Fire/Sprinkler
Level 2 - Perimeter Firestopping
FSP-1000 Level 2 - Perimeter Firestopping Firestopping
-
01/26→05/01
·
Flooring/Finishes
Metal Lockers - Fab/Deliver
DIV-10-210 Metal Lockers - Fab/Deliver Lockers
-
01/26→04/06
·
Flooring/Finishes
Millwork/Casework Lv-1 - Submittal
DIV-09-5-540 Millwork/Casework Lv-1 - Submittal Millwork/Casework Lv-1
-
01/26→05/01
·
Flooring/Finishes
Millwork/Casework Lv-10 - Fab & Deliver
DIV-09-10-120 Millwork/Casework Lv-10 - Fab & Deliver Millwork/Casework Lv-10
-
01/26→05/01
·
Flooring/Finishes
Millwork/Casework Lv-2- Fab & Deliver
DIV-09-1-120 Millwork/Casework Lv-2- Fab & Deliver Millwork/Casework Lv-2
-
01/26→05/01
·
Flooring/Finishes
Millwork/Casework Lv-3 - Fab & Deliver
DIV-09-3-320 Millwork/Casework Lv-3 - Fab & Deliver Millwork/Casework Lv-3
-
01/26→05/01
·
Flooring/Finishes
Millwork/Casework Lv-4 - Fab & Deliver
DIV-09-4-420 Millwork/Casework Lv-4 - Fab & Deliver Millwork/Casework Lv-4
-
01/26→05/01
·
Flooring/Finishes
Millwork/Casework Lv-9 - Fab & Deliver
DIV-09-9-920 Millwork/Casework Lv-9 - Fab & Deliver Millwork/Casework Lv-9
-
01/26→02/02
10
Other
Strip - Level 10, Pour 54 (2 day cure Drop & Reshore)
DP54-1050 Strip - Level 10, Pour 54 (2 day cure Drop & Reshore) Pour 54 (3)
-
01/26→02/02
10
Other
Strip - Level 10, Pour 55 (2 day cure Drop & Reshore)
DP55-1050 Strip - Level 10, Pour 55 (2 day cure Drop & Reshore) Pour 55 (4)
-
Mon 01/26
11
Concrete/Structure
Elevated Slab - Level 11, Pour 59 (4)
DP59-1040 Elevated Slab - Level 11, Pour 59 (4) Pour 59 (4)
-
01/26→01/30
11
Other
Strip - Level 11, Pour 56 (2 day cure Drop & Reshore)
DP56-1050 Strip - Level 11, Pour 56 (2 day cure Drop & Reshore) Pour 56 (1)
-
01/26→01/30
11
Other
Strip - Level 11, Pour 57 (2 day cure Drop & Reshore)
DP57-1050 Strip - Level 11, Pour 57 (2 day cure Drop & Reshore) Pour 57 (2)
-
01/26→02/02
11
Other
Strip - Level 11, Pour 58 (2 day cure Drop & Reshore)
DP58-1050 Strip - Level 11, Pour 58 (2 day cure Drop & Reshore) Pour 58 (3)
-
01/26→01/28
12
Other
FRP Deck - Level 12 Pour 61 (2)
DP61-1010 FRP Deck - Level 12 Pour 61 (2) Pour 61 (2)
-
01/26→01/27
12
Concrete/Structure
Rebar - Level 12 Pour 60
DP60-1030 Rebar - Level 12 Pour 60 Pour 60 (1)
-
01/26→01/30
1B
Other
Back Fill Area To Sub Grade
SC1B-N1-IR-340 Floor 1B - Back Fill Area To Sub Grade Floor 1B SC 1.N2 Overhead & Finishes
-
01/26→02/20
2
Other
Erect Podium Scaffolding (90 Cal. Days After Level 6 Poured)
EXT2-190 Floor 02 - Erect Podium Scaffolding (90 Cal. Days After Level 6 Poured) 2nd Floor
-
01/26→02/04
2
Drywall/Framing
N2501 - Hang/Tape/Finish Wall Board
2-TEL-405 Floor 2 - N2501 - Hang/Tape/Finish Wall Board Telecom Room Lv-2 N2501 MDF
-
Mon 01/26
2
Concrete/Structure
N2503 - Seal Concrete Floor
2-TEL-530 Floor 2 - N2503 - Seal Concrete Floor Telecom Room Lv-2 N2503
-
Mon 01/26
2
Concrete/Structure
N2504 - Seal Concrete Floor
2-TEL-230 Floor 2 - N2504 - Seal Concrete Floor Telecom Room Lv-2 N2504
-
01/26→01/28
2A
Inspections/QC
In-Wall Gilbane QC
SC2A-N2-IR-140 Floor 2A - In-Wall Gilbane QC Floor 2A SC 2.N2 Sterile
-
01/26→01/30
2A
HVAC/Mechanical
N2506 - AHU Drops/Duct Connections AHU 2-2
2A2A-N2-M-120 Floor 2A - N2506 - AHU Drops/Duct Connections AHU 2-2 Floor 2A AHU 2-2 SC 2.N2 Mechanical Space N2506 Sterile
-
01/26→01/30
2A
HVAC/Mechanical
N2506 - AHU Drops/Piping Connections AHU 2-2
2A2A-N2-M-110 Floor 2A - N2506 - AHU Drops/Piping Connections AHU 2-2 Floor 2A AHU 2-2 SC 2.N2 Mechanical Space N2506 Sterile
-
01/26→01/30
2A
HVAC/Mechanical
N2509 - AHU Drops/Duct Connections AHU 2-1
2C2C-N1-M-320 Floor 2A - N2509 - AHU Drops/Duct Connections AHU 2-1 Floor 2A AHU 2-1 SC 2.N1 Mechanical Space N2509 SPD
-
01/26→01/30
2A
HVAC/Mechanical
N2509 - AHU Drops/Piping Connections AHU 2-1
2C2C-N1-M-310 Floor 2A - N2509 - AHU Drops/Piping Connections AHU 2-1 Floor 2A AHU 2-1 SC 2.N1 Mechanical Space N2509 SPD
-
01/26→01/27
2A
Inspections/QC
OH Gilbane QC
SC2A-N2-IR-260 Floor 2A - OH Gilbane QC Floor 2A SC 2.N2 Sterile
-
01/26→02/06
2B
Electrical
2C - N2502 - Pull & Terminate Feeders
ELC-2-140 Floor 2B-2C - N2502 - Pull & Terminate Feeders Electrical Room Lv-2 N2502 2B, 2C
-
01/26→01/27
2B
Inspections/QC
OH Gilbane QC
SC2B-N3-IR-240 Floor 2B - OH Gilbane QC Floor 2B SC 2.N3
-
01/26→01/30
2C
Drywall/Framing
Frame Soffits/Hard Ceilings
SC2C-N1-IR-250 Floor 2C - Frame Soffits/Hard Ceilings Floor 2C SC 2.N1 In Wall Rough In
-
01/26→01/30
2C
HVAC/Mechanical
N2507 - AHU Drops/Duct Connections AJU 2-3
2C2C-N1-M-120 Floor 2C - N2507 - AHU Drops/Duct Connections AJU 2-3 Floor 2C AHU 2-3 SC 2.N1 Mechanical Space N2507 SPD
-
01/26→01/30
2C
HVAC/Mechanical
N2507 - AHU Drops/Piping Connections AHU 2-3
2C2C-N1-M-110 Floor 2C - N2507 - AHU Drops/Piping Connections AHU 2-3 Floor 2C AHU 2-3 SC 2.N1 Mechanical Space N2507 SPD
-
01/26→01/27
2C
Inspections/QC
OH Gilbane QC
SC2C-N1-IR-240 Floor 2C - OH Gilbane QC Floor 2C SC 2.N1 Framing & OH Rough In
-
01/26→02/20
2C
Electrical
Pull Branch Circuits
SC2C-N1-IR-300 Floor 2C - Pull Branch Circuits Floor 2C SC 2.N1 In Wall Rough In
-
01/26→02/20
3
Other
CEP Floor 3 - Install OH-Chilled Water (CHW) Hangers and Pipe
CEPN-M-3010 CEP Floor 3 - Install OH-Chilled Water (CHW) Hangers and Pipe Mechanical 3rd Flr (Chillers & Pumps)
-
01/26→01/30
3
Other
CEP Floor 3 - Layout
CEPN-3-3010 CEP Floor 3 - Layout Build-Out 3rd Flr
-
01/26→02/06
3
Plumbing
CEP Floor 3 - Sanitary/Storm
CEPN-3-3000 CEP Floor 3 - Sanitary/Storm Build-Out 3rd Flr
-
01/26→01/27
3
Flooring/Finishes
N3501 - Prime & 1st Finish Coat
TEL-3050 Floor 3 - N3501 - Prime & 1st Finish Coat Telecom Room Lv-3 N3501
-
01/26→02/06
3
Electrical
N3502 - Pull & Terminate Feeders
ELC-3-360 Floor 3 - N3502 - Pull & Terminate Feeders Electrical Room Lv-3 N3502 3B West, 3C
-
Mon 01/26
3
Flooring/Finishes
N3503 - Paint Plywood Back Boards
TEL-3-510 Floor 3 - N3503 - Paint Plywood Back Boards Telecom Room Lv-3 N3503
-
01/26→02/04
3
Drywall/Framing
N3504 - Hang/Tape/Finish Wall Board
TEL-3-420 Floor 3 - N3504 - Hang/Tape/Finish Wall Board Telecom Room Lv-3 N3204
-
Mon 01/26
3
Flooring/Finishes
N3504 - Paint Plywood Back Boards
TEL-3-490 Floor 3 - N3504 - Paint Plywood Back Boards Telecom Room Lv-3 N3504
-
01/26→02/06
3
Electrical
N3505 - Pull & Terminate Feeders
ELC-3-390 Floor 3 - N3505 - Pull & Terminate Feeders Electrical Room Lv-3 N3505 3A, 3B East
-
01/26→02/13
3A
Electrical
Install OH Cable Tray
SC3A-N2-IR-370 Floor 3A - Install OH Cable Tray Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
01/26→02/06
3A
Data
Low Voltage Rough-In Piping
SC3A-N2-F-100 Floor 3A - Low Voltage Rough-In Piping Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
01/26→02/04
3A
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC3A-N2-IR-330 Floor 3A - OH Sprinkler Rough In & QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
01/26→02/20
3B
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC3B-N3-IR-200 Floor 3B - OH Duct/VAV Boxes Rough-In/Insulation Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
01/26→02/04
3B
Ceilings
OR Modular Ceilings Layout
SC3B-N3-IR-120 Floor 3B - OR Modular Ceilings Layout Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
01/26→02/13
3C
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC3C-N1-IR-150 Floor 3C - In-Wall Electrical & I.T. Rough In & Control & QC Floor 3C SC 3.N1 Framing & Interior Roughs
-
01/26→02/20
3C
Electrical
OH Electrical & I.T. Rough In & QC
SC3C-N1-IR-230 Floor 3C - OH Electrical & I.T. Rough In & QC Floor 3C SC 3.N1 Overhead Roughs
-
01/26→01/30
4
Electrical
CEP Floor 4 - Electrical Equipment Pads
CEPN-4-4140 CEP Floor 4 - Electrical Equipment Pads Build-Out 4th Flr
-
01/26→02/06
4
Plumbing
CEP Floor 4 - Sanitary/Storm
CEPN-4-4000 CEP Floor 4 - Sanitary/Storm Build-Out 4th Flr
-
01/26→01/30
4
Other
Floor 4 (Gen& El. Rm.) - Install Panels
CEPN-E-4000 Floor 4 (Gen& El. Rm.) - Install Panels Electrical 4th floor (Generator & Main Electrical Rooms)
-
01/26→02/06
4A
Electrical
Install High OH Conduit Racks
SC4A-N2-IR-500 Floor 4A - Install High OH Conduit Racks Floor 4A SC 4.N2 Overhead Roughs
-
01/26→02/06
4A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
SC4A-N2-IR-330 Floor 4A - Med Gas Zone Valve Boxes/Terminations to Headwall Floor 4A SC 4.N2 Framing & Interior Roughs
-
01/26→02/13
4B
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC4B-N3-IR-110 Floor 4B - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
01/26→02/06
5B
Other
Layout Walls & Trade Penetrations
SC5B-N3-IR-100 Floor 5B - Layout Walls & Trade Penetrations Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
01/26→01/27
6
Other
Control Lines & Benchmarks
FL6-110 6th Floor - Control Lines & Benchmarks Floor 6
-
01/26→02/13
6
Concrete/Structure
Equipment Pads
FL6-100 6th Floor - Equipment Pads Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
01/26→01/27
7
Other
Control Lines & Benchmarks
FL7-N1-1000 Floor 7 - Control Lines & Benchmarks Floor 7
-
01/26→01/27
8
Other
Control Lines & Benchmarks
FL8-1000 Floor 8 - Control Lines & Benchmarks Floor 8
-
01/26→01/30
9
Other
Strip - Level 9, Pour 49 (2 day cure Drop & Reshore)
DP49-1050 Strip - Level 9, Pour 49 (2 day cure Drop & Reshore) Pour 49 (2)
-
01/26→02/20
CEP
Other
CEP - Install Junction Break Cabinets
CEP-E-1000 CEP - Install Junction Break Cabinets CEP-E Tie-In
-
01/26→01/27
CEP
Other
Prime & Torch Membrane (Includes 28 Day Cure)
CEPR-100 Prime & Torch Membrane (Includes 28 Day Cure) CEP Roof
-
01/27→02/09
·
Other
Wall & Door Protection - Review & Approval
DIV-10-170 Wall & Door Protection - Review & Approval Wall & Door Protection
-
01/27→01/29
11
Other
FRP Columns & Shearwalls - Level 11, Pour 58
DP58-1000 FRP Columns & Shearwalls - Level 11, Pour 58 Pour 58 (3)
-
01/27→02/24
11
Other
Level 11 Pour 58 (3) 28 Day Cure
DP59-1060 Level 11 Pour 58 (3) 28 Day Cure Pour 59 (4)
-
01/27→02/03
11
Other
Strip - Level 11, Pour 59 (2 day cure Drop & Reshore)
DP59-1050 Strip - Level 11, Pour 59 (2 day cure Drop & Reshore) Pour 59 (4)
-
01/27→02/02
2
Data
N2503 - Install Racks & Ladder Tray
2-TEL-350 Floor 2 - N2503 - Install Racks & Ladder Tray Telecom Room Lv-2 N2503
-
01/27→02/02
2
Data
N2504 - Install Racks & Ladder Tray
2-TEL-120 Floor 2 - N2504 - Install Racks & Ladder Tray Telecom Room Lv-2 N2504
-
01/27→01/28
2C
Inspections/QC
In-Wall Gilbane QC
SC2C-N1-IR-160 Floor 2C - In-Wall Gilbane QC Floor 2C SC 2.N1 In Wall Rough In
-
01/27→01/29
3
Electrical
N3503 - OH Conduit Rough-In
TEL-3-160 Floor 3 - N3503 - OH Conduit Rough-In Telecom Room Lv-3 N3503
-
01/27→01/29
3
Electrical
N3504 - OH Conduit Rough-In
TEL-3-170 Floor 3 - N3504 - OH Conduit Rough-In Telecom Room Lv-3 N3504
-
01/27→01/29
4
Concrete/Structure
Apply Weather Barrier at Header
4EXT-130 Floor 04 - Apply Weather Barrier at Header 4th Floor
-
01/27→01/29
6
Concrete/Structure
Fluid Applied Roofing At Sill Curbs
6EXT-180 Floor 06 - Fluid Applied Roofing At Sill Curbs 6th Floor
-
01/28→01/29
·
Concrete/Structure
Pour Steel Pan Stairs Level 1-4 Stair 27
ST27EL-125 Pour Steel Pan Stairs Level 1-4 Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
Wed 01/28
12
Concrete/Structure
Elevated Slab - Level 12, Pour 60 (1)
DP60-1040 Elevated Slab - Level 12, Pour 60 (1) Pour 60 (1)
-
01/28→01/30
12
Other
MEP Rough-In - Level 12, Pour 61
DP61-1020 MEP Rough-In - Level 12, Pour 61 Pour 61 (2)
-
01/28→01/29
2A
Inspections/QC
OH Inspections - MEPF
SC2A-N2-IR-280 Floor 2A - OH Inspections - MEPF Floor 2A SC 2.N2 Sterile
-
01/28→02/06
2A
Drywall/Framing
Soffits, Ceilings Framing & Gilbane QC
SC2A-N2-F-130 Floor 2A - Soffits, Ceilings Framing & Gilbane QC Floor 2A SC 2.N2 Final Finishes
-
01/28→01/29
2B
Inspections/QC
In-Wall Gilbane QC
SC2B-N3-IR-150 Floor 2B - In-Wall Gilbane QC Floor 2B SC 2.N3
-
01/28→01/29
2B
Inspections/QC
OH Inspections - MEPF
SC2B-N3-IR-260 Floor 2B - OH Inspections - MEPF Floor 2B SC 2.N3
-
01/28→02/10
2B
Data
Pull Wire For All Low Voltage Systems
SC2B-N3-F-160 Floor 2B - Pull Wire For All Low Voltage Systems Floor 2B SC 2.N3
-
01/28→02/05
2C
Drywall/Framing
Hang Drywall Ceilings
SC2C-N1-IR-310 Floor 2C - Hang Drywall Ceilings Floor 2C SC 2.N1 In Wall Rough In
-
01/28→01/29
2C
Inspections/QC
OH Inspections - MEPF
SC2C-N1-IR-260 Floor 2C - OH Inspections - MEPF Floor 2C SC 2.N1 Framing & OH Rough In
-
01/28→02/02
3
Other
N3501 - Install Plywood Back Boards
TEL-3040 Floor 3 - N3501 - Install Plywood Back Boards Telecom Room Lv-3 N3501
-
01/28→02/24
6
Electrical
Secondary OH Conduits 1
FL6-40 6th Floor - Secondary OH Conduits 1 Floor 6
-
01/28→02/10
7
Plumbing
OH Sanitary/Storm
FL7-N1-1100 Floor 7 - OH Sanitary/Storm Floor 7
-
01/28→02/24
8
Plumbing
OH Sanitary/Storm
FL8-1100 Floor 8 - OH Sanitary/Storm Floor 8
-
01/28→01/30
CEP
Other
Place & Finish LWIC
CEPR-110 Place & Finish LWIC CEP Roof
-
01/29→02/03
12
Other
FRP Deck - Level 12 Pour 62 (3)
DP62-1010 FRP Deck - Level 12 Pour 62 (3) Pour 62 (3)
-
01/29→02/02
12
Other
Strip - Level 12, Pour 60 (2 day cure Drop & Reshore)
DP60-1050 Strip - Level 12, Pour 60 (2 day cure Drop & Reshore) Pour 60 (1)
-
01/29→01/30
2A
Inspections/QC
In-Wall Inspections - MEPF
SC2A-N2-IR-160 Floor 2A - In-Wall Inspections - MEPF Floor 2A SC 2.N2 Sterile
-
01/29→01/30
2C
Inspections/QC
In-Wall Inspections - MEPF
SC2C-N1-IR-180 Floor 2C - In-Wall Inspections - MEPF Floor 2C SC 2.N1 In Wall Rough In
-
01/29→02/25
CEP
Other
Vendor Shop Drawing/Sample Prep
RFI-0820.30 Vendor Shop Drawing/Sample Prep RFI-0820 Generator Louver Revisions
-
01/30→02/03
11
Other
FRP Columns & Shearwalls - Level 11, Pour 59
DP59-1000 FRP Columns & Shearwalls - Level 11, Pour 59 Pour 59 (4)
-
01/30→02/02
12
Concrete/Structure
Rebar - Level 12 Pour 61
DP61-1030 Rebar - Level 12 Pour 61 Pour 61 (2)
-
01/30→02/02
2B
Inspections/QC
In-Wall Inspections - MEPF
SC2B-N3-IR-170 Floor 2B - In-Wall Inspections - MEPF Floor 2B SC 2.N3
-
01/30→02/04
3
Electrical
N3503 - Install Grounding Buss
TEL-3-180 Floor 3 - N3503 - Install Grounding Buss Telecom Room Lv-3 N3503
-
01/30→02/04
3
Electrical
N3504 - Install Grounding Buss
TEL-3-190 Floor 3 - N3504 - Install Grounding Buss Telecom Room Lv-3 N3504
-
01/30→02/02
3A
Plumbing
Med Gas Pre Certification
SC3A-N2-IR-360 Floor 3A - Med Gas Pre Certification Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
01/30→02/03
5
Concrete/Structure
Apply Weather Barrier at Header
5EXT-130 Floor 05 - Apply Weather Barrier at Header 5th Floor
-
01/30→02/03
6
Concrete/Structure
Layout for Box Beam Header
6EXT-100 Floor 06 - Layout for Box Beam Header 6th Floor
-
02/02→02/04
·
Other
IMRIS R10 - CT Vendor Kickoff + Equipment Coordination
REV10-1160 IMRIS R10 - CT Vendor Kickoff + Equipment Coordination IMRIS - Trade Coordination - Rev. 10
-
02/02→03/27
·
Other
IMRIS R10 - Fabricate (post-approval)
REV10-1250 IMRIS R10 - Fabricate (post-approval) IMRIS Procurement - Rev. 10
-
02/02→02/06
·
Fire/Sprinkler
Level 3 - Perimeter Firestopping
FSP-1010 Level 3 - Perimeter Firestopping Firestopping
-
02/02→05/08
·
Flooring/Finishes
Millwork/Casework Lv-11 - Fab & Deliver
DIV-09-11-130 Millwork/Casework Lv-11 - Fab & Deliver Millwork/Casework Lv-11
-
02/02→05/08
·
Flooring/Finishes
Millwork/Casework Lv-12 - Fab & Deliver
DIV-09-12-140 Millwork/Casework Lv-12 - Fab & Deliver Millwork/Casework Lv-12
-
02/02→05/08
·
Flooring/Finishes
Millwork/Casework Lv-13 - Fab & Deliver
DIV-09-13-150 Millwork/Casework Lv-13 - Fab & Deliver Millwork/Casework Lv-13
-
02/02→03/13
1B
Plumbing
UG Plumbing RI & Inspection
SC1B-N1-IR-350 Floor 1B - UG Plumbing RI & Inspection Floor 1B SC 1.N2 Overhead & Finishes
-
02/02→02/10
2A
HVAC/Mechanical
N2506 - BMS Controls AHU 2-2
2A2A-N2-M-130 Floor 2A - N2506 - BMS Controls AHU 2-2 Floor 2A AHU 2-2 SC 2.N2 Mechanical Space N2506 Sterile
-
02/02→02/13
2A
Electrical
N2506 - Install & Electronically Connect VFD's AHU 2-2
2A2A-N2-M-150 Floor 2A - N2506 - Install & Electronically Connect VFD's AHU 2-2 Floor 2A AHU 2-2 SC 2.N2 Mechanical Space N2506 Sterile
-
02/02→02/03
2A
HVAC/Mechanical
N2509 - BMS Controls AHU 2-1
2C2C-N1-M-330 Floor 2A - N2509 - BMS Controls AHU 2-1 Floor 2A AHU 2-1 SC 2.N1 Mechanical Space N2509 SPD
-
02/02→02/06
2C
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
SC2C-N1-F-110 Floor 2C - HVAC Drops & Diffusers in Soffit Floor 2C SC 2.N1 Final Finishes
-
02/02→02/10
2C
HVAC/Mechanical
N2507 - BMS Controls AHU 2-3
2C2C-N1-M-130 Floor 2C - N2507 - BMS Controls AHU 2-3 Floor 2C AHU 2-3 SC 2.N1 Mechanical Space N2507 SPD
-
02/02→02/04
3
Drywall/Framing
CEP Floor 3 - Frame Walls & Hang Top Board
CEPN-3-3020 CEP Floor 3 - Frame Walls & Hang Top Board Build-Out 3rd Flr
-
02/02→02/06
4
Other
CEP Floor 4 - Layout
CEPN-4-4020 CEP Floor 4 - Layout Build-Out 4th Flr
-
02/02→02/13
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders Panels
CEPN-E-4010 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders Panels Electrical 4th floor (Generator & Main Electrical Rooms)
-
02/02→02/20
6
Electrical
6th Floor N6503 - Normal Power C Conduit Rough-In
WN6-1000 6th Floor N6503 - Normal Power C Conduit Rough-In West Normal - N6503 USS 6NNA
-
02/02→02/20
6
Electrical
6th Floor N6507 - Normal Power B Conduit Rough-In
EN6-1000 6th Floor N6507 - Normal Power B Conduit Rough-In East Normal - N6507 USS 6NNB
-
02/02→02/06
CEP
Concrete/Structure
Install Roofing & Flashing
CEPR-120 Install Roofing & Flashing CEP Roof
-
02/03→02/06
·
Other
Bridge - Place and Pour Deck 2
BRIDGE-180 Bridge - Place and Pour Deck 2 New Bridge
-
Tue 02/03
12
Concrete/Structure
Elevated Slab - Level 12, Pour 61 (2)
DP61-1040 Elevated Slab - Level 12, Pour 61 (2) Pour 61 (2)
-
02/03→02/06
12
Other
MEP Rough-In - Level 12, Pour 62
DP62-1020 MEP Rough-In - Level 12, Pour 62 Pour 62 (3)
-
02/03→02/09
2
Data
N2504 - Pull LV Riser Cable
2-TEL-110 Floor 2 - N2504 - Pull LV Riser Cable Telecom Room Lv-2 N2504
-
02/03→02/04
2B
Drywall/Framing
Framing Inspections
SC2B-N3-F-150 Floor 2B - Framing Inspections Floor 2B SC 2.N3
-
Tue 02/03
3
Flooring/Finishes
N3501 - Paint Plywood Back Boards
TEL-3060 Floor 3 - N3501 - Paint Plywood Back Boards Telecom Room Lv-3 N3501
-
02/04→02/06
12
Other
FRP Columns & Shearwalls - Level 12, Pour 60
DP60-1000 FRP Columns & Shearwalls - Level 12, Pour 60 Pour 60 (1)
-
02/04→02/09
12
Other
FRP Deck - Level 12 Pour 63 (4)
DP63-1010 FRP Deck - Level 12 Pour 63 (4) Pour 63 (4)
-
02/04→02/10
12
Other
Strip - Level 12, Pour 61 (2 day cure Drop & Reshore)
DP61-1050 Strip - Level 12, Pour 61 (2 day cure Drop & Reshore) Pour 61 (2)
-
02/04→02/06
3
Electrical
N3501 - OH Conduit Rough-In
TEL-3110 Floor 3 - N3501 - OH Conduit Rough-In Telecom Room Lv-3 N3501
-
02/04→02/06
6
Concrete/Structure
Apply Weather Barrier at Header
6EXT-130 Floor 06 - Apply Weather Barrier at Header 6th Floor
-
02/05→02/18
·
Other
IMRIS R10 - MEP Clash Detection / BIM Coordination Cycle 1
REV10-1170 IMRIS R10 - MEP Clash Detection / BIM Coordination Cycle 1 IMRIS - Trade Coordination - Rev. 10
-
02/05→02/09
12
Concrete/Structure
Rebar - Level 12 Pour 62
DP62-1030 Rebar - Level 12 Pour 62 Pour 62 (3)
-
02/05→02/06
2
Flooring/Finishes
N2501 - Paint Wall Board
2-TEL-415 Floor 2 - N2501 - Paint Wall Board Telecom Room Lv-2 N2501 MDF
-
02/05→02/18
3
Electrical
CEP Floor 3 - Branch Circuits Conduit
CEPN-3-3050 CEP Floor 3 - Branch Circuits Conduit Build-Out 3rd Flr
-
02/05→02/09
3
Electrical
CEP Floor 3 - In Wall Electrical Rough
CEPN-3-3070 CEP Floor 3 - In Wall Electrical Rough Build-Out 3rd Flr
-
02/05→02/11
3
HVAC/Mechanical
CEP Floor 3 - Mechanical Equipment Pads
CEPN-3-3080 CEP Floor 3 - Mechanical Equipment Pads Build-Out 3rd Flr
-
02/05→02/18
3
Electrical
CEP Floor 3 - OH-Electrical Rough/Racks Systems
CEPN-3-3040 CEP Floor 3 - OH-Electrical Rough/Racks Systems Build-Out 3rd Flr
-
Thu 02/05
3
Concrete/Structure
N3503 - Seal Concrete Floor
TEL-3-520 Floor 3 - N3503 - Seal Concrete Floor Telecom Room Lv-3 N3503
-
02/05→02/06
3
Flooring/Finishes
N3504 - Prime & 1st Finish Coat
TEL-3-410 Floor 3 - N3504 - Prime & 1st Finish Coat Telecom Room Lv-3 N3204
-
Thu 02/05
3
Concrete/Structure
N3504 - Seal Concrete Floor
TEL-3-500 Floor 3 - N3504 - Seal Concrete Floor Telecom Room Lv-3 N3504
-
02/05→03/04
3B
Ceilings
Install Prefab Structural Steel Support For OR Ceilings (B-I Install)
SC3B-N3-IR-130 Floor 3B - Install Prefab Structural Steel Support For OR Ceilings (B-I Install) Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
02/05→02/09
4
Drywall/Framing
CEP Floor 4 - Frame Walls & Hang Top Board
CEPN-4-4010 CEP Floor 4 - Frame Walls & Hang Top Board Build-Out 4th Flr
-
Thu 02/05
5C
Milestone
Frame Interior Walls ◆
M580 Floor 5C - Frame Interior Walls Construction Milestones
-
02/06→02/19
2
Other
Floor 2 C - In Wall MEPF Rough In
GBW-370 Floor 2 C - In Wall MEPF Rough In Floor 2 Go Back Work
-
02/06→02/12
3
Data
N3503 - Install Racks & Ladder Tray
TEL-3-200 Floor 3 - N3503 - Install Racks & Ladder Tray Telecom Room Lv-3 N3503
-
02/06→02/12
3
Data
N3504 - Install Racks & Ladder Tray
TEL-3-210 Floor 3 - N3504 - Install Racks & Ladder Tray Telecom Room Lv-3 N3504
-
02/06→03/05
6
Plumbing
OH Sanitary/Storm
FL6-30 6th Floor - OH Sanitary/Storm Floor 6
-
02/09→02/13
·
Other
Bridge - Place and pour Deck 3
BRIDGE-190 Bridge - Place and pour Deck 3 New Bridge
-
02/09→05/15
·
Flooring/Finishes
Millwork/Casework Lv-5 - Fab & Deliver
DIV-09-5-520 Millwork/Casework Lv-5 - Fab & Deliver Millwork/Casework Lv-5
-
02/09→02/11
12
Other
FRP Columns & Shearwalls - Level 12, Pour 61
DP61-1000 FRP Columns & Shearwalls - Level 12, Pour 61 Pour 61 (2)
-
02/09→02/12
2
Other
N2501 - Install Plywood Back Boards
2-TEL-425 Floor 2 - N2501 - Install Plywood Back Boards Telecom Room Lv-2 N2501 MDF
-
02/09→02/10
2A
Drywall/Framing
Framing Inspections
SC2A-N2-F-150 Floor 2A - Framing Inspections Floor 2A SC 2.N2 Sterile
-
02/09→02/20
2A
Electrical
N2505 - Pull & Terminate Feeders
E-2-110 Floor 2A - N2505 - Pull & Terminate Feeders Electrical Room Lv-2 N2505 2A
-
02/09→03/06
2B
Electrical
Pull Branch Circuits
SC2B-N3-IR-220 Floor 2B - Pull Branch Circuits Floor 2B SC 2.N3
-
02/09→02/13
2C
Drywall/Framing
Framing Inspections
SC2C-N1-F-150 Floor 2C - Framing Inspections Floor 2C SC 2.N1 In Wall Rough In
-
02/09→02/13
3
Data
CEP Floor 3 - OH-Low Voltage Rough
CEPN-3-3060 CEP Floor 3 - OH-Low Voltage Rough Build-Out 3rd Flr
-
02/09→02/20
3
Drywall/Framing
Floor 3 North - Layout, Frame & Insulate Walls
GBW-450 Floor 3 North - Layout, Frame & Insulate Walls Floor 3 Go Back Work
-
02/09→02/12
3
Electrical
N3501 - Install Grounding Buss
TEL-3030 Floor 3 - N3501 - Install Grounding Buss Telecom Room Lv-3 N3501
-
02/09→02/12
3
Other
N3504 - Install Plywood Back Boards
TEL-3-400 Floor 3 - N3504 - Install Plywood Back Boards Telecom Room Lv-3 N3204
-
02/09→02/13
3A
Inspections/QC
In-Wall Gilbane QC
SC3A-N2-IR-160 Floor 3A - In-Wall Gilbane QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/09→03/06
3B
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC3B-N3-IR-230 Floor 3B - OH HVAC Piping/Controls/Insulation & QC Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
02/09→03/06
3B
Plumbing
OH Plumbing Rough In/Insulation & QC
SC3B-N3-IR-210 Floor 3B - OH Plumbing Rough In/Insulation & QC Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
02/09→02/10
4
Flooring/Finishes
Floor 4 N4505 - Prime & 1st Finish Coat
ELC-4-150 Floor 4 N4505 - Prime & 1st Finish Coat Electrical Room Lv-4 N4505 4A East, 4B East
-
02/09→02/10
4A
Plumbing
Med Gas Pre Certification
SC4A-N2-IR-350 Floor 4A - Med Gas Pre Certification Floor 4A SC 4.N2 Framing & Interior Roughs
-
02/09→03/06
4A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC4A-N2-IR-230 Floor 4A - OH HVAC Piping/Controls/Insulation & QC Floor 4A SC 4.N2 Overhead Roughs
-
02/09→02/20
4B
Electrical
Install High OH Conduit Racks
SC4B-N1-IR-520 Floor 4B - Install High OH Conduit Racks Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
02/09→02/20
4C
Electrical
Install High OH Conduit Racks
SC4C-N1-IR-510 Floor 4C - Install High OH Conduit Racks Floor 4C SC 4.N1 Overhead Roughs
-
02/09→02/27
6
Other
Layout Walls & Trade Penetrations
FL6-10 6th Floor - Layout Walls & Trade Penetrations Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
02/09→03/04
CEP
Concrete/Structure
Rev.7 CEP - Erect REV. 7 Plenum Support Steel
REV7-CEPPL-100 Rev.7 CEP - Erect REV. 7 Plenum Support Steel Rev.7 CEP Plenum Duct
-
02/10→05/18
·
Other
Wall & Door Protection - Fab/Deliver
DIV-10-200 Wall & Door Protection - Fab/Deliver Wall & Door Protection
-
Tue 02/10
12
Concrete/Structure
Elevated Slab - Level 12, Pour 62 (3)
DP62-1040 Elevated Slab - Level 12, Pour 62 (3) Pour 62 (3)
-
02/10→02/13
12
Other
MEP Rough-In - Level 12, Pour 63
DP63-1020 MEP Rough-In - Level 12, Pour 63 Pour 63 (4)
-
02/10→02/12
13
Other
FRP Deck - Level 13 Pour 64 (1)
DP64-1010 FRP Deck - Level 13 Pour 64 (1) Pour 64 (1)
-
Tue 02/10
2
Data
N2504 - Install I. T. Rooms Doors
2-TEL-170 Floor 2 - N2504 - Install I. T. Rooms Doors Telecom Room Lv-2 N2504
-
Tue 02/10
3
Inspections/QC
CEP Floor 3 - In Wall Inspections MEPF
CEPN-3-3110 CEP Floor 3 - In Wall Inspections MEPF Build-Out 3rd Flr
-
02/10→02/23
3
HVAC/Mechanical
CEP Floor 3 - OH Duct/VAV Boxes Rough-In/Insulation
CEPN-3-3100 CEP Floor 3 - OH Duct/VAV Boxes Rough-In/Insulation Build-Out 3rd Flr
-
02/10→02/12
4
Electrical
CEP Floor 4 - In Wall Electrical Rough
CEPN-4-4060 CEP Floor 4 - In Wall Electrical Rough Build-Out 4th Flr
-
02/10→03/23
4
Other
CEP Floor 4 - Medium Voltage Rough
CEPN-4-4040 CEP Floor 4 - Medium Voltage Rough Build-Out 4th Flr
-
02/10→02/16
4
Data
CEP Floor 4 -OH-Low Voltage Rough
CEPN-4-4080 CEP Floor 4 -OH-Low Voltage Rough Build-Out 4th Flr
-
02/11→02/18
12
Other
Strip - Level 12, Pour 62 (2 day cure Drop & Reshore)
DP62-1050 Strip - Level 12, Pour 62 (2 day cure Drop & Reshore) Pour 62 (3)
-
02/11→02/24
2
Drywall/Framing
Floor 2 B - Layout, Frame & Insulate Walls
GBW-390 Floor 2 B - Layout, Frame & Insulate Walls Floor 2 Go Back Work
-
02/11→03/03
2A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC2A-N2-F-170 Floor 2A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 2A SC 2.N2 Final Finishes
-
02/11→02/17
3
Drywall/Framing
CEP Floor 3 - Hang Drywall
CEPN-3-3210 CEP Floor 3 - Hang Drywall Build-Out 3rd Flr
-
02/11→03/10
4
Electrical
Floor 4 (Gen& El. Rm.) - Install Generators
CEPN-E-4050 Floor 4 (Gen& El. Rm.) - Install Generators Electrical 4th floor (Generator & Main Electrical Rooms)
-
02/11→03/03
4
Other
Floor 4 (Gen& El. Rm.) - Install Paralleling Gear Side A (EPSS-N)
CEPN-E-4030 Floor 4 (Gen& El. Rm.) - Install Paralleling Gear Side A (EPSS-N) Electrical 4th floor (Generator & Main Electrical Rooms)
-
02/11→02/12
4
Flooring/Finishes
Floor 4 N4502 - Prime & 1st Finish Coat
ELC-4-110 Floor 4 N4502 - Prime & 1st Finish Coat Electrical Room Lv-4 N4502 4A West, 4C
-
02/11→02/20
4
Drywall/Framing
Floor 4 N4503 - Hang/Tape/Finish Wall Board
TEL-4-100 Floor 4 N4503 - Hang/Tape/Finish Wall Board Telecom Room Lv-4 N4503
-
02/11→02/17
4
Electrical
Floor 4 N4505 - Install Electrical Panels/Equipment
ELC-4-160 Floor 4 N4505 - Install Electrical Panels/Equipment Electrical Room Lv-4 N4505 4A East, 4B East
-
02/11→03/10
4A
Plumbing
OH Plumbing Rough In/Insulation & QC
SC4A-N2-IR-220 Floor 4A - OH Plumbing Rough In/Insulation & QC Floor 4A SC 4.N2 Overhead Roughs
-
02/12→02/16
12
Other
FRP Columns & Shearwalls - Level 12, Pour 62
DP62-1000 FRP Columns & Shearwalls - Level 12, Pour 62 Pour 62 (3)
-
02/12→02/16
12
Concrete/Structure
Rebar - Level 12 Pour 63
DP63-1030 Rebar - Level 12 Pour 63 Pour 63 (4)
-
02/12→02/25
3
HVAC/Mechanical
CEP Floor 3 - OH HVAC Piping/Controls/Insulation & QC
CEPN-3-3090 CEP Floor 3 - OH HVAC Piping/Controls/Insulation & QC Build-Out 3rd Flr
-
02/12→03/25
3B
Ceilings
OR Modular Prefab Ceilings Install Clean Suite (B-I Install)
SC3B-N3-IR-300 Floor 3B - OR Modular Prefab Ceilings Install Clean Suite (B-I Install) Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
02/12→02/23
5
Drywall/Framing
Floor 5 N5503 - Hang/Tape/Finish Wall Board
TEL-5-100 Floor 5 N5503 - Hang/Tape/Finish Wall Board Telecom Room Lv-5 N5503
-
02/12→02/13
5
Flooring/Finishes
Floor 5 N5505 - Prime & 1st Finish Coat
ELC-5-130 Floor 5 N5505 - Prime & 1st Finish Coat Electrical Room Lv-5 N5505 5A,5B East
-
02/12→02/25
5A
Other
Install Pre-Fab Headwalls
SC5A-N2-IR-260 Floor 5A - Install Pre-Fab Headwalls Floor 5A SC 5.N2raming & Interior Roughs
-
02/12→03/04
5C
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC5C-N1-IR-110 Floor 5C - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 5C SC 5.N1 Overhead Roughs
-
02/13→02/17
13
Other
FRP Deck - Level 13 Pour 65 (2)
DP65-1010 FRP Deck - Level 13 Pour 65 (2) Pour 65 (2)
-
02/13→02/17
13
Other
MEP Rough-In - Level 13,Pour 64
DP64-1030 MEP Rough-In - Level 13,Pour 64 Pour 64 (1)
-
Fri 02/13
2
Flooring/Finishes
N2501 - Paint Plywood Back Boards
2-TEL-435 Floor 2 - N2501 - Paint Plywood Back Boards Telecom Room Lv-2 N2501 MDF
-
Fri 02/13
3
Concrete/Structure
N3501 - Seal Concrete Floor
TEL-3130 Floor 3 - N3501 - Seal Concrete Floor Telecom Room Lv-3 N3501
-
Fri 02/13
3
Flooring/Finishes
N3504 - Paint Plywood Back Boards
TEL-3-530 Floor 3 - N3504 - Paint Plywood Back Boards Telecom Room Lv-3 N3204
-
Fri 02/13
4
Inspections/QC
CEP Floor 4 - In Wall Inspections - MEPF
CEPN-4-4090 CEP Floor 4 - In Wall Inspections - MEPF Build-Out 4th Flr
-
02/13→02/26
4
HVAC/Mechanical
CEP Floor 4 -OH Duct/VAV Boxes Rough-In/Insulation
CEPN-4-4070 CEP Floor 4 -OH Duct/VAV Boxes Rough-In/Insulation Build-Out 4th Flr
-
02/13→02/26
4
HVAC/Mechanical
CEP Floor 4 -OH HVAC Piping/Controls/Insulation & QC
CEPN-4-4100 CEP Floor 4 -OH HVAC Piping/Controls/Insulation & QC Build-Out 4th Flr
-
02/13→02/19
4
Electrical
Floor 4 N4502 - Install Electrical Panels/Equipment
ELC-4-140 Floor 4 N4502 - Install Electrical Panels/Equipment Electrical Room Lv-4 N4502 4A West, 4C
-
02/13→02/24
4
Drywall/Framing
Floor 4 N4504 - Hang/Tape/Finish Wall Board
TEL-4-120 Floor 4 N4504 - Hang/Tape/Finish Wall Board Telecom Room Lv-4 N4504
-
02/16→02/27
·
Electrical
Bridge - Install Conduits For Data & Low Voltage (Underside Deck 2)
BRIDGE-210 Bridge - Install Conduits For Data & Low Voltage (Underside Deck 2) New Bridge
-
02/16→02/17
·
Other
Bridge - Set Up Building Control
BRIDGE-200 Bridge - Set Up Building Control New Bridge
-
02/16→02/24
·
Concrete/Structure
Install Precast Panels Level 1-6 (Set 2 WS)
SW-710 Install Precast Panels Level 1-6 (Set 2 WS) Precast
-
02/16→03/13
·
Concrete/Structure
Install Scaffold For CMU 1-5 Stair 26
STR-28-120 Install Scaffold For CMU 1-5 Stair 26 CMU Stairs 26 & 28
-
02/16→02/18
2
Electrical
N2501 - OH Conduit Rough-In
2-TEL-430 Floor 2 - N2501 - OH Conduit Rough-In Telecom Room Lv-2 N2501 MDF
-
02/16→02/27
2A
Electrical
N2509 - Install & Electronically Connect VFD's AHU 2-1
2C2C-N1-M-350 Floor 2A - N2509 - Install & Electronically Connect VFD's AHU 2-1 Floor 2A AHU 2-1 SC 2.N1 Mechanical Space N2509 SPD
-
02/16→02/20
3
Data
N3501 - Install Racks & Ladder Tray
TEL-3020 Floor 3 - N3501 - Install Racks & Ladder Tray Telecom Room Lv-3 N3501
-
02/16→02/18
3
Electrical
N3504 - OH Conduit Rough-In
TEL-3-470 Floor 3 - N3504 - OH Conduit Rough-In Telecom Room Lv-3 N3204
-
02/16→02/17
3A
Inspections/QC
In-Wall Inspections - MEPF
SC3A-N2-IR-180 Floor 3A - In-Wall Inspections - MEPF Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/16→03/13
3A
Electrical
Pull Branch Circuits
SC3A-N2-IR-240 Floor 3A - Pull Branch Circuits Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/16→03/06
3A
Data
Pull Wire For All Low Voltage Systems
SC3A-N2-F-140 Floor 3A - Pull Wire For All Low Voltage Systems Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/16→03/13
3B
Electrical
In-Wall Electrical & I.T. Rough In, Controls & QC
SC3B-N3-IR-160 Floor 3B - In-Wall Electrical & I.T. Rough In, Controls & QC Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
02/16→02/20
3C
Inspections/QC
In-Wall Gilbane QC
SC3C-N1-IR-160 Floor 3C - In-Wall Gilbane QC Floor 3C SC 3.N1 Framing & Interior Roughs
-
02/16→03/06
3C
Electrical
Install OH Cable Tray
3C3C-N1-IR-500 Floor 3C - Install OH Cable Tray Floor 3C SC 3.N1 Overhead Roughs
-
02/16→03/13
4A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC4A-N2-IR-130 Floor 4A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 4A SC 4.N2 Framing & Interior Roughs
-
02/16→03/13
4A
Plumbing
OH & In Wall MED Gas Rough In & QC
SC4A-N2-IR-200 Floor 4A - OH & In Wall MED Gas Rough In & QC Floor 4A SC 4.N2 Overhead Roughs
-
02/16→03/06
4B
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC4B-N3-IR-130 Floor 4B - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
02/16→02/20
4B
Ceilings
OR Modular Ceilings Layout
SC4B-N3-IR-120 Floor 4B - OR Modular Ceilings Layout Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
02/16→03/13
4C
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC4C-N1-IR-190 Floor 4C - OH Duct/VAV Boxes Rough-In/Insulation Floor 4C SC 4.N1 Overhead Roughs
-
02/16→02/25
5
Drywall/Framing
Floor 5 N5501 - Hang/Tape/Finish Wall Board
TEL-5-460 Floor 5 N5501 - Hang/Tape/Finish Wall Board Telecom Room Lv-5 N5501
-
02/16→02/25
5
Drywall/Framing
Floor 5 N5504 - Hang/Tape/Finish Wall Board
TEL-5-120 Floor 5 N5504 - Hang/Tape/Finish Wall Board Telecom Room Lv-5 N5504
-
02/16→02/20
5
Electrical
Floor 5 N5505 - Install Electrical Panels/Equipment
ELC-5-170 Floor 5 N5505 - Install Electrical Panels/Equipment Electrical Room Lv-5 N5505 5A,5B East
-
02/16→03/06
5B
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
SC5B-N3-IR-110 Floor 5B - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
02/17→03/02
·
Flooring/Finishes
Interior Signage - Review & Approval (Revise/Resubmit)
DIV-10-230 Interior Signage - Review & Approval (Revise/Resubmit) Interior Signage
-
Tue 02/17
12
Concrete/Structure
Elevated Slab - Level 12, Pour 63 (3)
DP63-1040 Elevated Slab - Level 12, Pour 63 (3) Pour 63 (4)
-
02/17→02/18
13
Concrete/Structure
Rebar - Level 13 Pour 64
DP64-1020 Rebar - Level 13 Pour 64 Pour 64 (1)
-
02/17→02/26
4
Drywall/Framing
Floor 4 N4501 - Hang/Tape/Finish Wall Board
TEL-4-400 Floor 4 N4501 - Hang/Tape/Finish Wall Board Telecom Room Lv-4 N4501
-
02/18→02/20
12
Other
FRP Columns & Shearwalls - Level 12, Pour 63
DP63-1000 FRP Columns & Shearwalls - Level 12, Pour 63 Pour 63 (4)
-
02/18→03/18
12
Other
Level 12 Pour 63 (4) 28 Day Cure
DP63-1060 Level 12 Pour 63 (4) 28 Day Cure Pour 63 (4)
-
02/18→02/25
12
Other
Strip - Level 12, Pour 63 (2 day cure Drop & Reshore)
DP63-1050 Strip - Level 12, Pour 63 (2 day cure Drop & Reshore) Pour 63 (4)
-
02/18→02/24
13
Other
FRP Deck - Level 13 Pour 66 (3)
DP66-2010 FRP Deck - Level 13 Pour 66 (3) Pour 66 (3)
-
02/18→02/20
13
Other
MEP Rough-In - Level 13, Pour 65
DP65-1020 MEP Rough-In - Level 13, Pour 65 Pour 65 (2)
-
02/18→03/10
2A
Drywall/Framing
Finish Drywall
SC2A-N2-F-220 Floor 2A - Finish Drywall Floor 2A SC 2.N2 Final Finishes
-
02/18→02/24
2C
Electrical
Electrical Rough in Soffit
SC2C-N1-F-120 Floor 2C - Electrical Rough in Soffit Floor 2C SC 2.N1 Final Finishes
-
02/18→02/25
3
Drywall/Framing
CEP Floor 3 - Finish Drywall
CEPN-3-3220 CEP Floor 3 - Finish Drywall Build-Out 3rd Flr
-
02/18→03/03
3A
Drywall/Framing
Blocking/Backing/Plywood
SC3A-N2-IR-250 Floor 3A - Blocking/Backing/Plywood Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/18→02/24
4
Drywall/Framing
CEP Floor 4 - Hang Drywall
CEPN-4-4220 CEP Floor 4 - Hang Drywall Build-Out 4th Flr
-
02/18→03/03
4
Electrical
Floor 4 N4505 - Pull & Terminate Feeders
ELC-4-200 Floor 4 N4505 - Pull & Terminate Feeders Electrical Room Lv-4 N4505 4A East, 4B East
-
02/19→02/25
·
Other
IMRIS R10 - RF Shielding Coordination (Vendor + GBC)
REV10-1180 IMRIS R10 - RF Shielding Coordination (Vendor + GBC) IMRIS - Trade Coordination - Rev. 10
-
02/19→03/04
·
Concrete/Structure
Install CMU Scaffold Support Deck Level 6 Stair 28
STR-26-240 Install CMU Scaffold Support Deck Level 6 Stair 28 CMU Stairs 26 & 28
-
02/19→02/25
·
Concrete/Structure
Install Steel Pan Stairs Levels 1-4 Stair 28
ST26W-305 Install Steel Pan Stairs Levels 1-4 Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
Thu 02/19
13
Concrete/Structure
Elevated Slab - Level 13, Pour 64 (1)
DP64-1040 Elevated Slab - Level 13, Pour 64 (1) Pour 64 (1)
-
02/19→02/24
2
Electrical
N2501 - Install Grounding Buss
2-TEL-440 Floor 2 - N2501 - Install Grounding Buss Telecom Room Lv-2 N2501 MDF
-
02/19→03/18
3
Electrical
CEP Floor 3 - Pull Branch Circuits
CEPN-3-3120 CEP Floor 3 - Pull Branch Circuits Build-Out 3rd Flr
-
02/19→02/24
3
Electrical
N3504 - Install Grounding Buss
TEL-3-390 Floor 3 - N3504 - Install Grounding Buss Telecom Room Lv-3 N3204
-
02/20→02/23
13
Concrete/Structure
Rebar - Level 13 Pour 65
DP65-1030 Rebar - Level 13 Pour 65 Pour 65 (2)
-
02/20→02/26
13
Other
Strip - Level 13, Pour 64 (2 day cure Drop & Reshore)
DP64-1050 Strip - Level 13, Pour 64 (2 day cure Drop & Reshore) Pour 64 (1)
-
02/20→03/19
2
Other
Floor 2 C - OH MEPF Rougth In
GBW-210 Floor 2 C - OH MEPF Rougth In Floor 2 Go Back Work
-
02/20→03/05
4
Electrical
Floor 4 N4502 - Pull & Terminate Feeders
ELC-4-170 Floor 4 N4502 - Pull & Terminate Feeders Electrical Room Lv-4 N4502 4A West, 4C
-
02/23→02/25
13
Other
FRP Columns & Shearwalls - Level 13, Pour 64
DP64-1000 FRP Columns & Shearwalls - Level 13, Pour 64 Pour 64 (1)
-
02/23→02/25
13
Other
MEP Rough-In - Level 13, Pour 66
DP66-2020 MEP Rough-In - Level 13, Pour 66 Pour 66 (3)
-
02/23→02/25
2
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
EXT2-170 Floor 02 - Fluid Applied Roofing At Edge Of Slab 2nd Floor
-
02/23→03/06
3
Other
Floor 3 North - In Wall MEPF Rough In
GBW-470 Floor 3 North - In Wall MEPF Rough In Floor 3 Go Back Work
-
02/23→03/04
3A
Drywall/Framing
Frame Soffits/Hard Ceilings
SC3A-N2-IR-290 Floor 3A - Frame Soffits/Hard Ceilings Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/23→02/27
3A
Inspections/QC
OH Gilbane QC
SC3A-N2-IR-270 Floor 3A - OH Gilbane QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
02/23→03/20
3B
Electrical
OH Electrical & I.T. Rough In & QC
SC3B-N3-IR-220 Floor 3B - OH Electrical & I.T. Rough In & QC Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
02/23→02/24
3C
Inspections/QC
In-Wall Inspections - MEPF
SC3C-N1-IR-170 Floor 3C - In-Wall Inspections - MEPF Floor 3C SC 3.N1 Framing & Interior Roughs
-
02/23→02/27
3C
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC3C-N1-IR-320 Floor 3C - OH Sprinkler Rough In & QC Floor 3C SC 3.N1 Overhead Roughs
-
02/23→02/24
4
Flooring/Finishes
Floor 4 N4503 - Prime & 1st Finish Coat
TEL-4-110 Floor 4 N4503 - Prime & 1st Finish Coat Telecom Room Lv-4 N4503
-
02/23→03/06
4
Drywall/Framing
Floor 4 North - Layout, Frame & Insulate Walls
GBW-630 Floor 4 North - Layout, Frame & Insulate Walls Floor 4 Testing/Commissioning/Life Safety
-
02/23→03/20
4A
Electrical
OH Electrical & I.T. Rough In & QC
SC4A-N2-IR-210 Floor 4A - OH Electrical & I.T. Rough In & QC Floor 4A SC 4.N2 Overhead Roughs
-
02/23→03/06
5
Electrical
Floor 5 N5505 - Pull & Terminate Feeders
ELC-5-200 Floor 5 N5505 - Pull & Terminate Feeders Electrical Room Lv-5 N5505 5A,5B East
-
02/23→03/06
5A
Electrical
Install High OH Conduit Racks
SC5A-N2-IR-530 Floor 5A - Install High OH Conduit Racks Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
02/23→03/13
6
Electrical
6th Floor N6502 - Essential Power C Conduit Rough-In
WE6-1000 6th Floor N6502 - Essential Power C Conduit Rough-In West Essential - N6503 USS 6NEA
-
02/23→02/27
6
Electrical
6th Floor N6503 - Normal Power C Branch Circuit Installation
WN6-1010 6th Floor N6503 - Normal Power C Branch Circuit Installation West Normal - N6503 USS 6NNA
-
02/23→02/27
6
Electrical
6th Floor N6507 - Normal Power B Branch Circuit Installation
EN6-1010 6th Floor N6507 - Normal Power B Branch Circuit Installation East Normal - N6507 USS 6NNB
-
02/23→03/13
6
Electrical
6th Floor N6508 - Essential Power B Conduit Rough-In
EE6-1010 6th Floor N6508 - Essential Power B Conduit Rough-In East Essential - N6508 USS 6NEB
-
02/23→02/27
CEP
Other
CEP - Wire Pull Termination
CEP-E-1010 CEP - Wire Pull Termination CEP-E Tie-In
-
Tue 02/24
13
Concrete/Structure
Elevated Slab - Level 13, Pour 65 (2)
DP65-1040 Elevated Slab - Level 13, Pour 65 (2) Pour 65 (2)
-
02/24→02/25
5
Flooring/Finishes
Floor 5 N5503 - Prime & 1st Finish Coat
TEL-5-110 Floor 5 N5503 - Prime & 1st Finish Coat Telecom Room Lv-5 N5503
-
02/25→04/02
·
Concrete/Structure
Install Precast Panels Level 1-6 (Set 3 NWS)
W-720 Install Precast Panels Level 1-6 (Set 3 NWS) Precast
-
02/25→03/03
·
Inspections/QC
Install Punch Windows - Set 2
EXG-1010 Install Punch Windows - Set 2 Exterior Glass & Glazing South Elevation (Punch Windows)
-
02/25→03/03
13
Other
FRP Deck - Level 13 Pour 67 (4)
DP67-2010 FRP Deck - Level 13 Pour 67 (4) Pour 67 (4)
-
02/25→02/27
13
Concrete/Structure
Rebar - Level 13 Pour 66
DP66-2030 Rebar - Level 13 Pour 66 Pour 66 (3)
-
02/25→03/03
13
Other
Strip - Level 13, Pour 65 (2 day cure Drop & Reshore)
DP65-1050 Strip - Level 13, Pour 65 (2 day cure Drop & Reshore) Pour 65 (2)
-
02/25→03/10
2
Other
Floor 2 B - In Wall MEPF Rough In
GBW-410 Floor 2 B - In Wall MEPF Rough In Floor 2 Go Back Work
-
Wed 02/25
2
Concrete/Structure
N2501 - Seal Concrete Floor
2-TEL-540 Floor 2 - N2501 - Seal Concrete Floor Telecom Room Lv-2 N2501 MDF
-
02/25→03/03
2C
Ceilings
Soffits & Ceilings Gilbane QC
SC2C-N1-F-130 Floor 2C - Soffits & Ceilings Gilbane QC Floor 2C SC 2.N1 Final Finishes
-
02/25→03/10
3
Drywall/Framing
Floor 3 South - Layout, Frame & Insulate Walls
GBW-510 Floor 3 South - Layout, Frame & Insulate Walls Floor 3 Go Back Work
-
Wed 02/25
3
Concrete/Structure
N3504 - Seal Concrete Floor
TEL-3-540 Floor 3 - N3504 - Seal Concrete Floor Telecom Room Lv-3 N3204
-
02/25→02/26
4
Other
Floor 4 N4503 - Install Plywood Back Boards
TEL-4-130 Floor 4 N4503 - Install Plywood Back Boards Telecom Room Lv-4 N4503
-
02/25→02/26
4
Flooring/Finishes
Floor 4 N4504 - Prime & 1st Finish Coat
TEL-4-150 Floor 4 N4504 - Prime & 1st Finish Coat Telecom Room Lv-4 N4504
-
02/25→03/17
4A
Plumbing
In-Wall Plumbing Rough & QC
SC4A-N2-IR-140 Floor 4A - In-Wall Plumbing Rough & QC Floor 4A SC 4.N2 Framing & Interior Roughs
-
02/25→03/24
6
Electrical
Secondary OH Conduits 2
FL6-50 6th Floor - Secondary OH Conduits 2 Floor 6
-
02/26→03/11
·
Other
IMRIS R10 - MEP Clash Detection / BIM Coordination Cycle 2
REV10-1200 IMRIS R10 - MEP Clash Detection / BIM Coordination Cycle 2 IMRIS - Trade Coordination - Rev. 10
-
02/26→02/27
·
Concrete/Structure
Pour Steel Pan Stairs Level 1-4 Stair 28
ST26W-315 Pour Steel Pan Stairs Level 1-4 Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
02/26→03/02
13
Other
FRP Columns & Shearwalls - Level 13, Pour 65
DP65-1000 FRP Columns & Shearwalls - Level 13, Pour 65 Pour 65 (2)
-
02/26→03/25
2
Ceilings
Install EFIS Soffit/Caulk
EXT2-150 Floor 02 - Install EFIS Soffit/Caulk 2nd Floor
-
02/26→03/04
2
Data
N2501 - Install Racks & Ladder Tray
2-TEL-450 Floor 2 - N2501 - Install Racks & Ladder Tray Telecom Room Lv-2 N2501 MDF
-
02/26→03/04
3
Fire/Sprinkler
CEP Floor 3 - OH Sprinkler Rough In & QC
CEPN-3-3140 CEP Floor 3 - OH Sprinkler Rough In & QC Build-Out 3rd Flr
-
02/26→03/02
3
Flooring/Finishes
CEP Floor 3 - Paint Prime & First Coat
CEPN-3-3260 CEP Floor 3 - Paint Prime & First Coat Build-Out 3rd Flr
-
02/26→03/02
3
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
EXT3-190 Floor 03 - Fluid Applied Roofing At Edge Of Slab 3rd Floor
-
02/26→03/04
3
Data
N3504 - Install Racks & Ladder Tray
TEL-3-380 Floor 3 - N3504 - Install Racks & Ladder Tray Telecom Room Lv-3 N3204
-
02/26→03/05
4
Drywall/Framing
CEP Floor 4 - Finish Drywall
CEPN-4-4240 CEP Floor 4 - Finish Drywall Build-Out 4th Flr
-
02/26→03/25
4B
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC4B-N3-IR-200 Floor 4B - OH Duct/VAV Boxes Rough-In/Insulation Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
02/26→02/27
5
Flooring/Finishes
Floor 5 N5501 - Prime & 1st Finish Coat
TEL-5-450 Floor 5 N5501 - Prime & 1st Finish Coat Telecom Room Lv-5 N5501
-
02/26→03/03
5
Other
Floor 5 N5503 - Install Plywood Back Boards
TEL-5-130 Floor 5 N5503 - Install Plywood Back Boards Telecom Room Lv-5 N5503
-
02/26→02/27
5
Flooring/Finishes
Floor 5 N5504 - Prime & 1st Finish Coat
TEL-5-150 Floor 5 N5504 - Prime & 1st Finish Coat Telecom Room Lv-5 N5504
-
02/26→03/12
CEP
Other
EOR Submittal Review
RFI-0820.40 EOR Submittal Review RFI-0820 Generator Louver Revisions
-
02/27→03/05
4
HVAC/Mechanical
CEP Floor 4 - OH-Ductwork Controls Rough
CEPN-4-4120 CEP Floor 4 - OH-Ductwork Controls Rough Build-Out 4th Flr
-
02/27→03/02
4
Flooring/Finishes
Floor 4 N4501 - Prime & 1st Finish Coat
TEL-4-410 Floor 4 N4501 - Prime & 1st Finish Coat Telecom Room Lv-4 N4501
-
02/27→03/03
4
Electrical
Floor 4 N4503 - OH Conduit Rough-In
TEL-4-140 Floor 4 N4503 - OH Conduit Rough-In Telecom Room Lv-4 N4503
-
02/27→03/02
4
Other
Floor 4 N4504 - Install Plywood Back Boards
TEL-4-160 Floor 4 N4504 - Install Plywood Back Boards Telecom Room Lv-4 N4504
-
03/02→03/06
·
Other
Bridge - Roof LWIC
BRIDGE-166 Bridge - Roof LWIC New Bridge
-
Mon 03/02
13
Concrete/Structure
Elevated Slab - Level 13, Pour 66 (3)
DP66-2040 Elevated Slab - Level 13, Pour 66 (3) Pour 66 (3)
-
03/02→03/13
2C
Electrical
N2507 - Install & Electronically Connect VFD's AHU 2-3
2C2C-N1-M-150 Floor 2C - N2507 - Install & Electronically Connect VFD's AHU 2-3 Floor 2C AHU 2-3 SC 2.N1 Mechanical Space N2507 SPD
-
03/02→03/03
3A
Inspections/QC
OH Inspections - MEPF
SC3A-N2-IR-320 Floor 3A - OH Inspections - MEPF Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/02→03/27
3C
Electrical
Pull Branch Circuits
SC3C-N1-IR-300 Floor 3C - Pull Branch Circuits Floor 3C SC 3.N1 Overhead Roughs
-
03/02→03/06
4A
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC4A-N2-IR-360 Floor 4A - OH Sprinkler Rough In & QC Floor 4A SC 4.N2 Overhead Roughs
-
03/02→03/05
5
Other
Floor 5 N5504 - Install Plywood Back Boards
TEL-5-160 Floor 5 N5504 - Install Plywood Back Boards Telecom Room Lv-5 N5504
-
03/02→03/13
5B
Electrical
Install High OH Conduit Racks
SC5B-N3-IR-550 Floor 5B - Install High OH Conduit Racks Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
03/02→03/11
6
Drywall/Framing
Floor 6 N6501 - Hang/Tape/Finish Wall Board
TEL-6-100 Floor 6 N6501 - Hang/Tape/Finish Wall Board Telecom Room Lv-6 N6501
-
03/02→03/06
7
Other
Layout Walls & Trade Penetrations
FL7-N1-280 Floor 7 - Layout Walls & Trade Penetrations Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
03/03→06/09
·
Flooring/Finishes
Interior Signage - Fab/Deliver
DIV-10-190 Interior Signage - Fab/Deliver Interior Signage
-
03/03→03/05
13
Other
FRP Columns & Shearwalls - Level 13, Pour 66
DP66-2000 FRP Columns & Shearwalls - Level 13, Pour 66 Pour 66 (3)
-
03/03→03/06
13
Other
MEP Rough-In - Level 13, Pour 67
DP67-2020 MEP Rough-In - Level 13, Pour 67 Pour 67 (4)
-
03/03→03/12
13
Other
Strip - Level 13, Pour 66 (2 day cure Drop & Reshore)
DP66-2050 Strip - Level 13, Pour 66 (2 day cure Drop & Reshore) Pour 66 (3)
-
03/03→03/30
3B
HVAC/Mechanical
OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite
SC3B-N3-IR-320 Floor 3B - OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
03/03→03/04
4
Other
Floor 4 N4501 - Install Plywood Back Boards
TEL-4-420 Floor 4 N4501 - Install Plywood Back Boards Telecom Room Lv-4 N4501
-
03/03→03/05
4
Electrical
Floor 4 N4504 - OH Conduit Rough-In
TEL-4-180 Floor 4 N4504 - OH Conduit Rough-In Telecom Room Lv-4 N4504
-
03/03→03/05
4
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
4EXT-190 Floor 04 - Fluid Applied Roofing At Edge Of Slab 4th Floor
-
03/04→03/10
·
Other
FRP Deck - Roof Pour 68 (1)
DP68-2010 FRP Deck - Roof Pour 68 (1) Pour 68 (1)
-
03/04→03/06
13
Concrete/Structure
Rebar - Level 13 Pour 67
DP67-2030 Rebar - Level 13 Pour 67 Pour 67 (4)
-
03/04→03/10
2C
Ceilings
MEPF Inspections in Soffits
SC2C-N1-F-160 Floor 2C - MEPF Inspections in Soffits Floor 2C SC 2.N1 Final Finishes
-
03/04→03/05
3A
Drywall/Framing
Framing Inspections
SC3A-N2-F-150 Floor 3A - Framing Inspections Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/04→03/10
3A
Drywall/Framing
Hang Drywall Ceilings
SC3A-N2-IR-310 Floor 3A - Hang Drywall Ceilings Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/04→03/17
3C
Drywall/Framing
Blocking/Backing/Plywood
SC3C-N1-IR-220 Floor 3C - Blocking/Backing/Plywood Floor 3C SC 3.N1 Framing & Interior Roughs
-
03/04→03/24
4
Other
Floor 4 (Gen& El. Rm.) - Install Paralleling Gear Side B (EPSS-N)
CEPN-E-4040 Floor 4 (Gen& El. Rm.) - Install Paralleling Gear Side B (EPSS-N) Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/04→03/09
4
Electrical
Floor 4 N4503 - Install Grounding Buss
TEL-4-170 Floor 4 N4503 - Install Grounding Buss Telecom Room Lv-4 N4503
-
03/04→03/09
5
Other
Floor 5 N5501 - Install Plywood Back Boards
TEL-5-440 Floor 5 N5501 - Install Plywood Back Boards Telecom Room Lv-5 N5501
-
Wed 03/04
5
Flooring/Finishes
Floor 5 N5503 - Paint Plywood Back Boards
TEL-5-360 Floor 5 N5503 - Paint Plywood Back Boards Telecom Room Lv-5 N5503
-
03/04→03/05
9
Other
Control Lines & Benchmarks
FL9-1010 Floor 9 - Control Lines & Benchmarks Floor 09 - Inpatient Acuity Adaptable Unit (34 Beds)
-
03/05→04/22
·
Concrete/Structure
CMU Level 6-12 Stair 28
STR-26-210 CMU Level 6-12 Stair 28 CMU Stairs 26 & 28
-
Thu 03/05
·
Milestone
Normal/Emergency Power Switch Gear Delivery ◆
M630 Normal/Emergency Power Switch Gear Delivery Construction Milestones
-
03/05→03/09
3
Inspections/QC
CEP Floor 3 - Test OH-MEP Systems
CEPN-3-3150 CEP Floor 3 - Test OH-MEP Systems Build-Out 3rd Flr
-
03/05→03/25
3A
Electrical
Electrical Rough in Soffits
SC3A-N2-F-120 Floor 3A - Electrical Rough in Soffits Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/05→03/11
3A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffits
SC3A-N2-F-110 Floor 3A - HVAC Drops & Diffusers in Soffits Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/05→03/18
3C
Drywall/Framing
Frame Soffits/Hard Ceilings
SC3C-N1-IR-250 Floor 3C - Frame Soffits/Hard Ceilings Floor 3C SC 3.N1 Overhead Roughs
-
03/05→03/11
4
Fire/Sprinkler
CEP Floor 4 - OH Sprinkler Rough In & QC
CEPN-4-4130 CEP Floor 4 - OH Sprinkler Rough In & QC Build-Out 4th Flr
-
03/05→03/18
4B
Ceilings
Install Prefab Structural Steel Support For OR Ceilings (B-I Install)
SC4B-N3-IR-500 Floor 4B - Install Prefab Structural Steel Support For OR Ceilings (B-I Install) Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
03/05→03/06
5
Flooring/Finishes
Floor 5 N5502 - Prime & 1st Finish Coatt
ELC-5-110 Floor 5 N5502 - Prime & 1st Finish Coatt Electrical Room Lv-5 N5502 5B West, 5C
-
03/05→03/09
5
Electrical
Floor 5 N5503 - OH Conduit Rough-In
TEL-5-140 Floor 5 N5503 - OH Conduit Rough-In Telecom Room Lv-5 N5503
-
03/05→03/12
5
Concrete/Structure
Rev.7 CEP - FTR/Pour 5th Floor CIP Parapets
REV7-CEPPL-110 Rev.7 CEP - FTR/Pour 5th Floor CIP Parapets Rev.7 CEP Plenum Duct
-
03/06→03/10
4
Flooring/Finishes
CEP Floor 4 - Paint Prime & First Coat
CEPN-4-4300 CEP Floor 4 - Paint Prime & First Coat Build-Out 4th Flr
-
03/06→04/02
4
Other
Floor 4 (Gen& El. Rm.) - Install MV 4th Floor Normal Substation (USS-4NNA)
CEPN-E-4100 Floor 4 (Gen& El. Rm.) - Install MV 4th Floor Normal Substation (USS-4NNA) Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/06→03/10
4
Electrical
Floor 4 N4501 - OH Conduit Rough-In
TEL-4-430 Floor 4 N4501 - OH Conduit Rough-In Telecom Room Lv-4 N4501
-
03/06→03/11
4
Electrical
Floor 4 N4504 - Install Grounding Buss
TEL-4-200 Floor 4 N4504 - Install Grounding Buss Telecom Room Lv-4 N4504
-
Fri 03/06
5
Flooring/Finishes
Floor 5 N5504 - Paint Plywood Back Boards
TEL-5-380 Floor 5 N5504 - Paint Plywood Back Boards Telecom Room Lv-5 N5504
-
03/06→03/10
5
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
5EXT-190 Floor 05 - Fluid Applied Roofing At Edge Of Slab 5th Floor
-
03/06→03/19
6
Electrical
6th Floor N6503 - Normal Power C Electrical Equipment Installation
WN6-1020 6th Floor N6503 - Normal Power C Electrical Equipment Installation West Normal - N6503 USS 6NNA
-
03/06→03/19
6
Electrical
6th Floor N6507 - Normal Power B Electrical Equipment Installation
EN6-1020 6th Floor N6507 - Normal Power B Electrical Equipment Installation East Normal - N6507 USS 6NNB
-
03/06→04/02
6
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms, Hang One Side As Required
FL6-1000 6th Floor - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms, Hang One Side As Required Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
03/06→03/19
9
Plumbing
OH-Sanitary/Storm
FL9-1000 Floor 9 - OH-Sanitary/Storm Floor 09 - Inpatient Acuity Adaptable Unit (34 Beds)
-
03/09→03/13
·
Other
Bridge - Install Roof Membrane (PVC)
BRIDGE-167 Bridge - Install Roof Membrane (PVC) New Bridge
-
Mon 03/09
13
Concrete/Structure
Elevated Slab - Level 13, Pour 67 (4)
DP67-2040 Elevated Slab - Level 13, Pour 67 (4) Pour 67 (4)
-
03/09→04/03
3
Other
Floor 3 North - OH MEPF Rougth In
GBW-460 Floor 3 North - OH MEPF Rougth In Floor 3 Go Back Work
-
03/09→03/20
4
Other
Floor 4 North - In Wall MEPF Rough In
GBW-650 Floor 4 North - In Wall MEPF Rough In Floor 4 Testing/Commissioning/Life Safety
-
03/09→03/13
4A
Electrical
Install OH Cable Tray
SC4A-N2-IR-370 Floor 4A - Install OH Cable Tray Floor 4A SC 4.N2 Overhead Roughs
-
03/09→04/03
4B
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC4B-N3-IR-230 Floor 4B - OH HVAC Piping/Controls/Insulation & QC Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
03/09→03/20
4C
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC4C-N1-IR-210 Floor 4C - OH HVAC Piping/Controls/Insulation & QC Floor 4C SC 4.N1 Overhead Roughs
-
03/09→03/13
5
Electrical
Floor 5 N5502 - Install Electrical Panels/Equipment
ELC-5-150 Floor 5 N5502 - Install Electrical Panels/Equipment Electrical Room Lv-5 N5502 5B West, 5C
-
03/09→03/11
5
Electrical
Floor 5 N5504 - OH Conduit Rough-In
TEL-5-180 Floor 5 N5504 - OH Conduit Rough-In Telecom Room Lv-5 N5504
-
03/09→03/13
5B
Ceilings
OR Modular Ceilings Layout
SC5B-N3-IR-120 Floor 5B - OR Modular Ceilings Layout Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
03/09→03/20
5C
Electrical
Install High OH Conduit Racks
SC5C-N1-IR-540 Floor 5C - Install High OH Conduit Racks Floor 5C SC 5.N1 Overhead Roughs
-
03/09→03/13
8
Other
Layout Walls & Trade Penetrations
FL8-N1-520 Floor 8 - Layout Walls & Trade Penetrations Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
03/10→03/12
13
Other
FRP Columns & Shearwalls - Level 13, Pour 67
DP67-2000 FRP Columns & Shearwalls - Level 13, Pour 67 Pour 67 (4)
-
03/10→03/19
13
Other
Strip - Level 13, Pour 67 (2 day cure Drop & Reshore)
DP67-2050 Strip - Level 13, Pour 67 (2 day cure Drop & Reshore) Pour 67 (4)
-
03/10→03/16
3
Other
CEP Floor 3 - Complete Insulation After Testing Large Chilled Water
CEPN-3-3170 CEP Floor 3 - Complete Insulation After Testing Large Chilled Water Build-Out 3rd Flr
-
03/10→03/16
4
Data
Floor 4 N4503 - Install Racks & Ladder Tray
TEL-4-190 Floor 4 N4503 - Install Racks & Ladder Tray Telecom Room Lv-4 N4503
-
Tue 03/10
5
Flooring/Finishes
Floor 5 N5501 - Paint Plywood Back Boards
TEL-5-530 Floor 5 N5501 - Paint Plywood Back Boards Telecom Room Lv-5 N5501
-
03/10→03/13
5
Electrical
Floor 5 N5503 - Install Grounding Buss
TEL-5-170 Floor 5 N5503 - Install Grounding Buss Telecom Room Lv-5 N5503
-
03/11→03/16
·
Other
FRP Deck - Roof Pour 69 (2)
DP69-1010 FRP Deck - Roof Pour 69 (2) Pour 69 (2)
-
03/11→03/13
·
Other
MEP Rough-In - Roof, Pour 68
DP68-2020 MEP Rough-In - Roof, Pour 68 Pour 68 (1)
-
03/11→04/07
2
Other
Floor 2 B - OH MEPF Rougth In
GBW-400 Floor 2 B - OH MEPF Rougth In Floor 2 Go Back Work
-
03/11→03/20
2A
Flooring/Finishes
Paint Prime & First Coat
SC2A-N2-F-230 Floor 2A - Paint Prime & First Coat Floor 2A SC 2.N2 Final Finishes
-
03/11→04/14
2C
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC2C-N1-F-170 Floor 2C - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 2C SC 2.N1 Final Finishes
-
03/11→03/24
3
Other
Floor 3 South - In Wall MEPF Rough In
GBW-530 Floor 3 South - In Wall MEPF Rough In Floor 3 Go Back Work
-
03/11→03/17
4
Other
Floor 4 (Gen& El. Rm.) - Install Day Tanks
CEPN-E-4170 Floor 4 (Gen& El. Rm.) - Install Day Tanks Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/11→04/07
4
Other
Floor 4 (Gen& El. Rm.) - Install Exhaust
CEPN-E-4090 Floor 4 (Gen& El. Rm.) - Install Exhaust Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/11→03/16
4
Electrical
Floor 4 N4501 - Install Grounding Buss
TEL-4-440 Floor 4 N4501 - Install Grounding Buss Telecom Room Lv-4 N4501
-
03/11→03/24
4A
HVAC/Mechanical
Pneumatic Tube Stations Rough-In
SC4A-N2-IR-150 Floor 4A - Pneumatic Tube Stations Rough-In Floor 4A SC 4.N2 Framing & Interior Roughs
-
03/11→04/07
4C
Plumbing
OH Plumbing Rough In/Insulation & QC
SC4C-N1-IR-200 Floor 4C - OH Plumbing Rough In/Insulation & QC Floor 4C SC 4.N1 Overhead Roughs
-
03/11→03/13
5
Electrical
Floor 5 N5501 - OH Conduit Rough-In
TEL-5-510 Floor 5 N5501 - OH Conduit Rough-In Telecom Room Lv-5 N5501
-
03/11→03/13
6
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
6EXT-190 Floor 06 - Fluid Applied Roofing At Edge Of Slab 6th Floor
-
03/12→03/18
·
HVAC/Mechanical
IMRIS R10 - AHU Leave-Out / Ceiling Coordination
REV10-1210 IMRIS R10 - AHU Leave-Out / Ceiling Coordination IMRIS - Trade Coordination - Rev. 10
-
03/12→03/18
4
Data
Floor 4 N4504 - Install Racks & Ladder Tray
TEL-4-210 Floor 4 N4504 - Install Racks & Ladder Tray Telecom Room Lv-4 N4504
-
03/12→04/08
4B
Plumbing
OH Plumbing Rough In/Insulation & QC
SC4B-N3-IR-210 Floor 4B - OH Plumbing Rough In/Insulation & QC Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
03/12→03/17
5
Electrical
Floor 5 N5504 - Install Grounding Buss
TEL-5-200 Floor 5 N5504 - Install Grounding Buss Telecom Room Lv-5 N5504
-
03/12→03/13
6
Flooring/Finishes
Floor 6 N6501 - Prime & 1st Finish Coat
TEL-6-110 Floor 6 N6501 - Prime & 1st Finish Coat Telecom Room Lv-6 N6501
-
03/12→03/23
6
Drywall/Framing
Floor 6 N6509 - Hang/Tape/Finish Wall Board
TEL-6-120 Floor 6 N6509 - Hang/Tape/Finish Wall Board Telecom Room Lv-6 N6509
-
03/13→06/04
CEP
Concrete/Structure
Fab/Deliver Louvers
RFI-0820.50 Fab/Deliver Louvers RFI-0820 Generator Louver Revisions
-
03/13→03/16
CEP
Concrete/Structure
Rev.7 CEP - Install Decking at Plenum Roof
REV7-CEPPL-120 Rev.7 CEP - Install Decking at Plenum Roof Rev.7 CEP Plenum Duct
-
03/16→03/20
·
Other
Bridge - Install Z Clips
BRIDGE-220 Bridge - Install Z Clips New Bridge
-
03/16→04/10
·
Concrete/Structure
CMU Level 1-5 Stair 26
STR-28-100 CMU Level 1-5 Stair 26 CMU Stairs 26 & 28
-
03/16→03/19
·
Concrete/Structure
Rebar - Roof Pour 68
DP68-2030 Rebar - Roof Pour 68 Pour 68 (1)
-
03/16→04/03
1B
Plumbing
Plumbing Risers At Columns
SC1B-N1-IR-100 Floor 1B - Plumbing Risers At Columns Floor 1B SC 1.N2 Overhead & Finishes
-
03/16→03/25
3A
Ceilings
Soffits & Ceilings Gilbane QC
SC3A-N2-F-130 Floor 3A - Soffits & Ceilings Gilbane QC Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/16→03/20
3B
Inspections/QC
In-Wall Gilbane QC
SC3B-N3-IR-170 Floor 3B - In-Wall Gilbane QC Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/16→04/10
3B
Electrical
Pull Branch Circuits
SC3B-N3-IR-250 Floor 3B - Pull Branch Circuits Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
03/16→04/24
4B
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC4B-N3-IR-160 Floor 4B - In-Wall Electrical & I.T. Rough In & Control & QC Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
03/16→03/19
5
Electrical
Floor 5 N5501 - Install Grounding Buss
TEL-5-430 Floor 5 N5501 - Install Grounding Buss Telecom Room Lv-5 N5501
-
03/16→03/27
5
Electrical
Floor 5 N5502 - Pull & Terminate Feeders
ELC-5-160 Floor 5 N5502 - Pull & Terminate Feeders Electrical Room Lv-5 N5502 5B West, 5C
-
Mon 03/16
5
Concrete/Structure
Floor 5 N5503 - Seal Concrete Floor
TEL-5-370 Floor 5 N5503 - Seal Concrete Floor Telecom Room Lv-5 N5503
-
03/16→04/10
5A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC5A-N2-IR-180 Floor 5A - OH Duct/VAV Boxes Rough-In/Insulation Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
03/16→03/20
6
Electrical
6th Floor N6502 - Essential Power C Branch Circuit Installation
WE6-1010 6th Floor N6502 - Essential Power C Branch Circuit Installation West Essential - N6503 USS 6NEA
-
03/16→03/20
6
Electrical
6th Floor N6508 - Essential Power B Branch Circuit Installation
EE6-1020 6th Floor N6508 - Essential Power B Branch Circuit Installation East Essential - N6508 USS 6NEB
-
03/16→03/19
6
Other
Floor 6 N6501 - Install Plywood Back Boards
TEL-6-130 Floor 6 N6501 - Install Plywood Back Boards Telecom Room Lv-6 N6501
-
03/16→03/31
9A
Other
Layout Walls & Trade Penetrations
9A-IR-N1-1055 Floor 9A - Layout Walls & Trade Penetrations Floor 9A East Framing & Interior Roughs
-
03/17→03/23
·
Other
FRP Deck - Roof Pour 70 (3)
DP70-2010 FRP Deck - Roof Pour 70 (3) Pour 70 (3)
-
03/17→03/19
·
Other
MEP Rough-In - Roof, Pour 69
DP69-1020 MEP Rough-In - Roof, Pour 69 Pour 69 (2)
-
03/17→03/19
3
Inspections/QC
CEP Floor 3 - OH MEPF Inspections
CEPN-3-3240 CEP Floor 3 - OH MEPF Inspections Build-Out 3rd Flr
-
03/17→04/13
3B
HVAC/Mechanical
OR Modular Ceilings Ductwork & Clean-Suite Insulation
SC3B-N3-IR-350 Floor 3B - OR Modular Ceilings Ductwork & Clean-Suite Insulation Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
03/17→03/23
5
Data
Floor 5 N5503 - Install Racks & Ladder Tray
TEL-5-190 Floor 5 N5503 - Install Racks & Ladder Tray Telecom Room Lv-5 N5503
-
03/17→03/23
CEP
Drywall/Framing
Rev.7 CEP - Exterior Framing/Inspect Plenum Walls
REV7-CEPPL-130 Rev.7 CEP - Exterior Framing/Inspect Plenum Walls Rev.7 CEP Plenum Duct
-
03/18→03/24
3C
Drywall/Framing
Framing Inspections
SC3C-N1-F-150 Floor 3C - Framing Inspections Floor 3C SC 3.N1 Framing & Interior Roughs
-
03/18→03/31
4
Electrical
Floor 4 (Gen& El. Rm.) - Fuel Piping From Day Tank to Generator
CEPN-E-4180 Floor 4 (Gen& El. Rm.) - Fuel Piping From Day Tank to Generator Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/18→03/24
4A
Inspections/QC
In-Wall Gilbane QC
SC4A-N2-IR-160 Floor 4A - In-Wall Gilbane QC Floor 4A SC 4.N2 Framing & Interior Roughs
-
Wed 03/18
5
Concrete/Structure
Floor 5 N5504 - Seal Concrete Floor
TEL-5-390 Floor 5 N5504 - Seal Concrete Floor Telecom Room Lv-5 N5504
-
03/19→03/25
·
Other
IMRIS R10 - Final Coordination Sign-Off (All Trades)
REV10-1220 IMRIS R10 - Final Coordination Sign-Off (All Trades) IMRIS - Trade Coordination - Rev. 10
-
03/19→03/25
3C
HVAC/Mechanical
HVAC Drops & Diffusers in Hard Ceiling
SC3C-N1-F-110 Floor 3C - HVAC Drops & Diffusers in Hard Ceiling Floor 3C SC 3.N1 Final Finishes
-
03/19→03/25
3C
Inspections/QC
OH Gilbane QC
SC3C-N1-IR-240 Floor 3C - OH Gilbane QC Floor 3C SC 3.N1 Overhead Roughs
-
03/19→04/08
3C
Data
Pull Wire For All Low Voltage Systems
SC3C-N1-F-140 Floor 3C - Pull Wire For All Low Voltage Systems Floor 3C SC 3.N1 Overhead Roughs
-
03/19→03/25
4
Data
Floor 4 N4501 - Install Racks & Ladder Tray
TEL-4-450 Floor 4 N4501 - Install Racks & Ladder Tray Telecom Room Lv-4 N4501
-
03/19→03/23
4A
Drywall/Framing
Frame Soffits/Hard Ceilings
SC4A-N2-IR-300 Floor 4A - Frame Soffits/Hard Ceilings Floor 4A SC 4.N2 Overhead Roughs
-
03/19→03/25
5
Data
Floor 5 N5504 - Install Racks & Ladder Tray
TEL-5-210 Floor 5 N5504 - Install Racks & Ladder Tray Telecom Room Lv-5 N5504
-
03/19→04/01
5B
Ceilings
Install Prefab Structural Steel Support For OR Ceilings (B-I Install)
SC5B-N3-IR500 Floor 5B - Install Prefab Structural Steel Support For OR Ceilings (B-I Install) Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
Fri 03/20
·
Concrete/Structure
Elevated Slab - Roof, Pour 68 (1)
DP68-2040 Elevated Slab - Roof, Pour 68 (1) Pour 68 (1)
-
03/20→03/24
·
Concrete/Structure
Rebar - Roof Pour 69
DP69-1030 Rebar - Roof Pour 69 Pour 69 (2)
-
03/20→04/02
2
Drywall/Framing
Floor 2 C - Hang Drywall & Finish Drywall
GBW-220 Floor 2 C - Hang Drywall & Finish Drywall Floor 2 Go Back Work
-
03/20→03/26
3
Data
CEP Floor 3 - All Low Voltage Devices
CEPN-3-3180 CEP Floor 3 - All Low Voltage Devices Build-Out 3rd Flr
-
03/20→03/24
3
Flooring/Finishes
CEP Floor 3 - Doors & Hardware
CEPN-3-3030 CEP Floor 3 - Doors & Hardware Build-Out 3rd Flr
-
03/20→03/27
3
HVAC/Mechanical
CEP Floor 3 - HVAC Trim / Diffusers
CEPN-3-3190 CEP Floor 3 - HVAC Trim / Diffusers Build-Out 3rd Flr
-
03/20→03/26
3
Other
CEP Floor 3 - Install Coil Door
CEPN-3-3290 CEP Floor 3 - Install Coil Door Build-Out 3rd Flr
-
Fri 03/20
5
Concrete/Structure
Floor 5 N5501 - Seal Concrete Floor
TEL-5-540 Floor 5 N5501 - Seal Concrete Floor Telecom Room Lv-5 N5501
-
03/20→04/02
5
Drywall/Framing
Floor 5 North - Layout, Frame & Insulate Walls
GBW-750 Floor 5 North - Layout, Frame & Insulate Walls Floor 5 Testing/Commissioning/Life Safety
-
03/20→04/16
6
Electrical
6th Floor N6503 - Normal Power C Feeder Installation
WN6-1030 6th Floor N6503 - Normal Power C Feeder Installation West Normal - N6503 USS 6NNA
-
03/20→04/16
6
Electrical
6th Floor N6507 - Normal Power B Feeder Installation
EN6-1030 6th Floor N6507 - Normal Power B Feeder Installation East Normal - N6507 USS 6NNB
-
Fri 03/20
6
Flooring/Finishes
Floor 6 N6501 - Paint Plywood Back Boards
TEL-6-370 Floor 6 N6501 - Paint Plywood Back Boards Telecom Room Lv-6 N6501
-
03/20→04/02
6
Electrical
Install High OH Conduit Racks
FL6-1190 6th Floor - Install High OH Conduit Racks Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
03/20→04/14
9A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
9A-IR-N1-1010 Floor 9A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 9A East Framing & Interior Roughs
-
03/23→04/03
·
Other
Bridge - Install Hanger for Existing Utilities and Supports
BRIDGE-230 Bridge - Install Hanger for Existing Utilities and Supports New Bridge
-
03/23→03/25
·
Other
FRP Columns & Shearwalls - Roof, Pour 68
DP68-2000 FRP Columns & Shearwalls - Roof, Pour 68 Pour 68 (1)
-
03/23→03/27
·
Concrete/Structure
Install Steel Pan Stairs Level 10-Roof Stair 26
ST28E-270 Install Steel Pan Stairs Level 10-Roof Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
03/23→03/26
·
Other
MEP Rough-In - Roof, Pour 70
DP70-2020 MEP Rough-In - Roof, Pour 70 Pour 70 (3)
-
03/23→03/27
·
Other
Strip - Roof Pour 68 (2 day cure Drop & Reshore)
DP68-2050 Strip - Roof Pour 68 (2 day cure Drop & Reshore) Pour 68 (1)
-
03/23→04/10
2A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC2A-N2-F-370 Floor 2A - Install Special Wall Finishes (incl. Wall Protection) Floor 2A SC 2.N2 Final Finishes
-
03/23→03/24
3B
Inspections/QC
In-Wall Inspections - MEPF
SC3B-N3-IR-190 Floor 3B - In-Wall Inspections - MEPF Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/23→04/01
3B
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC3B-N3-IR-480 Floor 3B - OH Sprinkler Rough In & QC Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
03/23→04/17
4
Other
Floor 4 North - OH MEPF Rougth In
GBW-640 Floor 4 North - OH MEPF Rougth In Floor 4 Testing/Commissioning/Life Safety
-
03/23→04/17
4B
Electrical
OH Electrical & I.T. Rough In & QC
SC4B-N3-IR-220 Floor 4B - OH Electrical & I.T. Rough In & QC Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
03/23→04/17
4C
Electrical
OH Electrical & I.T. Rough In & QC
SC4C-N1-IR-230 Floor 4C - OH Electrical & I.T. Rough In & QC Floor 4C SC 4.N1 Overhead Roughs
-
03/23→04/03
6
Electrical
6th Floor N6502 - Essential Power C Electrical Equipment Installation
WE6-1020 6th Floor N6502 - Essential Power C Electrical Equipment Installation West Essential - N6503 USS 6NEA
-
03/23→04/03
6
Electrical
6th Floor N6508 - Essential Power B Electrical Equipment Installation
EE6-1030 6th Floor N6508 - Essential Power B Electrical Equipment Installation East Essential - N6508 USS 6NEB
-
03/23→03/25
6
Electrical
Floor 6 N6501 - OH Conduit Rough-In
TEL-6-140 Floor 6 N6501 - OH Conduit Rough-In Telecom Room Lv-6 N6501
-
03/24→03/30
·
Other
FRP Deck - Roof Pour 71 (4)
DP71-2010 FRP Deck - Roof Pour 71 (4) Pour 71 (4)
-
03/24→04/06
4
Electrical
CEP Floor 4 - Branch Circuits Conduit
CEPN-4-4050 CEP Floor 4 - Branch Circuits Conduit Build-Out 4th Flr
-
03/24→04/13
4
Electrical
CEP Floor 4 - Pull Branch Circuits
CEPN-4-4110 CEP Floor 4 - Pull Branch Circuits Build-Out 4th Flr
-
03/24→03/26
4
Inspections/QC
CEP Floor 4 - Test OH-MEP Systems
CEPN-4-4150 CEP Floor 4 - Test OH-MEP Systems Build-Out 4th Flr
-
03/24→04/20
4
Other
Floor 4 (Gen& El. Rm.) - Install Stand Alone HVL's C1, D1, EN5 & EN6
CEPN-E-4230 Floor 4 (Gen& El. Rm.) - Install Stand Alone HVL's C1, D1, EN5 & EN6 Electrical 4th floor (Generator & Main Electrical Rooms)
-
03/24→04/13
4A
Electrical
Electrical Rough in Soffits
SC4A-N2-F-120 Floor 4A - Electrical Rough in Soffits Floor 4A SC 4.N2 Final Finishes
-
03/24→03/27
4A
Data
Low Voltage Rough-In Piping
SC4A-N2-F-100 Floor 4A - Low Voltage Rough-In Piping Floor 4A SC 4.N2 Overhead Roughs
-
03/24→03/30
5
Data
Floor 5 N5501 - Install Racks & Ladder Tray
TEL-5-420 Floor 5 N5501 - Install Racks & Ladder Tray Telecom Room Lv-5 N5501
-
03/24→03/25
6
Flooring/Finishes
Floor 6 N6509 - Prime & 1st Finish Coat
TEL-6-150 Floor 6 N6509 - Prime & 1st Finish Coat Telecom Room Lv-6 N6509
-
03/24→04/02
7
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
FL7-N1-190 Floor 7 - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
03/24→03/26
CEP
Concrete/Structure
Rev.7 CEP - Exterior Sheathing/Inspect Plenum Walls
REV7-CEPPL-140 Rev.7 CEP - Exterior Sheathing/Inspect Plenum Walls Rev.7 CEP Plenum Duct
-
Wed 03/25
·
Concrete/Structure
Elevated Slab - Roof, Pour 69 (2)
DP69-1040 Elevated Slab - Roof, Pour 69 (2) Pour 69 (2)
-
03/25→04/21
2C
Drywall/Framing
Finish Drywall
SC2C-N1-F-220 Floor 2C - Finish Drywall Floor 2C SC 2.N1 Final Finishes
-
03/25→04/21
3
Other
Floor 3 South - OH MEPF Rougth In
GBW-520 Floor 3 South - OH MEPF Rougth In Floor 3 Go Back Work
-
03/25→04/07
3B
Drywall/Framing
Blocking/Backing/Plywood
SC3B-N3-IR-260 Floor 3B - Blocking/Backing/Plywood Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/25→04/21
3B
Plumbing
Med Gas Zone Valve Boxes/Terminations
SC3B-N3-IR-410 Floor 3B - Med Gas Zone Valve Boxes/Terminations Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/25→03/27
4
Flooring/Finishes
CEP Floor 4 - After Equipment Paint
CEPN-4-4270 CEP Floor 4 - After Equipment Paint Build-Out 4th Flr
-
03/25→03/26
4A
Inspections/QC
In-Wall Inspections - MEPF
SC4A-N2-IR-170 Floor 4A - In-Wall Inspections - MEPF Floor 4A SC 4.N2 Framing & Interior Roughs
-
03/25→04/21
6
Electrical
Secondary OH Conduits 3
FL6-60 6th Floor - Secondary OH Conduits 3 Floor 6
-
03/26→03/30
·
Other
FRP Columns & Shearwalls - Roof, Pour 69
DP69-1000 FRP Columns & Shearwalls - Roof, Pour 69 Pour 69 (2)
-
03/26→03/30
·
Concrete/Structure
Rebar - Roof Pour 70
DP70-2030 Rebar - Roof Pour 70 Pour 70 (3)
-
03/26→04/01
·
Other
Strip - Roof pour 69 (2 day cure Drop & Reshore)
DP69-1050 Strip - Roof pour 69 (2 day cure Drop & Reshore) Pour 69 (2)
-
03/26→04/08
1
Electrical
CEP - Floor 1 OH Electrical RI
CEP-1-1005 CEP - Floor 1 OH Electrical RI CEP Floor 1
-
03/26→03/27
10
Other
Control Lines & Benchmarks
FL10-1000 Floor 10 - Control Lines & Benchmarks Floor 9 Clean & Punch-Out
-
03/26→04/08
10
Concrete/Structure
Install Temp Weather Protection to Dry-In @ 10th Floor Slab
TEMP-1000 Install Temp Weather Protection to Dry-In @ 10th Floor Slab Temporary Roof 10th
-
03/26→04/13
2
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
EXT2-180 Floor 02 - Field Measure & Fab. Metal Drip Edge 2nd Floor
-
03/26→04/22
3
Ceilings
Install EFIS Soffit/Caulk
EXT3-150 Floor 03 - Install EFIS Soffit/Caulk 3rd Floor
-
03/26→04/01
3A
Ceilings
MEP Inspections in Soffits/Hard Lid
SC3A-N2-F-160 Floor 3A - MEP Inspections in Soffits/Hard Lid Floor 3A SC 3.N2 PACU/Prep + 3 ORS
-
03/26→04/08
3C
Electrical
Electrical Rough in Hard Ceiling
SC3C-N1-F-120 Floor 3C - Electrical Rough in Hard Ceiling Floor 3C SC 3.N1 Final Finishes
-
03/26→03/27
3C
Inspections/QC
OH Inspections - MEPF
SC3C-N1-IR-280 Floor 3C - OH Inspections - MEPF Floor 3C SC 3.N1 Overhead Roughs
-
03/26→05/06
4B
Ceilings
OR Modular Prefab Ceilings Install Clean Suite (B-I Install)
SC4B-N3-IR-350 Floor 4B - OR Modular Prefab Ceilings Install Clean Suite (B-I Install) Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
03/26→03/31
6
Electrical
Floor 6 N6501 - Install Grounding Buss
TEL-6-170 Floor 6 N6501 - Install Grounding Buss Telecom Room Lv-6 N6501
-
03/26→04/01
6
Electrical
Floor 6 N6501 - Install Level 6 Cable Tray
TEL-6-360 Floor 6 N6501 - Install Level 6 Cable Tray Telecom Room Lv-6 N6501
-
03/26→03/31
6
Other
Floor 6 N6509 - Install Plywood Back Boards
TEL-6-160 Floor 6 N6509 - Install Plywood Back Boards Telecom Room Lv-6 N6509
-
03/26→04/22
CEP
Concrete/Structure
CEP - Install Structural Steel Under Level 3 For Fuel Oil Tanks
CEP-4000 CEP - Install Structural Steel Under Level 3 For Fuel Oil Tanks CMU Walls & Structural Steel
-
03/27→03/31
3
Flooring/Finishes
CEP Floor 3 - Final Paint Paint
CEPN-3-3280 CEP Floor 3 - Final Paint Paint Build-Out 3rd Flr
-
03/27→04/02
4
Other
CEP Floor 4 - Complete Insulation After Testing Large Chilled Water
CEPN-4-4170 CEP Floor 4 - Complete Insulation After Testing Large Chilled Water Build-Out 4th Flr
-
03/27→04/09
4A
Drywall/Framing
Blocking/Backing/Plywood
SC4A-N2-IR-250 Floor 4A - Blocking/Backing/Plywood Floor 4A SC 4.N2 Framing & Interior Roughs
-
03/27→04/01
CEP
Concrete/Structure
Rev.7 CEP - Insulation & Roofing
REV7-CEPPL-150 Rev.7 CEP - Insulation & Roofing Rev.7 CEP Plenum Duct
-
03/30→04/02
·
Other
MEP Rough-In - Roof, Pour 71
DP71-2020 MEP Rough-In - Roof, Pour 71 Pour 71 (4)
-
03/30→04/10
10
Plumbing
OH-Sanitary /Storm
FL10-1010 Floor 10 - OH-Sanitary /Storm Floor 9 Clean & Punch-Out
-
03/30→04/10
3C
Drywall/Framing
Hang Drywall Ceilings
SC3C-N1-IR-310 Floor 3C - Hang Drywall Ceilings Floor 3C SC 3.N1 Overhead Roughs
-
03/30→04/01
4
Other
IMRIS R10 - Deliver for Install (4th Floor)
REV10-1260 IMRIS R10 - Deliver for Install (4th Floor) IMRIS Procurement - Rev. 10
-
03/30→03/31
4A
Inspections/QC
OH Inspections - MEPF
SC4A-N2-IR-340 Floor 4A - OH Inspections - MEPF Floor 4A SC 4.N2 Overhead Roughs
-
03/30→04/24
4A
Electrical
Pull Branch Circuits
SC4A-N2-IR-240 Floor 4A - Pull Branch Circuits Floor 4A SC 4.N2 Overhead Roughs
-
03/30→04/17
4B
Plumbing
In-Wall Plumbing Rough QC
SC4B-N3-IR-150 Floor 4B - In-Wall Plumbing Rough QC Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
03/30→04/24
5A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC5A-N2-IR-210 Floor 5A - OH HVAC Piping/Controls/Insulation & QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
Tue 03/31
·
Concrete/Structure
Elevated Slab - Roof, Pour 70 (3)
DP70-2040 Elevated Slab - Roof, Pour 70 (3) Pour 70 (3)
-
03/31→05/04
3B
Drywall/Framing
Frame Hard Ceilings
SC3B-N3-IR-280 Floor 3B - Frame Hard Ceilings Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
04/01→04/03
·
Other
FRP Columns & Shearwalls - Roof, Pour 70
DP70-2000 FRP Columns & Shearwalls - Roof, Pour 70 Pour 70 (3)
-
04/01→04/07
·
Concrete/Structure
FRP Concrete Wall
RCW-1020 FRP Concrete Wall Elevator Penthouse Structure
-
04/01→04/07
·
Concrete/Structure
Install Steel Pan Stairs Level 10-Roof Stair 27
ST27EL-180 Install Steel Pan Stairs Level 10-Roof Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/01→04/07
·
Concrete/Structure
Install Steel Pan Stairs Level 10-Roof Stair 28
ST26W-385 Install Steel Pan Stairs Level 10-Roof Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/01→04/03
·
Other
Strip - Roof Pour 70 (2 day cure Drop & Reshore)
DP70-2050 Strip - Roof Pour 70 (2 day cure Drop & Reshore) Pour 70 (3)
-
04/01→04/07
3
Electrical
CEP Floor 3 - Electrical Fixtures/Devices
CEPN-3-3200 CEP Floor 3 - Electrical Fixtures/Devices Build-Out 3rd Flr
-
Wed 04/01
6
Flooring/Finishes
Floor 6 N6509 - Paint Plywood Back Boards
TEL-6-390 Floor 6 N6509 - Paint Plywood Back Boards Telecom Room Lv-6 N6509
-
04/01→04/02
6
HVAC/Mechanical
Set AHU 3-1
AHU3-1-1000 Set AHU 3-1 6th Floor AHU 3-1
-
04/01→04/14
9B
Other
Layout Walls & Trade Penetrations
9B-IR-N2-1000 Floor 9B - Layout Walls & Trade Penetrations West 9B West Framing & Interior Roughs
-
04/02→04/08
·
Other
IMRIS R10 - GBC Mobilize / Field Verify / Area Access + Protection
REV10-1270 IMRIS R10 - GBC Mobilize / Field Verify / Area Access + Protection IMRIS Procurement - Rev. 10
-
04/02→04/06
·
Concrete/Structure
Rebar - Roof Pour 71
DP71-2030 Rebar - Roof Pour 71 Pour 71 (4)
-
04/02→04/29
3
Other
CEP Floor 3 - Install OH-Condenser Water (CWR) Hangers and Pipe
CEPN-M-3000 CEP Floor 3 - Install OH-Condenser Water (CWR) Hangers and Pipe Mechanical 3rd Flr (Chillers & Pumps)
-
04/02→04/27
3A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC3A-N2-F-170 Floor 3A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 3A SC 3.N2 Final Finishes
-
Thu 04/02
6
Concrete/Structure
Floor 6 N6501 - Seal Concrete Floor
TEL-6-380 Floor 6 N6501 - Seal Concrete Floor Telecom Room Lv-6 N6501
-
04/02→04/06
6
Electrical
Floor 6 N6509 - OH Conduit Rough-In
TEL-6-180 Floor 6 N6509 - OH Conduit Rough-In Telecom Room Lv-6 N6509
-
04/02→04/15
CEP
Concrete/Structure
Rev.7 CEP - Install EIFS
REV7-CEPPL-160 Rev.7 CEP - Install EIFS Rev.7 CEP Plenum Duct
-
04/03→04/24
·
Inspections/QC
Install Punch Windows - Set 3
EXG-1020 Install Punch Windows - Set 3 Exterior Glass & Glazing South Elevation (Punch Windows)
-
04/03→04/16
·
Other
Level 4 - Backwelding
BW-1020 Level 4 - Backwelding Detailing (Back Welding)
-
04/03→04/09
2
Flooring/Finishes
Floor 2 C - Prime & 1st Coat
GBW-380 Floor 2 C - Prime & 1st Coat Floor 2 Go Back Work
-
04/03→04/07
4
Inspections/QC
CEP Floor 4 - OH MEPF Inspections
CEPN-4-4160 CEP Floor 4 - OH MEPF Inspections Build-Out 4th Flr
-
04/03→04/30
4
Other
Floor 4 (Gen& El. Rm.) - Install MV 4th Floor Essential Substation (USS-4NQB)
CEPN-E-4110 Floor 4 (Gen& El. Rm.) - Install MV 4th Floor Essential Substation (USS-4NQB) Electrical 4th floor (Generator & Main Electrical Rooms)
-
04/03→04/16
5
Other
Floor 5 North - In Wall MEPF Rough In
GBW-770 Floor 5 North - In Wall MEPF Rough In Floor 5 Testing/Commissioning/Life Safety
-
04/03→04/30
5
Other
Floor 5 North - OH MEPF Rougth In
GBW-760 Floor 5 North - OH MEPF Rougth In Floor 5 Testing/Commissioning/Life Safety
-
04/03→04/09
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 3-1
AHU3-1-1020 AHU Drops/Duct Connections AHU 3-1 6th Floor AHU 3-1
-
04/03→04/09
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 3-1
AHU3-1-1010 AHU Drops/Piping Connections AHU 3-1 6th Floor AHU 3-1
-
04/03→04/09
6
Data
Floor 6 N6501 - Install Racks & Ladder Tray
TEL-6-190 Floor 6 N6501 - Install Racks & Ladder Tray Telecom Room Lv-6 N6501
-
04/03→04/14
6
Electrical
Floor 6 N6511 - In Wall Conduit RI
ELC-6-360 Floor 6 N6511 - In Wall Conduit RI Electrical Room Lv-6 N6511
-
04/03→04/16
6
Drywall/Framing
Floor 6 North - Layout, Frame & Insulate Walls
GBW-870 Floor 6 North - Layout, Frame & Insulate Walls Floor 6 Testing/Commissioning/Life Safety
-
04/03→04/16
6
Plumbing
In Wall Plumbing Rough In
FL6-1100 6th Floor - In Wall Plumbing Rough In Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
04/03→04/23
6
Electrical
In-Wall Electrical & I.T. Rough In & All Low Voltage & QC
FL6-1010 6th Floor - In-Wall Electrical & I.T. Rough In & All Low Voltage & QC Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
04/03→04/16
6
Fire/Sprinkler
In-Wall Sprinkler Rough In
FL6-1180 6th Floor - In-Wall Sprinkler Rough In Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
04/03→04/09
6
HVAC/Mechanical
Set AHU 3-4
AHU3-4-1000 Set AHU 3-4 6th Floor AHU 3-4
-
04/03→04/06
6
HVAC/Mechanical
Set AHU 6-1
AHU6-1-1000 Set AHU 6-1 6th Floor AHU 6-1
-
04/03→04/16
6A
HVAC/Mechanical
OH - AHU Duct Mains
6A-1000 6A - OH - AHU Duct Mains 6A AHU
-
04/03→04/06
7
Drywall/Framing
Door Frames
FL7-N1-160 Floor 7 - Door Frames Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/03→04/06
7
Flooring/Finishes
Floor 7 N7502 -Prime & 1st Finish Coat
ELC-7-310 Floor 7 N7502 -Prime & 1st Finish Coat Electrical Room Lv-7 N7502
-
04/03→04/06
7
Flooring/Finishes
Floor 7 N7505 - Prime & 1st Finish Coat
ELC-7-330 Floor 7 N7505 - Prime & 1st Finish Coat Electrical Room Lv-7 N7505
-
04/03→04/09
7
Electrical
In Wall Electrical Rough-In
FL7-N1-170 Floor 7 - In Wall Electrical Rough-In Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/03→04/16
7
Electrical
Install High OH Conduit Racks
FL7-N1-310 Floor 7 - Install High OH Conduit Racks Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/03→04/14
8
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
FL8-N1-580 Floor 8 - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/06→05/01
·
Concrete/Structure
Bridge - Fireproof New Steel
BRIDGE-240 Bridge - Fireproof New Steel New Bridge
-
04/06→05/15
1B
Plumbing
OH Rough In Sanitary
SC1B-N1-IR-240 Floor 1B - OH Rough In Sanitary Floor 1B SC 1.N2 Overhead & Finishes
-
04/06→04/17
3
Drywall/Framing
Floor 3 North - Hang Drywall & Finish Drywall
GBW-480 Floor 3 North - Hang Drywall & Finish Drywall Floor 3 Go Back Work
-
04/06→05/01
6
Electrical
6th Floor N6502 - Essential Power C Feeder Installation
WE6-1030 6th Floor N6502 - Essential Power C Feeder Installation West Essential - N6503 USS 6NEA
-
04/06→05/01
6
Other
6th Floor N6502 - Essential Power C UPS Installation
WE6-1070 6th Floor N6502 - Essential Power C UPS Installation West Essential - N6503 USS 6NEA
-
Tue 04/07
·
Milestone
Chillers Delivery ◆
M550 Chillers Delivery Construction Milestones
-
Tue 04/07
·
Milestone
Concrete Structure Complete ◆
M160 Concrete Structure Complete Construction Milestones
-
Tue 04/07
·
Concrete/Structure
Elevated Slab - Roof, Pour 71 (4)
DP71-2040 Elevated Slab - Roof, Pour 71 (4) Pour 71 (4)
-
04/07→04/20
·
Flooring/Finishes
Millwork/Casework Lv-1 - Review & Approval
DIV-09-5-550 Millwork/Casework Lv-1 - Review & Approval Millwork/Casework Lv-1
-
Tue 04/07
·
Milestone
Slab on Grade Poured ◆
M620 Slab on Grade Poured Construction Milestones
-
04/07→05/04
3B
Plumbing
OR Modular Ceilings Med Gas Hangers & Piping Rough
SC3B-N3-IR-140 Floor 3B - OR Modular Ceilings Med Gas Hangers & Piping Rough Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
04/07→04/27
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Normal Substation A (C1 & D1)
CEPN-E-4130 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Normal Substation A (C1 & D1) Electrical 4th floor (Generator & Main Electrical Rooms)
-
04/07→04/13
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 6-1
AHU6-1-1020 AHU Drops/Duct Connections AHU 6-1 6th Floor AHU 6-1
-
04/07→04/10
6
Electrical
Floor 6 N6509 - Install Grounding Buss
TEL-6-200 Floor 6 N6509 - Install Grounding Buss Telecom Room Lv-6 N6509
-
04/07→04/13
6
Electrical
Floor 6 N6509 - Install Level 6 Cable Tray
TEL-6-410 Floor 6 N6509 - Install Level 6 Cable Tray Telecom Room Lv-6 N6509
-
04/07→04/13
7
Electrical
Floor 7 N7502 - Install Electrical Panels/Equipment
ELC-7-350 Floor 7 N7502 - Install Electrical Panels/Equipment Electrical Room Lv-7 N7502
-
04/07→04/13
7
Electrical
Floor 7 N7505 - Install Electrical Panels/Equipment
ELC-7-370 Floor 7 N7505 - Install Electrical Panels/Equipment Electrical Room Lv-7 N7505
-
04/08→04/21
·
Other
FRP Elevated Deck Over Hoistway - Elevator Penthouse
RCW-1010 FRP Elevated Deck Over Hoistway - Elevator Penthouse Elevator Penthouse Structure
-
04/08→04/28
·
Concrete/Structure
FRP Parapet Walls - Roof, Pour 71
DP71-2000 FRP Parapet Walls - Roof, Pour 71 Pour 71 (4)
-
04/08→05/01
·
Concrete/Structure
Install Precast Panels Levels 6-8 (Set 4 WS)
SE-730 Install Precast Panels Levels 6-8 (Set 4 WS) Precast
-
04/08→04/14
·
Concrete/Structure
Install Steel Pan Stairs Level 5-9 Stair 27
ST27EL-150 Install Steel Pan Stairs Level 5-9 Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/08→05/06
·
Other
Roof Pour 71 (4) 28 Day Cure
DP71-2060 Roof Pour 71 (4) 28 Day Cure Pour 71 (4)
-
04/08→04/10
·
Other
Strip - Roof Pour 71 (2 day cure Drop & Reshore)
DP71-2050 Strip - Roof Pour 71 (2 day cure Drop & Reshore) Pour 71 (4)
-
04/08→04/09
1
Other
Control Lines & Benchmarks
1-1000 Floor 1 - Control Lines & Benchmarks INTERIOR CONSTRUCTION
-
04/08→04/10
1
Concrete/Structure
Prep/Grind/Float Sill Curbs
1EXT-170 Floor 01 - Prep/Grind/Float Sill Curbs 1st Floor
-
04/08→04/21
2
Drywall/Framing
Floor 2 North - Hang Drywall & Finish Drywall
GBW-420 Floor 2 North - Hang Drywall & Finish Drywall Floor 2 Go Back Work
-
04/08→04/14
2C
Fire/Sprinkler
Fire Stopping/Labeling
SC2C-N1-F-180 Floor 2C - Fire Stopping/Labeling Floor 2C SC 2.N1 Final Finishes
-
04/08→04/09
3
Flooring/Finishes
CEP Floor 3 - Signage
CEPN-3-3250 CEP Floor 3 - Signage Build-Out 3rd Flr
-
04/08→04/14
3B
Drywall/Framing
Framing Inspections
SC3B-N3-F-150 Floor 3B - Framing Inspections Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
04/08→04/14
4
Data
CEP Floor 4 - All Low Voltage Devices
CEPN-4-4180 CEP Floor 4 - All Low Voltage Devices Build-Out 4th Flr
-
04/08→04/10
4
Flooring/Finishes
CEP Floor 4 - Doors & Hardware
CEPN-4-4250 CEP Floor 4 - Doors & Hardware Build-Out 4th Flr
-
04/08→04/15
4
HVAC/Mechanical
CEP Floor 4 - HVAC Trim / Diffusers
CEPN-4-4190 CEP Floor 4 - HVAC Trim / Diffusers Build-Out 4th Flr
-
04/08→04/14
4
Other
CEP Floor 4 - Install Coil Door
CEPN-4-4310 CEP Floor 4 - Install Coil Door Build-Out 4th Flr
-
04/08→04/14
4C
Inspections/QC
In-Wall Gilbane QC
SC4C-N1-IR-160 Floor 4C - In-Wall Gilbane QC Floor 4C SC 4.N1 Framing & Interior Roughs
-
04/08→04/10
7
Plumbing
In Wall Med Gas RI Shaft
FL7-N1-240 Floor 7 - In Wall Med Gas RI Shaft Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/08→04/14
7
Plumbing
In Wall Plumbing Rough-In
FL7-N1-200 Floor 7 - In Wall Plumbing Rough-In Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/09→04/15
·
Concrete/Structure
IMRIS R10 - Structural Steel Layout
REV10-1280 IMRIS R10 - Structural Steel Layout IMRIS Procurement - Rev. 10
-
04/09→04/10
3C
Ceilings
Soffits & Ceilings Gilbane QC
SC3C-N1-F-130 Floor 3C - Soffits & Ceilings Gilbane QC Floor 3C SC 3.N1 Final Finishes
-
04/09→04/29
4A
Data
Pull Wire For All Low Voltage Systems
SC4A-N2-F-140 Floor 4A - Pull Wire For All Low Voltage Systems Floor 4A SC 4.N2 Overhead Roughs
-
04/10→04/16
1
Concrete/Structure
Layout For CMU
1-1020 Floor 1 - Layout For CMU INTERIOR CONSTRUCTION
-
04/10→04/30
2
Electrical
Floor 2 C - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-230 Floor 2 C - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 2 Go Back Work
-
04/10→04/23
2C
Flooring/Finishes
Paint Prime & First Coat
SC2C-N1-F-230 Floor 2C - Paint Prime & First Coat Floor 2C SC 2.N1 Final Finishes
-
04/10→04/13
4A
Drywall/Framing
Framing Inspections
SC4A-N2-F-150 Floor 4A - Framing Inspections Floor 4A SC 4.N2 Framing & Interior Roughs
-
04/10→04/16
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 3-4
AHU3-4-1020 AHU Drops/Duct Connections AHU 3-4 6th Floor AHU 3-4
-
04/10→04/16
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 3-4
AHU3-4-1010 AHU Drops/Piping Connections AHU 3-4 6th Floor AHU 3-4
-
04/10→04/20
6
HVAC/Mechanical
BMS Controls AHU 3-1
AHU3-1-1060 BMS Controls AHU 3-1 6th Floor AHU 3-1
-
04/10→04/23
6
Electrical
Install & Electronically Connect VFD's AHU 3-1
AHU3-1-1150 Install & Electronically Connect VFD's AHU 3-1 6th Floor AHU 3-1
-
04/10→04/13
6
HVAC/Mechanical
Set AHU 4-1
AHU4-1-1000 Set AHU 4-1 6th Floor AHU 4-1
-
04/13→04/24
·
Concrete/Structure
Install CMU Scaffold Support Deck Level 6 Stair 26
STR-28-130 Install CMU Scaffold Support Deck Level 6 Stair 26 CMU Stairs 26 & 28
-
04/13→04/17
·
Concrete/Structure
Install Steel Pan Stairs Level 1-4 Stair 26
ST28E-210 Install Steel Pan Stairs Level 1-4 Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/13→04/15
1
Concrete/Structure
Fluid Applied Roofing At Sill Curbs
1EXT-180 Floor 01 - Fluid Applied Roofing At Sill Curbs 1st Floor
-
04/13→04/17
3C
Ceilings
MEP Inspections in Hard Ceilings
SC3C-N1-F-160 Floor 3C - MEP Inspections in Hard Ceilings Floor 3C SC 3.N1 Final Finishes
-
04/13→04/15
4A
Drywall/Framing
Hang Drywall Ceilings
SC4A-N2-IR-320 Floor 4A - Hang Drywall Ceilings Floor 4A SC 4.N2 Overhead Roughs
-
04/13→05/08
5A
Plumbing
OH Plumbing Rough In/Insulation & QC
SC5A-N2-IR-200 Floor 5A - OH Plumbing Rough In/Insulation & QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
04/13→05/08
5C
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC5C-N1-IR-190 Floor 5C - OH Duct/VAV Boxes Rough-In/Insulation Floor 5C SC 5.N1 Overhead Roughs
-
04/13→04/15
9A
Other
Stock Bathroom Pods
9A-IR-N1-1065 Floor 9A - Stock Bathroom Pods Floor 9A East Framing & Interior Roughs
-
04/14→04/16
2
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
EXT2-200 Floor 02 - Apply Fluid Applied Roofing on Eyebrow 2nd Floor
-
04/14→05/26
3B
Electrical
OR Ceilings Overhead Electrical & Lighting Rough
SC3B-N3-IR-290 Floor 3B - OR Ceilings Overhead Electrical & Lighting Rough Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
04/14→05/04
4
Inspections/QC
CEP Floor 4 - AHCA 80% Inspection
CEPN-4-4210 CEP Floor 4 - AHCA 80% Inspection Build-Out 4th Flr
-
04/14→04/27
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders to 4NNA (C1-1B, D1-1B)
CEPN-E-4150 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders to 4NNA (C1-1B, D1-1B) Electrical 4th floor (Generator & Main Electrical Rooms)
-
04/14→04/20
4A
Ceilings
Soffits & Ceilings Gilbane QC
SC4A-N2-F-130 Floor 4A - Soffits & Ceilings Gilbane QC Floor 4A SC 4.N2 Final Finishes
-
04/14→04/20
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 4-1
AHU4-1-1020 AHU Drops/Duct Connections AHU 4-1 6th Floor AHU 4-1
-
04/14→04/20
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 4-1
AHU4-1-1010 AHU Drops/Piping Connections AHU 4-1 6th Floor AHU 4-1
-
Tue 04/14
6
Concrete/Structure
Floor 6 N6509 - Seal Concrete Floor
TEL-6-400 Floor 6 N6509 - Seal Concrete Floor Telecom Room Lv-6 N6509
-
04/15→04/16
·
Concrete/Structure
Pour Steel Pan Stairs Level Level 5-9 Stair 27
ST27EL-155 Pour Steel Pan Stairs Level Level 5-9 Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/15→04/28
10A
Other
Layout Walls & Trade Penetrations
10A-IR-N1-1000 Floor 10A - Layout Walls & Trade Penetrations Floor 10A East Framing & Interior Roughs
-
04/15→05/19
2B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC2B-N3-F-170 Floor 2B - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 2B SC 2.N3
-
04/15→04/21
2C
Flooring/Finishes
Grout Bed for Tile
SC2C-N1-F-200 Floor 2C - Grout Bed for Tile Floor 2C SC 2.N1 Final Finishes
-
04/15→04/20
2C
Flooring/Finishes
Moisture Mitigation for Tile
SC2C-N1-F-190 Floor 2C - Moisture Mitigation for Tile Floor 2C SC 2.N1 Final Finishes
-
04/15→04/17
4
Flooring/Finishes
CEP Floor 4 - Final Paint Paint
CEPN-4-4260 CEP Floor 4 - Final Paint Paint Build-Out 4th Flr
-
04/15→04/16
4C
Inspections/QC
In-Wall Inspections - MEPF
SC4C-N1-IR-180 Floor 4C - In-Wall Inspections - MEPF Floor 4C SC 4.N1 Framing & Interior Roughs
-
04/15→04/21
6
Data
Floor 6 N6509 - Install Racks & Ladder Tray
TEL-6-210 Floor 6 N6509 - Install Racks & Ladder Tray Telecom Room Lv-6 N6509
-
04/15→04/22
6
Drywall/Framing
Floor 6 N6511 - Hang/Tape/Finish Drywall
ELC-6-300 Floor 6 N6511 - Hang/Tape/Finish Drywall Electrical Room Lv-6 N6511
-
04/15→04/16
7
Inspections/QC
In Wall MEPF Inspections
FL7-N1-250 Floor 7 - In Wall MEPF Inspections Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/15→04/16
8
Drywall/Framing
Door Frames
FL8-N1-570 Floor 8 - Door Frames Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/15→04/16
8
Flooring/Finishes
Floor 8 N8502 - Prime & 1st Finish Coat
ELC-8-310 Floor 8 N8502 - Prime & 1st Finish Coat Electrical Room Lv-8 N8502
-
04/15→04/16
8
Flooring/Finishes
Floor 8 N8505 - Prime & 1st Finish Coat
ELC-8-330 Floor 8 N8505 - Prime & 1st Finish Coat Electrical Room Lv-8 N8505
-
04/15→04/16
9
Flooring/Finishes
Floor 9 N9502 - Prime & 1st Finish Coat
ELC-9-150 Floor 9 N9502 - Prime & 1st Finish Coat Electrical Room Lv-9 N9502 9A West, 9B West, 9C West
-
04/15→04/24
9
Drywall/Framing
Floor 9 N9504 - Hang/Tape/Finish Wall Board
TEL-9-100 Floor 9 N9504 - Hang/Tape/Finish Wall Board Telecom Room Lv-9 N9504
-
04/15→04/16
9
Flooring/Finishes
Floor 9 N9505 - Prime & 1st Finish Coat
ELC-9-110 Floor 9 N9505 - Prime & 1st Finish Coat Electrical Room Lv-9 N9505 9A East, 9B East, 9C East
-
04/15→05/05
9A
Other
Install Pre-Fab Headwalls
9A-IR-N1-1130 Floor 9A - Install Pre-Fab Headwalls Floor 9A East Framing & Interior Roughs
-
04/15→05/05
9B
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
9B-IR-N2-1010 Floor 9B - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms West 9B West Framing & Interior Roughs
-
04/15→04/17
9B
Other
Stock Bathroom Pods
9B-IR-N2-1220 Floor 9B - Stock Bathroom Pods West 9B West Framing & Interior Roughs
-
04/16→04/29
·
Concrete/Structure
IMRIS R10 - Set Structural Steel / Supports Installed
REV10-1290 IMRIS R10 - Set Structural Steel / Supports Installed IMRIS Procurement - Rev. 10
-
04/16→04/20
1
Concrete/Structure
Layout for Box Beam Header
1EXT-100 Floor 01 - Layout for Box Beam Header 1st Floor
-
Thu 04/16
CEP
Other
Rev.7 CEP - Roof Trim
REV7-CEPPL-170 Rev.7 CEP - Roof Trim Rev.7 CEP Plenum Duct
-
04/17→04/23
·
Fire/Sprinkler
Level 4 - Perimeter Firestopping
FSP-1020 Level 4 - Perimeter Firestopping Firestopping
-
04/17→04/20
·
Concrete/Structure
Pour Steel Pan Stairs Level 10-Roof Stair 27
ST28E-185 Pour Steel Pan Stairs Level 10-Roof Stair 27 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/17→05/29
1
Concrete/Structure
Install CMU
FL1-20 Floor 1 - Install CMU INTERIOR CONSTRUCTION
-
04/17→04/30
4C
Drywall/Framing
Blocking/Backing/Plywood
SC4C-N1-IR-220 Floor 4C - Blocking/Backing/Plywood Floor 4C SC 4.N1 Framing & Interior Roughs
-
04/17→04/30
6
Other
6th Floor N6503 - Normal Power C Equipment Terminations
WN6-1050 6th Floor N6503 - Normal Power C Equipment Terminations West Normal - N6503 USS 6NNA
-
04/17→04/21
6
Electrical
6th Floor N6503 - Normal Power C Light Fixture Installation
WN6-1040 6th Floor N6503 - Normal Power C Light Fixture Installation West Normal - N6503 USS 6NNA
-
04/17→04/30
6
Other
6th Floor N6507 - Normal Power B Equipment Terminations
EN6-1050 6th Floor N6507 - Normal Power B Equipment Terminations East Normal - N6507 USS 6NNB
-
04/17→04/21
6
Electrical
6th Floor N6507 - Normal Power B Light Fixture Installation
EN6-1040 6th Floor N6507 - Normal Power B Light Fixture Installation East Normal - N6507 USS 6NNB
-
04/17→05/14
6
Electrical
6th Floor N6508 - Essential Power B Feeder Installation
EE6-1040 6th Floor N6508 - Essential Power B Feeder Installation East Essential - N6508 USS 6NEB
-
04/17→04/27
6
HVAC/Mechanical
BMS Controls AHU 3-4
AHU3-4-1060 BMS Controls AHU 3-4 6th Floor AHU 3-4
-
04/17→04/30
6
Other
Floor 6 North - In Wall MEPF Rough In
GBW-890 Floor 6 North - In Wall MEPF Rough In Floor 6 Testing/Commissioning/Life Safety
-
04/17→04/30
6
Electrical
Install & Electronically Connect VFD's AHU3-4
AHU3-4-1150 Install & Electronically Connect VFD's AHU3-4 6th Floor AHU 3-4
-
04/17→04/23
6
HVAC/Mechanical
Set AHU 5-4
AHU5-4-1000 Set AHU 5-4 6th Floor AHU 5-4
-
04/17→05/14
6A
Other
Insulation
6A-1070 6A - Insulation 6A AHU
-
04/17→05/14
6A
HVAC/Mechanical
OH - AHU Piping Main
6A-1020 6A - OH - AHU Piping Main 6A AHU
-
04/17→05/14
6B
HVAC/Mechanical
OH - AHU - Duct Mains
6B-1000 6B - OH - AHU - Duct Mains 6B AHU
-
04/17→04/23
7
Drywall/Framing
Hang Drywall
FL7-N1-210 Floor 7 - Hang Drywall Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/17→04/23
8
Electrical
Floor 8 N8502 - Install Electrical Panels/Equipment
ELC-8-350 Floor 8 N8502 - Install Electrical Panels/Equipment Electrical Room Lv-8 N8502
-
04/17→04/23
8
Electrical
Floor 8 N8505 - Install Electrical Panels/Equipment
ELC-8-370 Floor 8 N8505 - Install Electrical Panels/Equipment Electrical Room Lv-8 N8505
-
04/17→04/30
8
Electrical
Install High OH Conduit Racks
FL8-N1-610 Floor 8 - Install High OH Conduit Racks Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/17→04/23
9
Electrical
Floor 9 N9505 - Install Electrical Panels/Equipment
ELC-9-140 Floor 9 N9505 - Install Electrical Panels/Equipment Electrical Room Lv-9 N9505 9A East, 9B East, 9C East
-
04/20→04/21
·
Concrete/Structure
Pour Steel Pan Stairs Level 1-4 Stair 26
ST28E-215 Pour Steel Pan Stairs Level 1-4 Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/20→05/15
10A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
10A-IR-N1-1010 Floor 10A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 10A East Framing & Interior Roughs
-
04/20→04/24
3
Flooring/Finishes
Floor 3 North - Prime & 1st Coat
GBW-490 Floor 3 North - Prime & 1st Coat Floor 3 Go Back Work
-
04/20→04/24
4
Electrical
CEP Floor 4 - Electrical Fixtures/Devices
CEPN-4-4200 CEP Floor 4 - Electrical Fixtures/Devices Build-Out 4th Flr
-
04/20→05/01
4
Drywall/Framing
Floor 4 North - Hang Drywall & Finish Drywall
GBW-660 Floor 4 North - Hang Drywall & Finish Drywall Floor 4 Testing/Commissioning/Life Safety
-
04/20→04/24
4B
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC4B-N3-IR-480 Floor 4B - OH Sprinkler Rough In & QC Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
04/20→05/08
4C
Drywall/Framing
Frame Soffits/Hard Ceilings
SC4C-N1-IR-250 Floor 4C - Frame Soffits/Hard Ceilings Floor 4C SC 4.N1 Overhead Roughs
-
04/20→04/24
4C
Electrical
Install OH Cable Tray
SC4C-N1-IR-330 Floor 4C - Install OH Cable Tray Floor 4C SC 4.N1 Overhead Roughs
-
04/20→04/24
4C
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC4C-N1-IR-320 Floor 4C - OH Sprinkler Rough In & QC Floor 4C SC 4.N1 Overhead Roughs
-
04/20→05/15
5A
Electrical
OH Electrical & I.T. Rough In & QC
SC5A-N2-IR-190 Floor 5A - OH Electrical & I.T. Rough In & QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
04/21→07/29
·
Flooring/Finishes
Millwork/Casework Lv-1 - Fab & Deliver
DIV-09-5-530 Millwork/Casework Lv-1 - Fab & Deliver Millwork/Casework Lv-1
-
04/21→05/04
1
Drywall/Framing
Frame/Inspect CW Box Beam Header
1EXT-110 Floor 01- Frame/Inspect CW Box Beam Header 1st Floor
-
04/21→04/27
3A
Fire/Sprinkler
Fire Stopping/Labeling
SC3A-N2-F-180 Floor 3A - Fire Stopping/Labeling Floor 3A SC 3.N2 Final Finishes
-
04/21→05/04
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders - Paralleling Gear D1E
CEPN-E-4060 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders - Paralleling Gear D1E Electrical 4th floor (Generator & Main Electrical Rooms)
-
04/21→04/27
4A
Ceilings
MEP Inspections in Soffits/Hard Lid
SC4A-N2-F-160 Floor 4A - MEP Inspections in Soffits/Hard Lid Floor 4A SC 4.N2 Final Finishes
-
04/21→04/29
6
HVAC/Mechanical
BMS Controls AHU 4-1
AHU4-1-1030 BMS Controls AHU 4-1 6th Floor AHU 4-1
-
04/21→05/04
6
Electrical
Install & Electronically Connect VFD's AHU 4-1
AHU4-1-1040 Install & Electronically Connect VFD's AHU 4-1 6th Floor AHU 4-1
-
04/21→04/22
6
HVAC/Mechanical
Set AHU 5-1
AHU5-1-1000 Set AHU 5-1 6th Floor AHU 5-1
-
04/22→05/19
·
Concrete/Structure
Install Penthouse CMU - Penthouse
CMU-1000 Install Penthouse CMU - Penthouse Elevator Penthouse Structure
-
04/22→04/28
2
Flooring/Finishes
Floor 2 North - Prime & 1st Coat
GBW-430 Floor 2 North - Prime & 1st Coat Floor 2 Go Back Work
-
04/22→05/05
3
Drywall/Framing
Floor 3 South - Hang Drywall & Finish Drywall
GBW-540 Floor 3 South - Hang Drywall & Finish Drywall Floor 3 Go Back Work
-
04/22→05/19
4B
Plumbing
Med Gas Zone Valve Boxes/Terminations
SC4B-N3-IR-310 Floor 4B - Med Gas Zone Valve Boxes/Terminations Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
04/22→04/28
9
Electrical
Floor 9 N9502 - Install Electrical Panels/Equipment
ELC-9-160 Floor 9 N9502 - Install Electrical Panels/Equipment Electrical Room Lv-9 N9502 9A West, 9B West, 9C West
-
04/23→04/30
·
Concrete/Structure
CMU Level 13 Stair 28
STR-26-220 CMU Level 13 Stair 28 CMU Stairs 26 & 28
-
04/23→04/29
·
Concrete/Structure
Install Steel Pan Stairs Level 5-9 Stair 28
ST26W-345 Install Steel Pan Stairs Level 5-9 Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/23→05/06
2
Electrical
CEP Floor 2 OH Electrical & Low Voltage Rough In
CEP-2-4050 CEP Floor 2 OH Electrical & Low Voltage Rough In 2nd Floor (Fuel Oil Systems)
-
04/23→05/11
3
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
EXT3-200 Floor 03 - Field Measure & Fab. Metal Drip Edge 3rd Floor
-
04/23→05/20
4
Ceilings
Install EFIS Soffit/Caulk
4EXT-150 Floor 04 - Install EFIS Soffit/Caulk 4th Floor
-
04/23→04/29
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 5-1
AHU5-1-1020 AHU Drops/Duct Connections AHU 5-1 6th Floor AHU 5-1
-
04/23→04/24
6
Flooring/Finishes
Floor 6 N6511 - Prime & 1st Finish Coat
ELC-6-310 Floor 6 N6511 - Prime & 1st Finish Coat Electrical Room Lv-6 N6511
-
04/24→04/30
2C
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC2C-N1-F-270 Floor 2C - Install Special Wall Finishes (incl. Wall Protection) Floor 2C SC 2.N1 Final Finishes
-
04/24→04/29
2C
Electrical
Light Fixtures in Soffit
SC2C-N1-F-260 Floor 2C - Light Fixtures in Soffit Floor 2C SC 2.N1 Final Finishes
-
04/24→05/07
4
Drywall/Framing
Floor 4 South - Layout, Frame & Insulate Walls
GBW-570 Floor 4 South - Layout, Frame & Insulate Walls Floor 4 Testing/Commissioning/Life Safety
-
04/24→04/30
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 5-4
AHU5-4-1020 AHU Drops/Duct Connections AHU 5-4 6th Floor AHU 5-4
-
04/24→04/30
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 5-4
AHU5-4-1010 AHU Drops/Piping Connections AHU 5-4 6th Floor AHU 5-4
-
04/24→05/05
7
Drywall/Framing
Floor 7 N7504 - Hang/Tape/Finish Wall Board
TEL-7-105 Floor 7 N7504 - Hang/Tape/Finish Wall Board Telecom Room Lv-7 N7504
-
04/24→04/30
7
Drywall/Framing
Tape & Finish
FL7-N1-220 Floor 7 - Tape & Finish Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/24→05/07
9
Electrical
Floor 9 N9505 - Pull & Terminate Feeders
ELC-9-170 Floor 9 N9505 - Pull & Terminate Feeders Electrical Room Lv-9 N9505 9A East, 9B East, 9C East
-
04/27→06/15
·
Concrete/Structure
CMU Level 6-12 Stair 26
STR-28-110 CMU Level 6-12 Stair 26 CMU Stairs 26 & 28
-
04/27→05/15
3
Electrical
Floor 3 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-500 Floor 3 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 3 Go Back Work
-
04/27→04/28
4
Flooring/Finishes
CEP Floor 4 - Signage
CEPN-4-4290 CEP Floor 4 - Signage Build-Out 4th Flr
-
04/27→05/22
4B
Electrical
Pull Branch Circuits
SC4B-N3-IR-250 Floor 4B - Pull Branch Circuits Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
04/27→05/01
4C
Inspections/QC
OH Gilbane QC
SC4C-N1-IR-240 Floor 4C - OH Gilbane QC Floor 4C SC 4.N1 Overhead Roughs
-
04/27→05/22
4C
Electrical
Pull Branch Circuits
SC4C-N1-IR-300 Floor 4C - Pull Branch Circuits Floor 4C SC 4.N1 Overhead Roughs
-
04/27→05/01
5A
Electrical
Install OH Cable Tray
SC5A-N2-IR-360 Floor 5A - Install OH Cable Tray Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
04/27→05/01
6
Electrical
Floor 6 N6511 - Install Electrical Panels/Equipment
ELC-6-330 Floor 6 N6511 - Install Electrical Panels/Equipment Electrical Room Lv-6 N6511
-
04/27→05/08
6
Electrical
Floor 6 N6511 - OH Conduit RI
ELC-6-320 Floor 6 N6511 - OH Conduit RI Electrical Room Lv-6 N6511
-
04/27→06/01
6
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
FL6-1140 6th Floor - OH Duct/VAV Boxes Rough-In/Insulation Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
04/27→05/08
7
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
FL7-N1-130 Floor 7 - OH Duct/VAV Boxes Rough-In/Insulation Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
04/27→04/28
9
Flooring/Finishes
Floor 9 N9504 - Prime & 1st Finish Coat
TEL-9-110 Floor 9 N9504 - Prime & 1st Finish Coat Telecom Room Lv-9 N9504
-
04/28→05/18
3A
Drywall/Framing
Finish Drywall
SC3A-N2-F-190 Floor 3A - Finish Drywall Floor 3A SC 3.N2 Final Finishes
-
04/28→05/26
3B
Electrical
OR Modular Ceilings Electrical Rough to Clean-Suite
SC3B-N3-IR-330 Floor 3B - OR Modular Ceilings Electrical Rough to Clean-Suite Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
04/28→05/04
3C
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC3C-N1-F-170 Floor 3C - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 3C SC 3.N1 Final Finishes
-
04/28→05/04
3C
Fire/Sprinkler
Fire Stopping/Labeling
SC3C-N1-F-180 Floor 3C - Fire Stopping/Labeling Floor 3C SC 3.N1 Final Finishes
-
04/28→05/11
4B
HVAC/Mechanical
OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite
SC4B-N3-IR-370 Floor 4B - OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
04/29→05/01
10A
Other
Stock Bathroom Pods
10A-IR-N1-1210 Floor 10A - Stock Bathroom Pods Floor 10A East Framing & Interior Roughs
-
04/29→05/19
2
Electrical
Floor 2 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-440 Floor 2 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 2 Go Back Work
-
04/29→05/08
2A
Ceilings
Install Ceiling Grid
SC2A-N2-F-260 Floor 2A - Install Ceiling Grid Floor 2A SC 2.N2 Final Finishes
-
04/29→05/27
2B
Drywall/Framing
Finish Drywall
SC2B-N3-F-190 Floor 2B - Finish Drywall Floor 2B SC 2.N3
-
04/29→05/04
9
Other
Floor 9 N9504 - Install Plywood Back Boards
TEL-9-130 Floor 9 N9504 - Install Plywood Back Boards Telecom Room Lv-9 N9504
-
04/30→05/13
·
Other
IMRIS R10 - Rails Survey, Shim Pick / Install & Adjustments [(feeds detailed IMRIS + CT work below)]
REV10-1300 IMRIS R10 - Rails Survey, Shim Pick / Install & Adjustments [(feeds detailed IMRIS + CT work below)] IMRIS Procurement - Rev. 10
-
04/30→05/01
·
Concrete/Structure
Pour Steel Pan Stairs Level 5-9 Stair 28
ST26W-355 Pour Steel Pan Stairs Level 5-9 Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
04/30→05/13
3
HVAC/Mechanical
CEP Floor 3 - Install Chillers & Pumps
CEPN-M-3020 CEP Floor 3 - Install Chillers & Pumps Mechanical 3rd Flr (Chillers & Pumps)
-
04/30→05/08
6
HVAC/Mechanical
BMS Controls AHU 5-1
AHU5-1-1030 BMS Controls AHU 5-1 6th Floor AHU 5-1
-
04/30→05/06
6
HVAC/Mechanical
Set AHU 5-5
AHU5-5-1000 Set AHU 5-5 6th Floor AHU 5-5
-
05/01→05/07
4
Drywall/Framing
CEP Floor 4 - After Equipment Hang Drywall
CEPN-4-4230 CEP Floor 4 - After Equipment Hang Drywall Build-Out 4th Flr
-
05/01→05/14
5
Drywall/Framing
Floor 5 North - Hang Drywall & Finish Drywall
GBW-780 Floor 5 North - Hang Drywall & Finish Drywall Floor 5 Testing/Commissioning/Life Safety
-
05/01→05/04
6
Other
6th Floor N6503 - Normal Power C Trim Out
WN6-1060 6th Floor N6503 - Normal Power C Trim Out West Normal - N6503 USS 6NNA
-
05/01→05/04
6
Other
6th Floor N6507 - Normal Power B Trim Out
EN6-1060 6th Floor N6507 - Normal Power B Trim Out East Normal - N6507 USS 6NNB
-
05/01→05/11
6
HVAC/Mechanical
BMS Controls AHU 5-4
AHU5-4-1030 BMS Controls AHU 5-4 6th Floor AHU 5-4
-
05/01→05/29
6
Other
Floor 6 North - OH MEPF Rougth In
GBW-880 Floor 6 North - OH MEPF Rougth In Floor 6 Testing/Commissioning/Life Safety
-
05/01→05/14
6
Electrical
Install & Electronically Connect VFD's AHU 5-4
AHU5-4-1040 Install & Electronically Connect VFD's AHU 5-4 6th Floor AHU 5-4
-
05/01→05/07
6
HVAC/Mechanical
Set AHU 4-4
AHU4-4-1000 Set AHU 4-4 6th Floor AHU 4-4
-
05/01→05/07
7
Data
Install BMS Wiring
FL7-N1-230 Floor 7 - Install BMS Wiring Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/01→05/05
7
Flooring/Finishes
Prime & 1st Coat
FL7-N1-300 Floor 7 - Prime & 1st Coat Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/01→05/14
8
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
FL8-N1-540 Floor 8 - OH Duct/VAV Boxes Rough-In/Insulation Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/01→05/14
9A
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
9A-IR-N1-1300 Floor 9A - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) Floor 9A East Overhead Roughs
-
05/04→05/22
·
Drywall/Framing
Bridge - Exterior Wall Framing
BRIDGE-510 Bridge - Exterior Wall Framing New Bridge
-
05/04→05/15
·
Other
Bridge - Remove Temporary Shoring
BRIDGE-250 Bridge - Remove Temporary Shoring New Bridge
-
05/04→05/14
·
Concrete/Structure
Install Precast Panels Levels 6-8 (Set 5 WS)
SW-740 Install Precast Panels Levels 6-8 (Set 5 WS) Precast
-
05/04→05/07
·
Inspections/QC
Install Punch Windows - Set 4
EXG-1030 Install Punch Windows - Set 4 Exterior Glass & Glazing South Elevation (Punch Windows)
-
05/04→05/05
·
Concrete/Structure
Pour Steel Pan Stairs Level 10-Roof Stair 28
ST26W-395 Pour Steel Pan Stairs Level 10-Roof Stair 28 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
05/04→05/08
4
Flooring/Finishes
Floor 4 North - Prime & 1st Coat
GBW-670 Floor 4 North - Prime & 1st Coat Floor 4 Testing/Commissioning/Life Safety
-
05/04→05/05
4C
Inspections/QC
OH Inspections - MEPF
SC4C-N1-IR-280 Floor 4C - OH Inspections - MEPF Floor 4C SC 4.N1 Overhead Roughs
-
05/04→05/15
6
Other
6th Floor N6502 - Essential Power C Equipment Terminations
WE6-1050 6th Floor N6502 - Essential Power C Equipment Terminations West Essential - N6503 USS 6NEA
-
05/04→05/06
6
Electrical
6th Floor N6502 - Essential Power C Light Fixture Installation
WE6-1040 6th Floor N6502 - Essential Power C Light Fixture Installation West Essential - N6503 USS 6NEA
-
05/04→06/01
6
Drywall/Framing
6th Floor N6502 - Essential Power C UPS Battery Installation/Test
WE6-1080 6th Floor N6502 - Essential Power C UPS Battery Installation/Test West Essential - N6503 USS 6NEA
-
05/04→05/08
6
HVAC/Mechanical
Set AHU 3-2
AHU3-2-1000 Set AHU 3-2 6th Floor AHU 3-2
-
05/05→05/07
1
Concrete/Structure
Sheath/Inspect CW Box Beam Header
1EXT-120 Floor 01 - Sheath/Inspect CW Box Beam Header 1st Floor
-
05/05→05/18
2A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC2A-N2-F-270 Floor 2A - HVAC Drops & Diffusers/Grid Floor 2A SC 2.N2 Final Finishes
-
05/05→06/09
3B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Soffits
SC3B-N3-F-170 Floor 3B - Batt Insulation & Hang Drywall Bottom - Walls, Soffits Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
05/05→05/26
3B
Electrical
Electrical Rough in Hard Ceilings
SC3B-N3-F-110 Floor 3B - Electrical Rough in Hard Ceilings Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/05→05/18
3B
HVAC/Mechanical
HVAC Drops & Diffusers In Hard Lids
SC3B-N3-F-100 Floor 3B - HVAC Drops & Diffusers In Hard Lids Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/05→05/08
3B
Data
OH Low Voltage Pipe Rough-In
SC3B-N3-F-120 Floor 3B - OH Low Voltage Pipe Rough-In Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/05→05/18
3B
Plumbing
OR Ceilings Med Gas Connection to Clean Suite
SC3B-N3-IR-310 Floor 3B - OR Ceilings Med Gas Connection to Clean Suite Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/05→05/11
3C
Flooring/Finishes
Grout Bed for Tile
SC3C-N1-F-200 Floor 3C - Grout Bed for Tile Floor 3C SC 3.N1 Final Finishes
-
05/05→05/18
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders - Paralleling Gear C1E
CEPN-E-4070 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders - Paralleling Gear C1E Electrical 4th floor (Generator & Main Electrical Rooms)
-
05/05→05/29
4A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC4A-N2-F-170 Floor 4A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 4A SC 4.N2 Final Finishes
-
Tue 05/05
9
Flooring/Finishes
Floor 9 N9504 - Paint Plywood Back Boards
TEL-9-360 Floor 9 N9504 - Paint Plywood Back Boards Telecom Room Lv-9 N9504
-
05/06→05/19
1
Plumbing
OH Sanitary/Storm
FL1-30 Floor 1 - OH Sanitary/Storm INTERIOR CONSTRUCTION
-
05/06→05/12
3
Flooring/Finishes
Floor 3 South - Prime & 1st Coat
GBW-550 Floor 3 South - Prime & 1st Coat Floor 3 Go Back Work
-
05/06→05/21
4C
Drywall/Framing
Hang Drywall Ceilings
SC4C-N1-IR-310 Floor 4C - Hang Drywall Ceilings Floor 4C SC 4.N1 Overhead Roughs
-
05/06→05/12
5C
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC5C-N1-IR-210 Floor 5C - OH HVAC Piping/Controls/Insulation & QC Floor 5C SC 5.N1 Overhead Roughs
-
05/06→05/12
7
Data
All Low Voltage Devices
FL7-N1-360 Floor 7 - All Low Voltage Devices Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/06→05/15
7
Drywall/Framing
Floor 7 N7501 - Hang/Tape/Finish Wall Board
TEL-7-120 Floor 7 N7501 - Hang/Tape/Finish Wall Board Telecom Room Lv-7 N7501
-
05/06→05/12
7
Electrical
Floor 7 N7502 - Pull & Terminate Feeders
ELC-7-360 Floor 7 N7502 - Pull & Terminate Feeders Electrical Room Lv-7 N7502
-
05/06→05/07
7
Flooring/Finishes
Floor 7 N7504 - Prime & 1st Finish Coat
TEL-7-110 Floor 7 N7504 - Prime & 1st Finish Coat Telecom Room Lv-7 N7504
-
05/06→05/12
7
Electrical
Floor 7 N7505 - Pull & Terminate Feeders
ELC-7-390 Floor 7 N7505 - Pull & Terminate Feeders Electrical Room Lv-7 N7505
-
05/06→05/15
9
Drywall/Framing
Floor 9 N9501 - Hang/Tape/Finish Wall Board
TEL-9-120 Floor 9 N9501 - Hang/Tape/Finish Wall Board Telecom Room Lv-9 N9501
-
05/06→05/19
9
Electrical
Floor 9 N9502 - Pull & Terminate Feeders
ELC-9-200 Floor 9 N9502 - Pull & Terminate Feeders Electrical Room Lv-9 N9502 9A West, 9B West, 9C West
-
05/06→05/08
9
Electrical
Floor 9 N9504 - OH Conduit Rough-In
TEL-9-140 Floor 9 N9504 - OH Conduit Rough-In Telecom Room Lv-9 N9504
-
05/06→05/07
9
HVAC/Mechanical
Set AHU N9503
9-M-100 Set AHU N9503 Floor 9 Mechanical Space N9503
-
05/06→05/27
9A
Electrical
Electrical Terminations to Headwall
9A-IR-N1-1170 Floor 9A - Electrical Terminations to Headwall Floor 9A East Framing & Interior Roughs
-
05/06→05/19
9A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall & QC
9A-IR-N1-1160 Floor 9A - Med Gas Zone Valve Boxes/Terminations to Headwall & QC Floor 9A East Framing & Interior Roughs
-
05/06→06/03
9A
Electrical
OH-Electrical Rough/Racks Systems
9A-IR-N1-1030 Floor 9A - OH-Electrical Rough/Racks Systems Floor 9A East Overhead Roughs
-
05/06→05/14
9B
Other
Install Pre-Fab Headwalls
9B-IR-N2-1130 Floor 9B - Install Pre-Fab Headwalls West 9B West Framing & Interior Roughs
-
05/07→06/04
2
Concrete/Structure
CEP Floor 2 Build Catwalks & Remaining Steel
CEP-2-3990 CEP Floor 2 Build Catwalks & Remaining Steel 2nd Floor (Fuel Oil Systems)
-
05/07→05/20
2
Other
CEP Floor 2 Install Fuel Oil Tanks
CEP-2-3980 CEP Floor 2 Install Fuel Oil Tanks 2nd Floor (Fuel Oil Systems)
-
05/07→05/11
5A
Drywall/Framing
Frame Soffits/Hard Ceilings
SC5A-N2-IR-290 Floor 5A - Frame Soffits/Hard Ceilings Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/07→06/18
5B
Ceilings
OR Modular Prefab Ceilings Install Clean Suite (B-I Install)
SC5B-N3-IR-350 Floor 5B - OR Modular Prefab Ceilings Install Clean Suite (B-I Install) Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
05/07→05/13
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 5-5
AHU5-5-1020 AHU Drops/Duct Connections AHU 5-5 6th Floor AHU 5-5
-
05/07→05/13
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 5-5
AHU5-5-1010 AHU Drops/Piping Connections AHU 5-5 6th Floor AHU 5-5
-
05/08→05/12
1
Concrete/Structure
Apply Weather Barrier at Header
1EXT-130 Floor 01 - Apply Weather Barrier at Header 1st Floor
-
05/08→05/21
4
Other
Floor 4 South - In Wall MEPF Rough In
GBW-590 Floor 4 South - In Wall MEPF Rough In Floor 4 Testing/Commissioning/Life Safety
-
05/08→05/14
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 4-4
AHU4-4-1020 AHU Drops/Duct Connections AHU 4-4 6th Floor AHU 4-4
-
05/08→05/14
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 4-4
AHU4-4-1010 AHU Drops/Piping Connections AHU 4-4 6th Floor AHU 4-4
-
Fri 05/08
6
Milestone
Install TPO System & Accessories 6th Floor ◆
M590 Install TPO System & Accessories 6th Floor Construction Milestones
-
05/08→05/13
7
Other
Floor 7 N7504 - Install Plywood Back Boards
TEL-7-130 Floor 7 N7504 - Install Plywood Back Boards Telecom Room Lv-7 N7504
-
05/08→05/21
7
Electrical
Pull Branch Circuits
FL7-N1-260 Floor 7 - Pull Branch Circuits Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/08→05/14
9
HVAC/Mechanical
AHU Drops/Piping Connections AHU N9503
9-M-110 AHU Drops/Piping Connections AHU N9503 Floor 9 Mechanical Space N9503
-
05/11→05/15
2A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC2A-N2-F-310 Floor 2A - Drop Borders & Trade Cuts Ceiling Tiles Floor 2A SC 2.N2 Final Finishes
-
05/11→05/22
2A
Electrical
Light Fixtures in Grid
SC2A-N2-F-300 Floor 2A - Light Fixtures in Grid Floor 2A SC 2.N2 Final Finishes
-
05/11→05/15
2A
Electrical
Remove Temp Light Fixtures
SC2A-N2-F-290 Floor 2A - Remove Temp Light Fixtures Floor 2A SC 2.N2 Final Finishes
-
05/11→05/22
2C
Ceilings
Install Ceiling Grid
SC2C-N1-F-360 Floor 2C - Install Ceiling Grid Floor 2C SC 2.N1 Final Finishes
-
05/11→05/22
3B
Electrical
Install OH Cable Tray
SC3B-N3-F-160 Floor 3B - Install OH Cable Tray Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/11→06/01
4
Electrical
Floor 4 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-680 Floor 4 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 4 Testing/Commissioning/Life Safety
-
05/11→05/22
4C
Electrical
Electrical Rough in Hard Ceiling
SC4C-N1-F-120 Floor 4C - Electrical Rough in Hard Ceiling Floor 4C SC 4.N1 Final Finishes
-
05/11→05/15
4C
HVAC/Mechanical
HVAC Drops & Diffusers in Hard Ceiling
SC4C-N1-F-110 Floor 4C - HVAC Drops & Diffusers in Hard Ceiling Floor 4C SC 4.N1 Final Finishes
-
05/11→05/15
4C
Data
OH Low Voltage Pipe Rough-In
SC4C-N1-F-100 Floor 4C - OH Low Voltage Pipe Rough-In Floor 4C SC 4.N1 Overhead Roughs
-
05/11→06/08
5A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC5A-N2-IR-120 Floor 5A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 5A SC 5.N2raming & Interior Roughs
-
05/11→06/01
5A
Plumbing
In-Wall Plumbing Rough & QC
SC5A-N2-IR-130 Floor 5A - In-Wall Plumbing Rough & QC Floor 5A SC 5.N2raming & Interior Roughs
-
05/11→05/15
5A
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC5A-N2-IR-350 Floor 5A - OH Sprinkler Rough In & QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/11→05/12
5A
HVAC/Mechanical
Pneumatic Tube Stations Rough-In
SC5A-N2-IR-140 Floor 5A - Pneumatic Tube Stations Rough-In Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/11→05/15
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 3-2
AHU3-2-1020 AHU Drops/Duct Connections AHU 3-2 6th Floor AHU 3-2
-
05/11→05/15
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 3-2
AHU3-2-1010 AHU Drops/Piping Connections AHU 3-2 6th Floor AHU 3-2
-
05/11→05/22
6
Electrical
Floor 6 N6511 - Pull & Terminate Feeders
ELC-6-340 Floor 6 N6511 - Pull & Terminate Feeders Electrical Room Lv-6 N6511
-
05/11→05/14
9
Electrical
Floor 9 N9504 - Install Grounding Buss
TEL-9-170 Floor 9 N9504 - Install Grounding Buss Telecom Room Lv-9 N9504
-
05/12→05/14
3
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
EXT3-210 Floor 03 - Apply Fluid Applied Roofing on Eyebrow 3rd Floor
-
05/12→06/09
4B
HVAC/Mechanical
OR Modular Ceilings Ductwork & Clean-Suite Insulation
SC4B-N3-IR-400 Floor 4B - OR Modular Ceilings Ductwork & Clean-Suite Insulation Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
05/12→05/15
5A
Data
OH Low Voltage Pipe Rough-In
SC5A-N2-IR-125 Floor 5A - OH Low Voltage Pipe Rough-In Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/13→05/15
1
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
1EXT-190 Floor 01 - Fluid Applied Roofing At Edge Of Slab 1st Floor
-
05/13→05/20
2A
Fire/Sprinkler
Sprinkler Drops/Heads
SC2A-N2-F-330 Floor 2A - Sprinkler Drops/Heads Floor 2A SC 2.N2 Final Finishes
-
05/13→05/19
2B
Fire/Sprinkler
Fire Stopping/Labeling
SC2B-N3-F-180 Floor 2B - Fire Stopping/Labeling Floor 2B SC 2.N3
-
05/13→06/03
3
Electrical
Floor 3 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-560 Floor 3 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 3 Go Back Work
-
05/13→05/15
5A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
SC5A-N2-IR-320 Floor 5A - Med Gas Zone Valve Boxes/Terminations to Headwall Floor 5A SC 5.N2raming & Interior Roughs
-
05/13→05/19
5C
Electrical
Install OH Cable Tray
SC5C-N1-IR-330 Floor 5C - Install OH Cable Tray Floor 5C SC 5.N1 Overhead Roughs
-
05/13→05/19
5C
HVAC/Mechanical
Pneumatic Tube Stations Rough-In
SC5C-N1-IR-130 Floor 5C - Pneumatic Tube Stations Rough-In Floor 5C SC 5.N1 Overhead Roughs
-
05/14→05/18
·
HVAC/Mechanical
IMRIS R10 - OH Duct Installation
REV10-1770 IMRIS R10 - OH Duct Installation IMRIS Overhead Roughs - Rev. 10
-
05/14→05/18
·
Other
IMRIS R10 - Quench Vent Revisions
REV10-1310 IMRIS R10 - Quench Vent Revisions IMRIS Overhead Roughs - Rev. 10
-
05/14→05/21
·
Other
North - Set Up Access Platform System
NWW-300 North - Set Up Access Platform System North Window Washing Support Steel / Equipment
-
05/14→05/15
11
Other
Control Lines & Benchmarks
FL11-1000 Floor 11 - Control Lines & Benchmarks Floor 11 – Inpatient Acuity Adaptable Unit (34 Beds)
-
05/14→05/18
13
Concrete/Structure
Prep/Grind/Float Sill Curbs
13EXT-170 Floor 13 - Prep/Grind/Float Sill Curbs 13th Floor
-
05/14→07/17
3
Other
CEP Floor 3 - Install Control Valves & BMS System
CEPN-M-3040 CEP Floor 3 - Install Control Valves & BMS System Mechanical 3rd Flr (Chillers & Pumps)
-
05/14→05/28
3
Electrical
CEP Floor 3 - Install VFD's
CEPN-E-3000 CEP Floor 3 - Install VFD's Electrical 3rd Flr (Chillers & Pumps)
-
05/14→05/28
3
HVAC/Mechanical
CEP Floor 3 - Piping Drops to Chillers and Pumps
CEPN-M-3030 CEP Floor 3 - Piping Drops to Chillers and Pumps Mechanical 3rd Flr (Chillers & Pumps)
-
05/14→07/17
4
Electrical
Floor 4 (Gen& El. Rm.) - Rough-In Electrical to Mechanical Equipment
CEPN-E-4020 Floor 4 (Gen& El. Rm.) - Rough-In Electrical to Mechanical Equipment Electrical 4th floor (Generator & Main Electrical Rooms)
-
05/14→05/20
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 6-1
AHU6-1-1010 AHU Drops/Piping Connections AHU 6-1 6th Floor AHU 6-1
-
05/14→05/22
6
HVAC/Mechanical
BMS Controls AHU 5-5
AHU5-5-1030 BMS Controls AHU 5-5 6th Floor AHU 5-5
-
05/14→05/28
6
Electrical
Install & Electronically Connect VFD's AHU 5-5
AHU5-5-1040 Install & Electronically Connect VFD's AHU 5-5 6th Floor AHU 5-5
-
05/14→05/20
6
HVAC/Mechanical
Set AHU 3-5
AHU3-5-1000 Set AHU 3-5 6th Floor AHU 3-5
-
Thu 05/14
7
Flooring/Finishes
Floor 7 N7504 - Paint Plywood Back Boards
TEL-7-210 Floor 7 N7504 - Paint Plywood Back Boards Telecom Room Lv-7 N7504
-
05/15→05/26
·
Concrete/Structure
Install Precast Panels Levels 6-8 (Set 6 WS)
W-750 Install Precast Panels Levels 6-8 (Set 6 WS) Precast
-
05/15→05/20
·
Inspections/QC
Install Punch Windows - Set 5
EXG-1040 Install Punch Windows - Set 5 Exterior Glass & Glazing South Elevation (Punch Windows)
-
05/15→05/21
5
Flooring/Finishes
Floor 5 North - Prime & 1st Coat
GBW-790 Floor 5 North - Prime & 1st Coat Floor 5 Testing/Commissioning/Life Safety
-
05/15→05/29
6
Other
6th Floor N6508 - Essential Power B Equipment Terminations
EE6-1060 6th Floor N6508 - Essential Power B Equipment Terminations East Essential - N6508 USS 6NEB
-
05/15→05/19
6
Electrical
6th Floor N6508 - Essential Power B Light Fixture Installation
EE6-1050 6th Floor N6508 - Essential Power B Light Fixture Installation East Essential - N6508 USS 6NEB
-
05/15→05/21
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 5-1
AHU5-1-1010 AHU Drops/Piping Connections AHU 5-1 6th Floor AHU 5-1
-
05/15→05/26
6
HVAC/Mechanical
BMS Controls AHU 4-4
AHU4-4-1030 BMS Controls AHU 4-4 6th Floor AHU 4-4
-
05/15→05/29
6
Electrical
Install & Electronically Connect VFD's AHU 4-4
AHU4-4-1040 Install & Electronically Connect VFD's AHU 4-4 6th Floor AHU 4-4
-
05/15→05/29
6A
HVAC/Mechanical
Duct Sox
6A-1050 6A - Duct Sox 6A AHU
-
05/15→06/12
6B
HVAC/Mechanical
OH - AHU - Piping Mains
6B-1010 6B - OH - AHU - Piping Mains 6B AHU
-
05/15→05/19
7
Electrical
Floor 7 N7504 - OH Conduit Rough-In
TEL-7-140 Floor 7 N7504 - OH Conduit Rough-In Telecom Room Lv-7 N7504
-
05/15→05/21
9
HVAC/Mechanical
AHU Drops/Duct Connections 9th Floor N9503
9-M-120 AHU Drops/Duct Connections 9th Floor N9503 Floor 9 Mechanical Space N9503
-
Fri 05/15
9
Concrete/Structure
Floor 9 N9504 - Seal Concrete Floor
TEL-9-370 Floor 9 N9504 - Seal Concrete Floor Telecom Room Lv-9 N9504
-
05/15→06/05
9B
Electrical
Electrical Terminations to Headwall
9B-IR-N2-1170 Floor 9B - Electrical Terminations to Headwall West 9B West Framing & Interior Roughs
-
05/15→05/29
9B
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
9B-IR-N2-2010 Floor 9B - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) West 9B West Overhead Roughs
-
05/18→06/15
·
Drywall/Framing
Bridge - Start Exterior Framing and Dry-In
BRIDGE-260 Bridge - Start Exterior Framing and Dry-In New Bridge
-
05/18→05/27
·
Concrete/Structure
Install Exterior Louvers North
ELN-400 Install Exterior Louvers North Exterior Louvers
-
05/18→05/19
10
Flooring/Finishes
Floor 10 N10502 -Prime & 1st Finish Coat
ELC-10-150 Floor 10 N10502 -Prime & 1st Finish Coat Electrical Room Lv-10 N10502 10A west, 10B West, 10C West
-
05/18→06/08
10
Fire/Sprinkler
Floor 10 North - Firestopping, Layout, Frame & Insulate Walls
GBW-1170 Floor 10 North - Firestopping, Layout, Frame & Insulate Walls Floor 10 Testing/Commissioning/Life Safety
-
05/18→06/08
10A
Other
Install Pre-Fab Headwalls
10A-IR-N1-1130 Floor 10A - Install Pre-Fab Headwalls Floor 10A East Framing & Interior Roughs
-
05/18→06/08
11
Fire/Sprinkler
Floor 11 North - Firestopping, Layout, Frame & Insulate Walls
GBW-1320 Floor 11 North - Firestopping, Layout, Frame & Insulate Walls Floor 11 Testing/Commissioning/Life Safety
-
05/18→06/01
11
Plumbing
OH-Sanitary/Storm
FL11-1020 Floor 11 - OH-Sanitary/Storm Floor 11 – Inpatient Acuity Adaptable Unit (34 Beds)
-
05/18→06/08
11A
Other
Layout Walls & Trade Penetrations
11A-IR-N1-1100 Floor 11A - Layout Walls & Trade Penetrations Floor 11A East Framing & Interior Roughs
-
05/18→05/19
12
Other
Control Lines & Benchmarks
12-1000 Floor 12 - Control Lines & Benchmarks Floor 11 Clean & Punch-Out
-
05/18→06/08
1B
Fire/Sprinkler
OH Sprinkler Rough In & Mains - QC
SC1B-N1-IR-280 Floor 1B - OH Sprinkler Rough In & Mains - QC Floor 1B SC 1.N2 Overhead & Finishes
-
05/18→06/08
2A
Data
All Low Voltage Devices
SC2A-N2-F-340 Floor 2A - All Low Voltage Devices Floor 2A SC 2.N2 Final Finishes
-
05/18→06/01
2C
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC2C-N1-F-210 Floor 2C - Ceramic Tile / Grout - Bathrooms Floor 2C SC 2.N1 Final Finishes
-
05/18→05/22
5A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffits
SC5A-N2-F-100 Floor 5A - HVAC Drops & Diffusers in Soffits Floor 5A SC 5.N2 Final Finishes
-
05/18→05/19
5A
Plumbing
Med Gas Pre Certification
SC5A-N2-IR-340 Floor 5A - Med Gas Pre Certification Floor 5A SC 5.N2raming & Interior Roughs
-
05/18→06/15
5A
Plumbing
OH & In Wall MED Gas Rough In & QC
SC5A-N2-IR-220 Floor 5A - OH & In Wall MED Gas Rough In & QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/18→05/19
6
Other
6th Floor N6502 - Essential Power C Trim Out
WE6-1060 6th Floor N6502 - Essential Power C Trim Out West Essential - N6503 USS 6NEA
-
05/18→05/27
6
HVAC/Mechanical
BMS Controls AHU 3-2
AHU3-2-1030 BMS Controls AHU 3-2 6th Floor AHU 3-2
-
05/18→06/01
6
Electrical
Install & Electronically Connect VFD's AHU 3-2
AHU3-2-1040 Install & Electronically Connect VFD's AHU 3-2 6th Floor AHU 3-2
-
05/18→05/22
6
HVAC/Mechanical
Set AHU 5-2
AHU5-2-1000 Set AHU 5-2 6th Floor AHU 5-2
-
05/18→05/19
7
Flooring/Finishes
Floor 7 N7501 - Prime & 1st Finish Coat
TEL-7-150 Floor 7 N7501 - Prime & 1st Finish Coat Telecom Room Lv-7 N7501
-
05/18→05/19
9
Flooring/Finishes
Floor 9 N9501 - Prime & 1st Finish Coat
TEL-9-150 Floor 9 N9501 - Prime & 1st Finish Coat Telecom Room Lv-9 N9501
-
05/18→05/22
9
Data
Floor 9 N9504 - Install Racks & Ladder Tray
TEL-9-190 Floor 9 N9504 - Install Racks & Ladder Tray Telecom Room Lv-9 N9504
-
05/18→06/08
9
Fire/Sprinkler
Floor 9 North - Fire Stopping, Layout, Frame & Insulate Walls
GBW-1010 Floor 9 North - Fire Stopping, Layout, Frame & Insulate Walls Floor 9 Testing/Commissioning/Life Safety
-
05/19→05/26
·
Other
IMRIS R10 - Unistrut Install for R.F. Shield
REV10-1320 IMRIS R10 - Unistrut Install for R.F. Shield IMRIS Overhead Roughs - Rev. 10
-
05/19→05/21
13
Concrete/Structure
Fluid Applied Roofing At Sill Curbs
13EXT-180 Floor 13 - Fluid Applied Roofing At Sill Curbs 13th Floor
-
05/19→05/29
2C
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC2C-N1-F-400 Floor 2C - Drop Borders & Trade Cuts Ceiling Tiles Floor 2C SC 2.N1 Final Finishes
-
05/19→06/09
2C
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC2C-N1-F-370 Floor 2C - HVAC Drops & Diffusers/Grid Floor 2C SC 2.N1 Final Finishes
-
05/19→05/29
3A
Flooring/Finishes
Paint Prime & First Coat
SC3A-N2-F-230 Floor 3A - Paint Prime & First Coat Floor 3A SC 3.N2 Final Finishes
-
05/19→05/20
3B
Plumbing
Med Gas Pre Certification
SC3B-N3-IR-470 Floor 3B - Med Gas Pre Certification Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
05/19→05/29
3C
Drywall/Framing
Finish Drywall
SC3C-N1-F-220 Floor 3C - Finish Drywall Floor 3C SC 3.N1 Final Finishes
-
05/19→06/02
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Essential @ HVL EN 5 & 6 to Paralleling Gear
CEPN-E-4160 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Essential @ HVL EN 5 & 6 to Paralleling Gear Electrical 4th floor (Generator & Main Electrical Rooms)
-
05/19→06/16
5B
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC5B-N3-IR-200 Floor 5B - OH Duct/VAV Boxes Rough-In/Insulation Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
05/19→06/16
9A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
9A-IR-N1-1080 Floor 9A - OH Duct/VAV Boxes Rough-In/Insulation Floor 9A East Overhead Roughs
-
05/20→05/26
·
Concrete/Structure
Install Structural Steel - Penthouse
ST-1010 Install Structural Steel - Penthouse Elevator Penthouse Structure
-
05/20→05/27
10
Electrical
Floor 10 N10502 - Install Electrical Panels/Equipment
ELC-10-160 Floor 10 N10502 - Install Electrical Panels/Equipment Electrical Room Lv-10 N10502 10A west, 10B West, 10C West
-
05/20→06/03
12
Plumbing
OH-Sanitary/Storm
12-1030 Floor 12 - OH-Sanitary/Storm Floor 11 Clean & Punch-Out
-
05/20→06/10
12A
Other
Layout Walls & Trade Penetrations
12A-IR-N1-1000 Floor 12A - Layout Walls & Trade Penetrations Floor 12 A East Framing & Interior Roughs
-
05/20→05/21
13
Other
Control Lines & Benchmarks
13-1000 Floor 13 - Control Lines & Benchmarks Floor 13 Education Center, Conference Center, Administration Suite
-
05/20→05/27
4A
Fire/Sprinkler
Fire Stopping/Labeling
SC4A-N2-F-180 Floor 4A - Fire Stopping/Labeling Floor 4A SC 4.N2 Final Finishes
-
05/20→06/17
5C
Electrical
OH Electrical & I.T. Rough In & QC
SC5C-N1-IR-230 Floor 5C - OH Electrical & I.T. Rough In & QC Floor 5C SC 5.N1 Overhead Roughs
-
05/20→06/17
5C
Plumbing
OH Plumbing Rough In/Insulation & QC
SC5C-N1-IR-200 Floor 5C - OH Plumbing Rough In/Insulation & QC Floor 5C SC 5.N1 Overhead Roughs
-
05/20→06/17
6
Electrical
OH Electrical & I.T. Rough In & QC
FL6-1120 6th Floor - OH Electrical & I.T. Rough In & QC Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
05/20→05/26
7
Other
Floor 7 N7501 - Install Plywood Back Boards
TEL-7-160 Floor 7 N7501 - Install Plywood Back Boards Telecom Room Lv-7 N7501
-
05/20→05/26
7
Electrical
Floor 7 N7504 - Install Grounding Buss
TEL-7-170 Floor 7 N7504 - Install Grounding Buss Telecom Room Lv-7 N7504
-
05/20→06/03
7
Electrical
OH Electrical & I.T. Rough In & QC
FL7-N1-150 Floor 7 - OH Electrical & I.T. Rough In & QC Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/20→06/17
8
Electrical
OH Electrical & I.T. Rough In & QC
FL8-N1-560 Floor 8 - OH Electrical & I.T. Rough In & QC Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/20→05/26
9
Other
Floor 9 N9501 - Install Plywood Back Boards
TEL-9-160 Floor 9 N9501 - Install Plywood Back Boards Telecom Room Lv-9 N9501
-
05/20→05/21
9A
Plumbing
Med Gas Pre Certification
9A-F-N1-1345 Floor 9A - Med Gas Pre Certification Floor 9A East Final Finishes 9A
-
05/20→06/17
9B
Electrical
OH-Electrical Rough/Racks Systems
9B-IR-N2-1030 Floor 9B - OH-Electrical Rough/Racks Systems West 9B West Overhead Roughs
-
05/21→07/17
2
Other
CEP Floor 2 Install Fuel Oil Piping
CEP-2-4000 CEP Floor 2 Install Fuel Oil Piping 2nd Floor (Fuel Oil Systems)
-
05/21→06/09
4
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
4EXT-200 Floor 04 - Field Measure & Fab. Metal Drip Edge 4th Floor
-
05/21→06/18
5
Ceilings
Install EFIS Soffit/Caulk
5EXT-150 Floor 05 - Install EFIS Soffit/Caulk 5th Floor
-
05/21→05/28
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 3-5
AHU3-5-1020 AHU Drops/Duct Connections AHU 3-5 6th Floor AHU 3-5
-
05/21→05/28
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 3-5
AHU3-5-1010 AHU Drops/Piping Connections AHU 3-5 6th Floor AHU 3-5
-
05/21→06/01
6
HVAC/Mechanical
BMS Controls AHU 6-1
AHU6-1-1030 BMS Controls AHU 6-1 6th Floor AHU 6-1
-
05/21→06/04
6
Electrical
Install & Electronically Connect VFD's AHU 6-1
AHU6-1-1040 Install & Electronically Connect VFD's AHU 6-1 6th Floor AHU 6-1
-
05/21→06/18
9A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
9A-IR-N1-2000 Floor 9A - OH HVAC Piping/Controls/Insulation & QC Floor 9A East Overhead Roughs
-
05/22→06/05
·
Other
North - Install Monorails
NWW-320 North - Install Monorails North Window Washing Support Steel / Equipment
-
05/22→06/12
13
Other
Layout Walls & Trade Penetrations
13B-IR-N2-100 Floor 13 - Layout Walls & Trade Penetrations Floor 13 A Framing & Interior Roughs
-
05/22→05/27
13
Concrete/Structure
Layout for Box Beam Header
13EXT-100 Floor 13 - Layout for Box Beam Header 13th Floor
-
05/22→06/05
13
Plumbing
OH-Sanitary/Storm
13-1030 Floor 13 - OH-Sanitary/Storm Floor 13 Education Center, Conference Center, Administration Suite
-
05/22→06/19
4
Other
Floor 4 South - OH MEPF Rougth In
GBW-580 Floor 4 South - OH MEPF Rougth In Floor 4 Testing/Commissioning/Life Safety
-
05/22→06/12
5
Electrical
Floor 5 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-800 Floor 5 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 5 Testing/Commissioning/Life Safety
-
05/22→06/05
6
Electrical
Install & Electronically Connect VFD's AHU 5-1
AHU5-1-1040 Install & Electronically Connect VFD's AHU 5-1 6th Floor AHU 5-1
-
05/22→05/29
7
Data
Pull Wire For All Low Voltage Systems
FL7-N1-270 Floor 7 - Pull Wire For All Low Voltage Systems Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
05/22→06/02
9
HVAC/Mechanical
BMS Controls AHU N9503
9-M-160 BMS Controls AHU N9503 Floor 9 Mechanical Space N9503
-
05/26→06/29
·
Concrete/Structure
Bridge - Exterior EIFS System
BRIDGE-520 Bridge - Exterior EIFS System New Bridge
-
05/26→05/28
2C
Electrical
Remove Temp Light Fixtures
SC2C-N1-F-390 Floor 2C - Remove Temp Light Fixtures Floor 2C SC 2.N1 Final Finishes
-
05/26→06/02
2C
Fire/Sprinkler
Sprinkler Drops/Heads
SC2C-N1-F-430 Floor 2C - Sprinkler Drops/Heads Floor 2C SC 2.N1 Final Finishes
-
05/26→06/22
3B
Data
Pull All Low Voltage Cable
SC3B-N3-F-190 Floor 3B - Pull All Low Voltage Cable Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/26→06/01
4B
Inspections/QC
In-Wall Gilbane QC
SC4B-N3-IR-170 Floor 4B - In-Wall Gilbane QC Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
05/26→06/15
4B
Electrical
Install OH Cable Tray
SC4B-N3-IR-510 Floor 4B - Install OH Cable Tray Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
05/26→05/27
4C
Ceilings
Ceilings Gilbane QC
SC4C-N1-F-130 Floor 4C - Ceilings Gilbane QC Floor 4C SC 4.N1 Final Finishes
-
05/26→06/15
5A
Electrical
Electrical Rough in Soffits
SC5A-N2-IR-115 Floor 5A - Electrical Rough in Soffits Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/26→06/22
5A
Electrical
Pull Branch Circuits
SC5A-N2-IR-230 Floor 5A - Pull Branch Circuits Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
05/26→06/01
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 5-2
AHU5-2-1020 AHU Drops/Duct Connections AHU 5-2 6th Floor AHU 5-2
-
05/26→06/01
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 5-2
AHU5-2-1010 AHU Drops/Piping Connections AHU 5-2 6th Floor AHU 5-2
-
05/26→06/22
9A
Plumbing
OH Plumbing Rough In/Insulation & QC
9A-IR-N1-1110 Floor 9A - OH Plumbing Rough In/Insulation & QC Floor 9A East Overhead Roughs
-
05/27→06/09
·
Other
FRP Roof Over Hoistway - Elevator Penthouse
ST-1020 FRP Roof Over Hoistway - Elevator Penthouse Elevator Penthouse Structure
-
05/27→05/29
·
HVAC/Mechanical
IMRIS R10 - O.H. Ductwork @ Quench Vent
REV10-1330 IMRIS R10 - O.H. Ductwork @ Quench Vent IMRIS Overhead Roughs - Rev. 10
-
05/27→07/02
·
Concrete/Structure
Install Precast Panels Levels 8-12 (Set 7 WS)
SE-760 Install Precast Panels Levels 8-12 (Set 7 WS) Precast
-
05/27→06/01
·
Inspections/QC
Install Punch Windows - Set 6
EXG-1050 Install Punch Windows - Set 6 Exterior Glass & Glazing South Elevation (Punch Windows)
-
05/27→06/09
·
Other
Level 5 - Backwelding
BW-1030 Level 5 - Backwelding Detailing (Back Welding)
-
05/27→06/02
2C
Electrical
Light Fixtures in Grid
SC2C-N1-F-440 Floor 2C - Light Fixtures in Grid Floor 2C SC 2.N1 Final Finishes
-
05/27→06/09
3B
Electrical
Rough-in Can Lights
SC3B-N3-IR-490 Floor 3B - Rough-in Can Lights Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
05/27→06/30
4B
Drywall/Framing
Frame Soffits/Hard Ceilings
SC4B-N3-IR-300 Floor 4B - Frame Soffits/Hard Ceilings Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
Wed 05/27
7
Flooring/Finishes
Floor 7 N7501 - Paint Plywood Back Boards
TEL-7-190 Floor 7 N7501 - Paint Plywood Back Boards Telecom Room Lv-7 N7501
-
Wed 05/27
9
Flooring/Finishes
Floor 9 N9501 - Paint Plywood Back Boards
TEL-9-380 Floor 9 N9501 - Paint Plywood Back Boards Telecom Room Lv-9 N9501
-
05/28→06/10
10
Electrical
Floor 10 N10502 - Pull & Terminate Feeders
ELC-10-200 Floor 10 N10502 - Pull & Terminate Feeders Electrical Room Lv-10 N10502 10A west, 10B West, 10C West
-
05/28→06/10
13
Drywall/Framing
Frame/Inspect CW Box Beam Header
13EXT-110 Floor 13 - Frame/Inspect CW Box Beam Header 13th Floor
-
05/28→06/08
2B
Electrical
Light Fixtures in Soffit
SC2B-N3-F-250 Floor 2B - Light Fixtures in Soffit Floor 2B SC 2.N3
-
05/28→06/08
2B
Flooring/Finishes
Paint Prime & First Coat
SC2B-N3-F-230 Floor 2B - Paint Prime & First Coat Floor 2B SC 2.N3
-
05/28→05/29
4C
Drywall/Framing
Framing Inspections
SC4C-N1-F-150 Floor 4C - Framing Inspections Floor 4C SC 4.N1 Framing & Interior Roughs
-
05/28→05/29
4C
Ceilings
MEP Inspections in Hard Ceiling
SC4C-N1-F-160 Floor 4C - MEP Inspections in Hard Ceiling Floor 4C SC 4.N1 Final Finishes
-
05/28→06/01
7
Electrical
Floor 7 N7501 - OH Conduit Rough-In
TEL-7-180 Floor 7 N7501 - OH Conduit Rough-In Telecom Room Lv-7 N7501
-
05/28→06/01
9
Electrical
Floor 9 N9501 - OH Conduit Rough-In
TEL-9-180 Floor 9 N9501 - OH Conduit Rough-In Telecom Room Lv-9 N9501
-
05/29→06/18
3
Inspections/QC
CEP Floor 3 - AHCA 80% Inspection
CEPN-3-3270 CEP Floor 3 - AHCA 80% Inspection Build-Out 3rd Flr
-
05/29→07/02
3
Electrical
CEP Floor 3 - Install Conduit to Equipment
CEPN-E-3010 CEP Floor 3 - Install Conduit to Equipment Electrical 3rd Flr (Chillers & Pumps)
-
05/29→06/11
3
Other
CEP Floor 3 - Tie-in CHW Pipe Riser From 6th Floor Shaft
CEPN-M-3050 CEP Floor 3 - Tie-in CHW Pipe Riser From 6th Floor Shaft Mechanical 3rd Flr (Chillers & Pumps)
-
05/29→06/08
6
HVAC/Mechanical
BMS Controls AHU 3-5
AHU3-5-1030 BMS Controls AHU 3-5 6th Floor AHU 3-5
-
05/29→06/11
6
Electrical
Install & Electronically Connect VFD's AHU 3-5
AHU3-5-1040 Install & Electronically Connect VFD's AHU 3-5 6th Floor AHU 3-5
-
05/29→06/04
6
HVAC/Mechanical
Set AHU 4-5
AHU4-5-1000 Set AHU 4-5 6th Floor AHU 4-5
-
06/01→06/12
·
Other
IMRIS R10 - Process Water Piping
REV10-1340 IMRIS R10 - Process Water Piping IMRIS Overhead Roughs - Rev. 10
-
06/01→06/12
10A
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
10A-IR-N1-2020 Floor 10A - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) Floor 10A East Overhead Roughs
-
06/01→06/19
1A
Concrete/Structure
Install Curtain Wall System
SC1A-N2-IR-340 Floor 1A - Install Curtain Wall System Floor 1A SC 1.N1 Framing & Interior Roughs
-
06/01→06/10
1A
Other
Layout Walls & Trade Penetrations
SC1A-N2-IR-300 Floor 1A - Layout Walls & Trade Penetrations Floor 1A SC 1.N1 Framing & Interior Roughs
-
06/01→06/05
3A
Flooring/Finishes
Grout Bed for Tile
SC3C-N2-F-900 Floor 3A - Grout Bed for Tile Floor 3A SC 3.N2 Final Finishes
-
06/01→06/12
3A
Ceilings
Install Ceiling Grid
SC3A-N2-F-360 Floor 3A - Install Ceiling Grid Floor 3A SC 3.N2 Final Finishes
-
06/01→06/19
3A
Electrical
Light Fixtures in Soffit
SC3A-N2-F-250 Floor 3A - Light Fixtures in Soffit Floor 3A SC 3.N2 Final Finishes
-
06/01→06/26
3B
Drywall/Framing
Finish Drywall
SC3B-N3-F-220 Floor 3B - Finish Drywall Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
06/01→06/03
3C
Flooring/Finishes
Paint Prime & First Coat
SC3C-N1-F-230 Floor 3C - Paint Prime & First Coat Floor 3C SC 3.N1 Final Finishes
-
06/01→06/19
4A
Drywall/Framing
Finish Drywall
SC4A-N2-F-190 Floor 4A - Finish Drywall Floor 4A SC 4.N2 Final Finishes
-
06/01→06/05
4C
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC4C-N1-F-170 Floor 4C - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 4C SC 4.N1 Final Finishes
-
06/01→06/02
6
Other
6th Floor N6508 - Essential Power B Trim Out
EE6-1070 6th Floor N6508 - Essential Power B Trim Out East Essential - N6508 USS 6NEB
-
06/01→06/12
6
Drywall/Framing
Floor 6 North - Hang Drywall & Finish Drywall
GBW-900 Floor 6 North - Hang Drywall & Finish Drywall Floor 6 Testing/Commissioning/Life Safety
-
06/01→06/03
6A
HVAC/Mechanical
HVAC Trims
6A-1080 6A - HVAC Trims 6A AHU
-
06/02→06/08
·
Concrete/Structure
Install Exterior Louvers East
ELE-200 Install Exterior Louvers East Exterior Louvers
-
06/02→06/08
·
Inspections/QC
Install Punch Windows - Set 7
EXG-1060 Install Punch Windows - Set 7 Exterior Glass & Glazing South Elevation (Punch Windows)
-
06/02→06/29
11A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
11A-IR-N1-2080 Floor 11A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 11A East Framing & Interior Roughs
-
06/02→06/03
4B
Inspections/QC
In-Wall Inspections - MEPF
SC4B-N3-IR-180 Floor 4B - In-Wall Inspections - MEPF Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
06/02→06/08
5A
Inspections/QC
In-Wall Gilbane QC
SC5A-N2-IR-150 Floor 5A - In-Wall Gilbane QC Floor 5A SC 5.N2raming & Interior Roughs
-
06/02→06/10
6
HVAC/Mechanical
BMS Controls AHU 5-2
AHU5-2-1030 BMS Controls AHU 5-2 6th Floor AHU 5-2
-
06/02→06/15
6
Electrical
Install & Electronically Connect VFD's AHU 5-2
AHU5-2-1040 Install & Electronically Connect VFD's AHU 5-2 6th Floor AHU 5-2
-
06/02→06/15
6
Electrical
Install OH Cable Trays
FL6-20 6th Floor - Install OH Cable Trays Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
06/02→06/29
6
Plumbing
OH Plumbing Rough In/Insulation & QC
FL6-1080 6th Floor - OH Plumbing Rough In/Insulation & QC Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
06/02→06/08
6
HVAC/Mechanical
Set AHU 4-2
AHU4-2-1000 Set AHU 4-2 6th Floor AHU 4-2
-
06/02→06/08
6
HVAC/Mechanical
Set AHU 5-3
AHU5-3-1000 Set AHU 5-3 6th Floor AHU 5-3
-
06/02→06/15
6
HVAC/Mechanical
Set Pneumatic Equipment & OH Tubbing System
FL6-1210 6th Floor - Set Pneumatic Equipment & OH Tubbing System Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
06/02→06/05
7
Electrical
Floor 7 N7501 - Install Grounding Buss
TEL-7-200 Floor 7 N7501 - Install Grounding Buss Telecom Room Lv-7 N7501
-
06/02→06/05
9
Electrical
Floor 9 N9501 - Install Grounding Buss
TEL-9-200 Floor 9 N9501 - Install Grounding Buss Telecom Room Lv-9 N9501
-
06/02→06/22
9A
Plumbing
In Wall Med Gas RI
9A-IR-N1-1220 Floor 9A - In Wall Med Gas RI Floor 9A East Framing & Interior Roughs
-
06/02→06/22
9A
Plumbing
In-Wall Plumbing Rough QC
9A-IR-N1-1020 Floor 9A - In-Wall Plumbing Rough QC Floor 9A East Framing & Interior Roughs
-
06/03→06/09
3B
Fire/Sprinkler
Fire Stopping/Labeling
SC3B-N3-F-180 Floor 3B - Fire Stopping/Labeling Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
06/03→06/16
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders Generator
CEPN-E-4080 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders Generator Electrical 4th floor (Generator & Main Electrical Rooms)
-
06/03→06/30
4B
Plumbing
OR Modular Ceilings Med Gas Hangers & Piping Rough
SC4B-N3-IR-140 Floor 4B - OR Modular Ceilings Med Gas Hangers & Piping Rough Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
06/03→06/30
5B
Electrical
OH Electrical & I.T. Rough In & QC
SC5B-N3-IR-220 Floor 5B - OH Electrical & I.T. Rough In & QC Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
06/03→06/30
5B
Plumbing
OH Plumbing Rough In/Insulation & QC
SC5B-N3-IR-210 Floor 5B - OH Plumbing Rough In/Insulation & QC Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
06/03→06/16
9
Electrical
Install & Electronically Connect VFD's N9503
9-M-250 Install & Electronically Connect VFD's N9503 Floor 9 Mechanical Space N9503
-
06/03→06/30
9B
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
9B-IR-N2-1080 Floor 9B - OH Duct/VAV Boxes Rough-In/Insulation West 9B West Overhead Roughs
-
06/04→06/24
3C
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC3C-N1-F-210 Floor 3C - Ceramic Tile / Grout - Bathrooms Floor 3C SC 3.N1 Final Finishes
-
06/04→06/17
4B
Drywall/Framing
Blocking/Backing/Plywood
SC4B-N3-IR-260 Floor 4B - Blocking/Backing/Plywood Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
06/04→06/05
6A
HVAC/Mechanical
Mechanical Inspection
6A-1060 6A - Mechanical Inspection 6A AHU
-
06/04→06/17
7
Fire/Sprinkler
OH Sprinkler Rough In & QC
FL7-N1-140 Floor 7 - OH Sprinkler Rough In & QC Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/04→07/01
9A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
9A-IR-N1-1050 Floor 9A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 9A East Framing & Interior Roughs
-
06/05→06/18
2
Electrical
CEP Floor 2 Install Lighting, All Electrical & Low Voltage Devices
CEP-2-4040 CEP Floor 2 Install Lighting, All Electrical & Low Voltage Devices 2nd Floor (Fuel Oil Systems)
-
06/05→06/11
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 4-5
AHU4-5-1020 AHU Drops/Duct Connections AHU 4-5 6th Floor AHU 4-5
-
06/05→06/11
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 4-5
AHU4-5-1010 AHU Drops/Piping Connections AHU 4-5 6th Floor AHU 4-5
-
06/05→06/11
CEP
Concrete/Structure
Rev.7 CEP - Install Louvers
REV7-CEPPL-180 Rev.7 CEP - Install Louvers Rev.7 CEP Plenum Duct
-
06/08→06/09
·
Inspections/QC
North - Inspections Monorails
NWW-330 North - Inspections Monorails North Window Washing Support Steel / Equipment
-
06/08→06/26
3A
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC3C-N2-F-910 Floor 3A - Ceramic Tile / Grout - Bathrooms Floor 3A SC 3.N2 Final Finishes
-
06/08→06/19
3A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC3A-N2-F-370 Floor 3A - HVAC Drops & Diffusers/Grid Floor 3A SC 3.N2 Final Finishes
-
06/08→06/12
4C
Fire/Sprinkler
Fire Stopping/Labeling
SC4C-N1-F-180 Floor 4C - Fire Stopping/Labeling Floor 4C SC 4.N1 Final Finishes
-
06/08→06/12
4C
Flooring/Finishes
Grout Bed for Tile
SC4C-N1-F-200 Floor 4C - Grout Bed for Tile Floor 4C SC 4.N1 Final Finishes
-
06/08→06/11
4C
Flooring/Finishes
Moisture Mitigation for Tile
SC4C-N1-F-190 Floor 4C - Moisture Mitigation for Tile Floor 4C SC 4.N1 Final Finishes
-
Mon 06/08
7
Milestone
Building Weather Tight - 7th Floor ◆
M170 Building Weather Tight - 7th Floor Construction Milestones
-
Mon 06/08
9
Concrete/Structure
Floor 9 N9501 - Seal Concrete Floor
TEL-9-390 Floor 9 N9501 - Seal Concrete Floor Telecom Room Lv-9 N9501
-
06/09→06/11
10
Other
Floor 10 North - Set Pods
GBW-1180 Floor 10 North - Set Pods Floor 10 Testing/Commissioning/Life Safety
-
06/09→06/11
11A
Other
Stock Bathroom Pods
11A-IR-N1-1210 Floor 11A - Stock Bathroom Pods Floor 11A East Framing & Interior Roughs
-
06/09→07/07
1B
Electrical
OH Electrical Rough In, FA, Security, Data & QC
SC1B-N1-IR-170 Floor 1B - OH Electrical Rough In, FA, Security, Data & QC Floor 1B SC 1.N2 Overhead & Finishes
-
06/09→06/10
2A
Ceilings
Ceiling Grid QC
SC2A-N2-F-350 Floor 2A - Ceiling Grid QC Floor 2A SC 2.N2 Final Finishes
-
06/09→06/15
2B
Ceilings
Install Ceiling Grid
SC2B-N3-F-270 Floor 2B - Install Ceiling Grid Floor 2B SC 2.N3
-
06/09→07/07
2B
Flooring/Finishes
Rubber Flooring / Flooring
SC2B-N3-F-300 Floor 2B - Rubber Flooring / Flooring Floor 2B SC 2.N3
-
06/09→06/29
2C
Data
All Low Voltage Devices
SC2C-N1-F-450 Floor 2C - All Low Voltage Devices Floor 2C SC 2.N1 Final Finishes
-
06/09→06/11
3A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC3A-N2-F-400 Floor 3A - Drop Borders & Trade Cuts Ceiling Tiles Floor 3A SC 3.N2 Final Finishes
-
06/09→06/10
5A
Inspections/QC
In-Wall Inspections - MEPF
SC5A-N2-IR-160 Floor 5A - In-Wall Inspections - MEPF Floor 5A SC 5.N2raming & Interior Roughs
-
06/09→06/15
5A
Ceilings
Soffits & Ceilings Gilbane QC
SC5A-N2-F-130 Floor 5A - Soffits & Ceilings Gilbane QC Floor 5A SC 5.N2 Final Finishes
-
06/09→06/15
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 4-2
AHU4-2-1020 AHU Drops/Duct Connections AHU 4-2 6th Floor AHU 4-2
-
06/09→06/15
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 5-3
AHU5-3-1020 AHU Drops/Duct Connections AHU 5-3 6th Floor AHU 5-3
-
06/09→06/15
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 4-2
AHU4-2-1010 AHU Drops/Piping Connections AHU 4-2 6th Floor AHU 4-2
-
06/09→06/15
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 5-3
AHU5-3-1010 AHU Drops/Piping Connections AHU 5-3 6th Floor AHU 5-3
-
06/09→06/15
9
Data
Floor 9 N9501 - Install Racks & Ladder Tray
TEL-9-210 Floor 9 N9501 - Install Racks & Ladder Tray Telecom Room Lv-9 N9501
-
06/09→06/11
9
Other
Floor 9 North - Set Bathroom Pods
GBW-1070 Floor 9 North - Set Bathroom Pods Floor 9 Testing/Commissioning/Life Safety
-
06/10→06/16
·
Fire/Sprinkler
Level 5 - Perimeter Firestopping
FSP-1030 Level 5 - Perimeter Firestopping Firestopping
-
06/10→06/23
·
Other
Level 6 - Backwelding
BW-1040 Level 6 - Backwelding Detailing (Back Welding)
-
06/10→06/23
·
Concrete/Structure
North - Install Waterproofing Under Slab
NWW-340 North - Install Waterproofing Under Slab North Window Washing Support Steel / Equipment
-
06/10→06/16
3B
Inspections/QC
OH Gilbane QC
SC3B-N3-IR-420 Floor 3B - OH Gilbane QC Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
06/10→06/11
3B
Drywall/Framing
OR Ceilings Owner/AE Final Layout Approval Prior Drywall
SC3B-N3-IR-380 Floor 3B - OR Ceilings Owner/AE Final Layout Approval Prior Drywall Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
06/10→06/12
4
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
4EXT-210 Floor 04 - Apply Fluid Applied Roofing on Eyebrow 4th Floor
-
06/10→07/22
4B
Electrical
OR Ceilings Overhead Electrical & Lighting Rough
SC4B-N3-IR-340 Floor 4B - OR Ceilings Overhead Electrical & Lighting Rough Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
06/11→06/22
1
Drywall/Framing
N1503 - Hang/Tape/Finish Wall Board
TEL-1-100 Floor 1 - N1503 - Hang/Tape/Finish Wall Board Telecom Room Lv-1 N1503
-
06/11→06/15
12A
Other
Stock Bathroom Pods
12A-IR-N1-1220 Floor 12A - Stock Bathroom Pods Floor 12 A East Framing & Interior Roughs
-
06/11→07/01
12B
Other
Layout Walls & Trade Penetrations
12B-IR-N2-1000 Floor 12B - Layout Walls & Trade Penetrations Floor 12 B West Framing & Interior Roughs
-
06/11→06/15
13
Concrete/Structure
Sheath/Inspect CW Box Beam Header
13EXT-120 Floor 13 - Sheath/Inspect CW Box Beam Header 13th Floor
-
06/11→06/24
5A
Drywall/Framing
Blocking/Backing/Plywood
SC5A-N2-IR-240 Floor 5A - Blocking/Backing/Plywood Floor 5A SC 5.N2raming & Interior Roughs
-
06/12→06/25
10
Other
Floor 10 North - In Wall MEPF Rough In
GBW-1200 Floor 10 North - In Wall MEPF Rough In Floor 10 Testing/Commissioning/Life Safety
-
06/12→06/22
6
HVAC/Mechanical
BMS Controls AHU 4-5
AHU4-5-1030 BMS Controls AHU 4-5 6th Floor AHU 4-5
-
06/12→06/25
6
Electrical
Install & Electronically Connect VFD's AHU 4-5
AHU4-5-1040 Install & Electronically Connect VFD's AHU 4-5 6th Floor AHU 4-5
-
06/12→06/25
9
Other
Floor 9 North - In Wall MEPF Rough In
GBW-1030 Floor 9 North - In Wall MEPF Rough In Floor 9 Testing/Commissioning/Life Safety
-
06/12→06/18
CEP
HVAC/Mechanical
Rev.7 CEP - Install Plenum Duct
REV7-CEPPL-190 Rev.7 CEP - Install Plenum Duct Rev.7 CEP Plenum Duct
-
06/15→06/17
·
Other
IMRIS R10 - Wave Guide Connections Quench Vent
REV10-1350 IMRIS R10 - Wave Guide Connections Quench Vent IMRIS Overhead Roughs - Rev. 10
-
06/15→06/26
3
Other
CEP Floor 3 - Flush (CHW) Piping @ CEP to Floors 1-6
CEPN-M-3070 CEP Floor 3 - Flush (CHW) Piping @ CEP to Floors 1-6 Mechanical 3rd Flr (Chillers & Pumps)
-
06/15→07/06
3A
Data
All Low Voltage Devices
SC3A-N2-F-440 Floor 3A - All Low Voltage Devices Floor 3A SC 3.N2 Final Finishes
-
06/15→07/06
3A
Electrical
Light Fixtures in Grid
SC3A-N2-F-410 Floor 3A - Light Fixtures in Grid Floor 3A SC 3.N2 Final Finishes
-
06/15→06/19
3A
Fire/Sprinkler
Sprinkler Drops/Heads
SC3A-N2-F-430 Floor 3A - Sprinkler Drops/Heads Floor 3A SC 3.N2 Final Finishes
-
06/15→06/19
3C
Ceilings
Install Ceiling Grid
SC3C-N1-F-240 Floor 3C - Install Ceiling Grid Floor 3C SC 3.N1 Final Finishes
-
06/15→07/06
4C
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC4C-N1-F-220 Floor 4C - Ceramic Tile / Grout - Bathrooms Floor 4C SC 4.N1 Final Finishes
-
06/15→06/19
6
Flooring/Finishes
Floor 6 North - Prime & 1st Coat
GBW-910 Floor 6 North - Prime & 1st Coat Floor 6 Testing/Commissioning/Life Safety
-
06/15→06/26
6B
Other
6B N6505 - Steam Piping
6B-1060 6B N6505 - Steam Piping 6B AHU
-
06/16→06/18
·
Other
Bridge - Field Dimension Metal panels
BRIDGE-270 Bridge - Field Dimension Metal panels New Bridge
-
06/16→06/23
·
Concrete/Structure
CMU Level 13 Stair 26
STR-28-115 CMU Level 13 Stair 26 CMU Stairs 26 & 28
-
06/16→06/22
·
Concrete/Structure
Install Steel Pan Stairs Level 5-9 Stair 26
ST28E-240 Install Steel Pan Stairs Level 5-9 Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
06/16→06/25
10
Drywall/Framing
Floor 10 N10504 - Hang/Tape/Finish Wall Board
TEL-10-100 Floor 10 N10504 - Hang/Tape/Finish Wall Board Telecom Room Lv-10 N10504
-
06/16→06/17
10
Flooring/Finishes
Floor 10 N10505 - Prime & 1st Finish Coat
ELC-10-110 Floor 10 N10505 - Prime & 1st Finish Coat Electrical Room Lv-10 N10505 10A East, 10B West,10C West
-
06/16→06/17
10
HVAC/Mechanical
Set AHU N10503
10-M-100 Set AHU N10503 Floor 10 Mechanical Space N10503
-
06/16→06/29
11A
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
11A-IR-N1-2040 Floor 11A - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) Floor 11A East Overhead Roughs
-
06/16→06/18
13
Concrete/Structure
Apply Weather Barrier at Header
13EXT-130 Floor 13 - Apply Weather Barrier at Header 13th Floor
-
06/16→06/22
2B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC2B-N3-F-330 Floor 2B - Drop Borders & Trade Cuts Ceiling Tiles Floor 2B SC 2.N3
-
06/16→07/14
2B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC2B-N3-F-290 Floor 2B - HVAC Drops & Diffusers/Grid Floor 2B SC 2.N3
-
06/16→07/07
2B
Electrical
Light Fixtures in Grid
SC2B-N3-F-360 Floor 2B - Light Fixtures in Grid Floor 2B SC 2.N3
-
06/16→07/07
2B
Electrical
Remove Temp Light Fixtures
SC2B-N3-F-320 Floor 2B - Remove Temp Light Fixtures Floor 2B SC 2.N3
-
06/16→06/29
4C
Data
Pull Wire For All Low Voltage Systems
SC4C-N1-F-140 Floor 4C - Pull Wire For All Low Voltage Systems Floor 4C SC 4.N1 Overhead Roughs
-
06/16→06/22
5A
Ceilings
MEP Inspections in Soffits/Hard Lid
SC5A-N2-F-160 Floor 5A - MEP Inspections in Soffits/Hard Lid Floor 5A SC 5.N2 Final Finishes
-
06/16→06/22
5A
Inspections/QC
OH Gilbane QC
SC5A-N2-IR-280 Floor 5A - OH Gilbane QC Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
06/16→06/24
6
HVAC/Mechanical
BMS Controls AHU 4-2
AHU4-2-1060 BMS Controls AHU 4-2 6th Floor AHU 4-2
-
06/16→06/24
6
HVAC/Mechanical
BMS Controls AHU 5-3
AHU5-3-1030 BMS Controls AHU 5-3 6th Floor AHU 5-3
-
06/16→06/29
6
Electrical
Install & Electronically Connect VFD's AHU 4-2
AHU4-2-1150 Install & Electronically Connect VFD's AHU 4-2 6th Floor AHU 4-2
-
06/16→06/29
6
Electrical
Install & Electronically Connect VFD's AHU 5-3
AHU5-3-1040 Install & Electronically Connect VFD's AHU 5-3 6th Floor AHU 5-3
-
06/16→07/07
6
Data
Pull All Low Voltage Wire
FL6-70 6th Floor - Pull All Low Voltage Wire Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
06/16→06/22
6
HVAC/Mechanical
Set AHU 4-3
AHU4-3-1000 Set AHU 4-3 6th Floor AHU 4-3
-
06/17→06/30
1
HVAC/Mechanical
Temporary Power for Temp Cooling Units & AHUs Floor 1-6
TEMP-61-PWR Temporary Power for Temp Cooling Units & AHUs Floor 1-6 Temporary Cooling
-
06/17→06/18
3B
Inspections/QC
OH Inspections - MEPF
SC3B-N3-IR-450 Floor 3B - OH Inspections - MEPF Floor 3B SC 3.N3 (7 OR's) Overhead Roughs
-
06/17→06/30
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Essential Substation 4NQB(EN5-QB, EN6-QB)
CEPN-E-4140 Floor 4 (Gen& El. Rm.) - Pull/Terminate/Test Feeders 4th Floor Essential Substation 4NQB(EN5-QB, EN6-QB) Electrical 4th floor (Generator & Main Electrical Rooms)
-
06/17→06/30
5
Drywall/Framing
Floor 5 South - Layout, Frame & Insulate Walls
GBW-690 Floor 5 South - Layout, Frame & Insulate Walls Floor 5 Testing/Commissioning/Life Safety
-
06/17→07/15
5B
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC5B-N3-IR-230 Floor 5B - OH HVAC Piping/Controls/Insulation & QC Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
06/17→06/30
5B
HVAC/Mechanical
OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite
SC5B-N3-IR-370 Floor 5B - OR Modular Ceilings Install Ductwork Rough & Connections to Clean-Suite Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
06/17→06/30
9A
Fire/Sprinkler
OH Sprinkler Rough In & QC
9A-IR-N1-1140 Floor 9A - OH Sprinkler Rough In & QC Floor 9A East Overhead Roughs
-
06/18→06/24
·
Other
IMRIS R10 - Unistrut Install for MEPs
REV10-1360 IMRIS R10 - Unistrut Install for MEPs IMRIS Overhead Roughs - Rev. 10
-
06/18→06/29
10
Drywall/Framing
Floor 10 N10501 - Hang/Tape/Finish Wall Board
TEL-10-120 Floor 10 N10501 - Hang/Tape/Finish Wall Board Telecom Room Lv-10 N10501
-
06/18→06/24
10
Electrical
Floor 10 N10505 - Install Electrical Panels/Equipment
ELC-10-140 Floor 10 N10505 - Install Electrical Panels/Equipment Electrical Room Lv-10 N10505 10A East, 10B West,10C West
-
06/18→07/16
10A
Electrical
OH-Electrical Rough/Racks Systems
10A-IR-N1-1030 Floor 10A - OH-Electrical Rough/Racks Systems Floor 10A East Overhead Roughs
-
06/18→06/25
2B
Fire/Sprinkler
Sprinkler Drops/Heads
SC2B-N3-F-380 Floor 2B - Sprinkler Drops/Heads Floor 2B SC 2.N3
-
06/18→06/24
4B
Fire/Sprinkler
Fire Stopping/Labeling
SC4B-N3-F-180 Floor 4B - Fire Stopping/Labeling Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
06/18→06/19
4B
Drywall/Framing
Framing Inspections
SC4B-N3-F-160 Floor 4B - Framing Inspections Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
06/18→06/22
5C
Drywall/Framing
Frame Hard Ceilings
SC5C-N1-IR-250 Floor 5C - Frame Hard Ceilings Floor 5C SC 5.N1 Overhead Roughs
-
06/18→07/01
5C
Plumbing
In-Wall Plumbing Rough QC
SC5C-N1-IR-140 Floor 5C - In-Wall Plumbing Rough QC Floor 5C SC 5.N1 Framing & Interior Roughs
-
06/18→06/24
5C
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC5C-N1-IR-320 Floor 5C - OH Sprinkler Rough In & QC Floor 5C SC 5.N1 Overhead Roughs
-
06/18→07/15
6
Fire/Sprinkler
OH Sprinkler Rough In & QC
FL6-1170 6th Floor - OH Sprinkler Rough In & QC Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
06/18→07/16
7
Plumbing
OH Plumbing Rough In/Insulation & QC
FL7-N1-120 Floor 7 - OH Plumbing Rough In/Insulation & QC Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/18→06/24
8
Electrical
In Wall Electrical Rough-In
FL8-N1-590 Floor 8 - In Wall Electrical Rough-In Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/18→07/01
8
Fire/Sprinkler
OH Sprinkler Rough In & QC
FL8-N1-550 Floor 8 - OH Sprinkler Rough In & QC Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/18→07/16
9A
Electrical
OH Electrical & I.T. Rough In & QC
9A-IR-N1-1120 Floor 9A - OH Electrical & I.T. Rough In & QC Floor 9A East Overhead Roughs
-
06/18→06/24
9B
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
9B-IR-N2-1160 Floor 9B - Med Gas Zone Valve Boxes/Terminations to Headwall West 9B West Framing & Interior Roughs
-
06/19→07/10
·
Other
Bridge - Install Exterior Metal Panels
BRIDGE-500 Bridge - Install Exterior Metal Panels New Bridge
-
06/19→06/23
13
Concrete/Structure
Fluid Applied Roofing At Edge Of Slab
13EXT-190 Floor 13 - Fluid Applied Roofing At Edge Of Slab 13th Floor
-
06/19→07/17
3B
Drywall/Framing
Hang/Tape/Finish Drywall OR Ceilings
SC3B-N3-F-531 Floor 3B - Hang/Tape/Finish Drywall OR Ceilings Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
06/19→07/08
5
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
5EXT-200 Floor 05 - Field Measure & Fab. Metal Drip Edge 5th Floor
-
06/19→07/10
6
Ceilings
Install EFIS Soffit/Caulk
6EXT-150 Floor 06 - Install EFIS Soffit/Caulk 6th Floor
-
06/19→07/02
9B
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
9B-IR-N2-2000 Floor 9B - OH HVAC Piping/Controls/Insulation & QC West 9B West Overhead Roughs
-
06/22→07/13
1A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rms
SC1A-N2-IR-290 Floor 1A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rms Floor 1A SC 1.N1 Framing & Interior Roughs
-
06/22→06/24
3C
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC3C-N1-F-350 Floor 3C - Drop Borders & Trade Cuts Ceiling Tiles Floor 3C SC 3.N1 Final Finishes
-
06/22→06/26
3C
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC3C-N1-F-340 Floor 3C - HVAC Drops & Diffusers/Grid Floor 3C SC 3.N1 Final Finishes
-
06/22→06/24
3C
Electrical
Light Fixtures in Hard Ceilings
SC3C-N1-F-270 Floor 3C - Light Fixtures in Hard Ceilings Floor 3C SC 3.N1 Final Finishes
-
06/22→07/06
4
Drywall/Framing
Floor 4 South - Hang Drywall & Finish Drywall
GBW-600 Floor 4 South - Hang Drywall & Finish Drywall Floor 4 Testing/Commissioning/Life Safety
-
06/22→06/24
4A
Flooring/Finishes
Paint Prime & First Coat
SC4A-N2-F-230 Floor 4A - Paint Prime & First Coat Floor 4A SC 4.N2 Final Finishes
-
06/22→07/13
4B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Soffits
SC4B-N3-F-170 Floor 4B - Batt Insulation & Hang Drywall Bottom - Walls, Soffits Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
06/22→07/01
4C
Drywall/Framing
Finish Drywall
SC4C-N1-F-210 Floor 4C - Finish Drywall Floor 4C SC 4.N1 Final Finishes
-
06/22→07/13
5C
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC5C-N1-IR-150 Floor 5C - In-Wall Electrical & I.T. Rough In & Control & QC Floor 5C SC 5.N1 Framing & Interior Roughs
-
06/22→07/13
6
Electrical
Floor 6 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-920 Floor 6 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 6 Testing/Commissioning/Life Safety
-
06/23→06/24
·
Concrete/Structure
Pour Steel Pan Stairs Level 5-9 Stair 26
ST28E-245 Pour Steel Pan Stairs Level 5-9 Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
06/23→06/24
1
Flooring/Finishes
N1503 - Paint Room
TEL-1-110 Floor 1 - N1503 - Paint Room Telecom Room Lv-1 N1503
-
Tue 06/23
5A
Inspections/QC
OH Inspections - MEPF
SC5A-N2-IR-300 Floor 5A - OH Inspections - MEPF Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
06/23→07/14
5C
Electrical
Electrical Rough in Hard Ceiling
SC5C-N1-F-120 Floor 5C - Electrical Rough in Hard Ceiling Floor 5C SC 5.N1 Overhead Roughs
-
06/23→06/29
5C
HVAC/Mechanical
HVAC Drops & Diffusers in Hard Ceiling
SC5C-N1-F-110 Floor 5C - HVAC Drops & Diffusers in Hard Ceiling Floor 5C SC 5.N1 Final Finishes
-
06/23→06/26
5C
Data
OH Low Voltage Pipe Rough-In
SC5C-N1-F-100 Floor 5C - OH Low Voltage Pipe Rough-In Floor 5C SC 5.N1 Overhead Roughs
-
06/23→06/29
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 4-3
AHU4-3-1020 AHU Drops/Duct Connections AHU 4-3 6th Floor AHU 4-3
-
06/23→06/29
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 4-3
AHU4-3-1010 AHU Drops/Piping Connections AHU 4-3 6th Floor AHU 4-3
-
06/23→07/21
9B
Plumbing
OH Plumbing Rough In/Insulation & QC
9B-IR-N2-1110 Floor 9B - OH Plumbing Rough In/Insulation & QC West 9B West Overhead Roughs
-
06/24→07/08
·
Other
Level 1 - Backwelding
BW-1050 Level 1 - Backwelding Detailing (Back Welding)
-
06/24→06/30
·
Fire/Sprinkler
Level 6 - Perimeter Firestopping
FSP-1040 Level 6 - Perimeter Firestopping Firestopping
-
06/24→06/25
·
Concrete/Structure
North - Inspections Waterproofing
NWW-350 North - Inspections Waterproofing North Window Washing Support Steel / Equipment
-
06/24→06/30
4B
Electrical
Electrical Rough in Soffits
SC4B-N3-F-110 Floor 4B - Electrical Rough in Soffits Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
06/24→07/22
4B
Electrical
OR Modular Ceilings Electrical Rough to Clean-Suite
SC4B-N3-IR-380 Floor 4B - OR Modular Ceilings Electrical Rough to Clean-Suite Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
06/24→06/26
5A
Drywall/Framing
Hang Drywall Ceilings
SC5A-N2-IR-310 Floor 5A - Hang Drywall Ceilings Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
06/25→06/29
·
Fire/Sprinkler
IMRIS R10 - Sprinkler Rough In
REV10-1370 IMRIS R10 - Sprinkler Rough In IMRIS Overhead Roughs - Rev. 10
-
06/25→06/26
·
Concrete/Structure
Pour Steel Pan Stairs Level 10-Roof Stair 26
ST28E-275 Pour Steel Pan Stairs Level 10-Roof Stair 26 Stair Towers Steel Pan Stairs 26 West, 27 Elevator, 28 East
-
06/25→06/30
1
Other
N1503 - Install Plywood Back Boards
TEL-1-120 Floor 1 - N1503 - Install Plywood Back Boards Telecom Room Lv-1 N1503
-
06/25→07/09
10
Electrical
Floor 10 N10505 - Pull & Terminate Feeders
ELC-10-170 Floor 10 N10505 - Pull & Terminate Feeders Electrical Room Lv-10 N10505 10A East, 10B West,10C West
-
06/25→07/01
3C
Fire/Sprinkler
Sprinkler Drops/Heads
SC3C-N1-F-400 Floor 3C - Sprinkler Drops/Heads Floor 3C SC 3.N1 Final Finishes
-
06/25→06/26
4A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC4A-N1-F-900 Floor 4A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 4A SC 4.N2 Final Finishes
-
06/25→07/01
4A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffits
SC4A-N2-F-110 Floor 4A - HVAC Drops & Diffusers in Soffits Floor 4A SC 4.N2 Final Finishes
-
06/25→07/01
4A
Ceilings
Install Ceiling Grid
SC4A-N2-F-250 Floor 4A - Install Ceiling Grid Floor 4A SC 4.N2 Final Finishes
-
06/25→07/01
4A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC4A-N2-F-370 Floor 4A - Install Special Wall Finishes (incl. Wall Protection) Floor 4A SC 4.N2 Final Finishes
-
06/25→07/16
4A
Electrical
Light Fixtures in Soffit
SC4A-N2-F-260 Floor 4A - Light Fixtures in Soffit Floor 4A SC 4.N2 Final Finishes
-
06/25→06/26
5A
Drywall/Framing
Framing Inspections
SC5A-N2-F-150 Floor 5A - Framing Inspections Floor 5A SC 5.N2raming & Interior Roughs
-
06/25→07/01
5C
Inspections/QC
OH Gilbane QC
SC5C-N1-IR-240 Floor 5C - OH Gilbane QC Floor 5C SC 5.N1 Overhead Roughs
-
06/25→06/26
8
Data
Install BMS Wiring
FL8-N1-640 Floor 8 - Install BMS Wiring Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/25→07/09
8
Electrical
Pull Branch Circuits
FL8-N1-670 Floor 8 - Pull Branch Circuits Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/25→07/23
9A
Electrical
Pull Branch Circuits
9A-IR-N1-1240 Floor 9A - Pull Branch Circuits Floor 9A East Overhead Roughs
-
06/25→06/26
9B
Plumbing
Med Gas Pre Certification
9B-IR-N2-1210 Floor 9B - Med Gas Pre Certification West 9B West Framing & Interior Roughs
-
06/26→07/17
·
Concrete/Structure
North - Install EIFS System
NWW-360 North - Install EIFS System North Window Washing Support Steel / Equipment
-
06/26→06/29
10
Flooring/Finishes
Floor 10 N10504- Prime & 1st Finish Coat
TEL-10-110 Floor 10 N10504- Prime & 1st Finish Coat Telecom Room Lv-10 N10504
-
06/26→07/24
10
Other
Floor 10 North - OH MEPF Rougth In
GBW-1190 Floor 10 North - OH MEPF Rougth In Floor 10 Testing/Commissioning/Life Safety
-
06/26→07/24
9
Other
Floor 9 North - OH MEPF Rougth In
GBW-1020 Floor 9 North - OH MEPF Rougth In Floor 9 Testing/Commissioning/Life Safety
-
06/29→07/01
3
Other
CEP Floor 3 - Install Temporary Flushing Pump for Floors 7-13
CEPN-M-3090 CEP Floor 3 - Install Temporary Flushing Pump for Floors 7-13 Mechanical 3rd Flr (Chillers & Pumps)
-
06/29→08/03
3
Other
CEP Floor 3 - Insulate CHW Piping
CEPN-M-3080 CEP Floor 3 - Insulate CHW Piping Mechanical 3rd Flr (Chillers & Pumps)
-
06/29→07/06
4A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC4A-N1-F-910 Floor 4A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 4A SC 4.N2 Final Finishes
-
06/29→07/23
5A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC5A-N2-F-170 Floor 5A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 5A SC 5.N2 Final Finishes
-
06/29→07/01
6B
Other
Condensate
6B-1130 6B - Condensate 6B AHU
-
06/29→07/07
6B
Other
Fan Coils
6B-1120 6B - Fan Coils 6B AHU
-
06/29→07/06
8
Drywall/Framing
Hang Drywall
FL8-N1-620 Floor 8 - Hang Drywall Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/30→07/14
·
Other
Bridge - Roof Detailing
BRIDGE-290 Bridge - Roof Detailing New Bridge
-
06/30→07/02
·
Electrical
IMRIS R10 - O.H. Electrical (Below Shield)
REV10-1380 IMRIS R10 - O.H. Electrical (Below Shield) IMRIS Overhead Roughs - Rev. 10
-
06/30→07/01
10
Flooring/Finishes
Floor 10 N10501 - Prime & 1st Finish Coat
TEL-10-150 Floor 10 N10501 - Prime & 1st Finish Coat Telecom Room Lv-10 N10501
-
06/30→07/06
10
Other
Floor 10 N10504 - Install Plywood Back Boards
TEL-10-130 Floor 10 N10504 - Install Plywood Back Boards Telecom Room Lv-10 N10504
-
06/30→07/14
10A
Data
OH Low Voltage Pipe Rough-In
10A-IR-N1-1235 Floor 10A - OH Low Voltage Pipe Rough-In Floor 10A East Overhead Roughs
-
06/30→07/10
11
Drywall/Framing
Floor 11 (N11504) - Hang/Tape/Finish Wall Board
TEL-11-100 Floor 11 (N11504) - Hang/Tape/Finish Wall Board Telecom Room Lv-11 N11504
-
06/30→07/01
11
Flooring/Finishes
Floor 11 (N11505) - Prime & 1st Finish Coat
ELC-11-110 Floor 11 (N11505) - Prime & 1st Finish Coat Electrical Room Lv-11 N11505 11A East, 11B East, 11C East
-
06/30→07/21
2B
Data
All Low Voltage Devices
SC2B-N3-F-390 Floor 2B - All Low Voltage Devices Floor 2B SC 2.N3
-
06/30→07/01
2C
Ceilings
Ceiling Grid QC
SC2C-N1-F-470 Floor 2C - Ceiling Grid QC Floor 2C SC 2.N1 Final Finishes
-
06/30→07/21
5A
Data
Pull Wire For All Low Voltage Systems
SC5A-N2-F-140 Floor 5A - Pull Wire For All Low Voltage Systems Floor 5A SC 5.N2 PACU/Prep + 4 OR's
-
06/30→07/09
6
HVAC/Mechanical
BMS Controls AHU 4-3
AHU4-3-1030 BMS Controls AHU 4-3 6th Floor AHU 4-3
-
06/30→07/14
6
Electrical
Install & Electronically Connect VFD's AHU 4-3
AHU4-3-1040 Install & Electronically Connect VFD's AHU 4-3 6th Floor AHU 4-3
-
06/30→07/07
6
HVAC/Mechanical
Set AHU 3-3
AHU3-3-1000 Set AHU 3-3 6th Floor AHU 3-3
-
Wed 07/01
1
Flooring/Finishes
N1503 - Paint Plywood Back Boards
TEL-1-350 Floor 1 - N1503 - Paint Plywood Back Boards Telecom Room Lv-1 N1503
-
07/01→07/29
10A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
10A-IR-N1-1080 Floor 10A - OH Duct/VAV Boxes Rough-In/Insulation Floor 10A East Overhead Roughs
-
07/01→07/29
11A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
11A-IR-N1-1060 Floor 11A - OH Duct/VAV Boxes Rough-In/Insulation Floor 11A East Overhead Roughs
-
07/01→07/22
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull 15KV Feeders From CEPN 4th Floor HVL-D1-1 and C1-1 to Floor. 6th (SDJC1-1, SDJD1-1)
CEPN-E-4231 Floor 4 (Gen& El. Rm.) - Pull 15KV Feeders From CEPN 4th Floor HVL-D1-1 and C1-1 to Floor. 6th (SDJC1-1, SDJD1-1) Electrical 4th floor (Generator & Main Electrical Rooms)
-
07/01→07/08
4B
HVAC/Mechanical
HVAC Drops & Diffusers in Soffits
SC4B-N3-F-100 Floor 4B - HVAC Drops & Diffusers in Soffits Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
07/01→07/07
4B
Data
OH Low Voltage Pipe Rough-In
SC4B-N3-F-120 Floor 4B - OH Low Voltage Pipe Rough-In Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
07/01→07/15
4B
Plumbing
OR Ceilings Med Gas Connection to Clean Suite
SC4B-N3-IR-360 Floor 4B - OR Ceilings Med Gas Connection to Clean Suite Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
07/01→07/15
5
Other
Floor 5 South - In Wall MEPF Rough In
GBW-710 Floor 5 South - In Wall MEPF Rough In Floor 5 Testing/Commissioning/Life Safety
-
07/01→07/22
5B
Plumbing
In-Wall Plumbing Rough QC
SC5B-N3-IR-150 Floor 5B - In-Wall Plumbing Rough QC Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/01→07/29
5B
HVAC/Mechanical
OR Modular Ceilings Ductwork & Clean-Suite Insulation
SC5B-N3-IR-400 Floor 5B - OR Modular Ceilings Ductwork & Clean-Suite Insulation Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/01→07/15
6
Drywall/Framing
Floor 6 South - Layout, Frame & Insulate Walls
GBW-810 Floor 6 South - Layout, Frame & Insulate Walls Floor 6 Testing/Commissioning/Life Safety
-
07/01→07/08
6
Other
Install Temporary ACC With Pumps
TEMP-33-PUMPS Install Temporary ACC With Pumps Temporary Cooling
-
07/01→07/15
6
Other
Install Temporary Cooling Units Floor
TEMP-11 Install Temporary Cooling Units Floor Temporary Cooling
-
07/01→07/08
6
Electrical
Temporary Electrical Start-Up on 6th Floor Tower
TEMP-13 Temporary Electrical Start-Up on 6th Floor Tower Temporary Cooling
-
07/01→07/15
9A
Electrical
Install OH Cable Tray
9A-F-N1-1120 Floor 9A - Install OH Cable Tray Floor 9A East Overhead Roughs
-
07/01→07/13
9B
Fire/Sprinkler
OH Sprinkler Rough In& QC
9B-IR-N2-1140 Floor 9B - OH Sprinkler Rough In& QC West 9B West Overhead Roughs
-
07/02→07/07
1
Electrical
N1503 - OH Conduit Rough-In
TEL-1-130 Floor 1 - N1503 - OH Conduit Rough-In Telecom Room Lv-1 N1503
-
07/02→07/08
10
Other
Floor 10 N10501 - Install Plywood Back Boards
TEL-10-160 Floor 10 N10501 - Install Plywood Back Boards Telecom Room Lv-10 N10501
-
07/02→07/14
11
Drywall/Framing
Floor 11 (N11501) - Hang/Tape/Finish Wall Board
TEL-11-120 Floor 11 (N11501) - Hang/Tape/Finish Wall Board Telecom Room Lv-11 N11501
-
07/02→07/09
11
Electrical
Floor 11 (N11505) - Install Electrical Panels/Equipment
ELC-11-150 Floor 11 (N11505) - Install Electrical Panels/Equipment Electrical Room Lv-11 N11505 11A East, 11B East, 11C East
-
07/02→07/07
12B
Other
Stock Bathroom Pods
12B-IR-N2-1220 Floor 12B - Stock Bathroom Pods Floor 12 B West Framing & Interior Roughs
-
07/02→07/09
4A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC4A-N2-F-300 Floor 4A - Drop Borders & Trade Cuts Ceiling Tiles Floor 4A SC 4.N2 Final Finishes
-
07/02→07/07
4C
Flooring/Finishes
Paint Prime & First Coat
SC4C-N1-F-230 Floor 4C - Paint Prime & First Coat Floor 4C SC 4.N1 Final Finishes
-
07/02→07/06
5C
Inspections/QC
OH Inspections - MEPF
SC5C-N1-IR-280 Floor 5C - OH Inspections - MEPF Floor 5C SC 5.N1 Overhead Roughs
-
07/02→07/30
9B
Electrical
OH Electrical & I.T. Rough In & QC
9B-IR-N2-1120 Floor 9B - OH Electrical & I.T. Rough In & QC West 9B West Overhead Roughs
-
07/06→07/10
·
Electrical
IMRIS R10 - Cable Tray
REV10-1390 IMRIS R10 - Cable Tray IMRIS Overhead Roughs - Rev. 10
-
07/06→07/28
·
Concrete/Structure
Install Precast Panels Levels 8-12 (Set 8 WS)
E-770 Install Precast Panels Levels 8-12 (Set 8 WS) Precast
-
07/06→07/24
10A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
10A-IR-N1-2000 Floor 10A - OH HVAC Piping/Controls/Insulation & QC Floor 10A East Overhead Roughs
-
07/06→07/24
3
Other
CEP Floor 3 - Pull Cable to Equipment & Terminate
CEPN-E-3020 CEP Floor 3 - Pull Cable to Equipment & Terminate Electrical 3rd Flr (Chillers & Pumps)
-
07/06→07/07
9A
Inspections/QC
In-Wall Inspections - MEPF
9A-IR-N1-1070 Floor 9A - In-Wall Inspections - MEPF Floor 9A East Framing & Interior Roughs
-
Tue 07/07
10
Flooring/Finishes
Floor 10 N10504 - Paint Plywood Back Boards
TEL-10-360 Floor 10 N10504 - Paint Plywood Back Boards Telecom Room Lv-10 N10504
-
07/07→07/09
13
Concrete/Structure
Level 13 - Prime & Torch Membrane (Includes 28 Day Concrete Cure)
L13RA-095 Level 13 - Prime & Torch Membrane (Includes 28 Day Concrete Cure) Level 13 Roofing & Assembly
-
07/07→07/08
3A
Ceilings
Ceiling Grid QC
SC3A-N2-F-480 Floor 3A - Ceiling Grid QC Floor 3A SC 3.N2 Final Finishes
-
07/07→07/09
3A
Electrical
Remove Temp Light Fixtures
SC3A-N2-F-390 Floor 3A - Remove Temp Light Fixtures Floor 3A SC 3.N2 Final Finishes
-
07/07→07/27
3C
Data
All Low Voltage Devices
SC3C-N1-F-410 Floor 3C - All Low Voltage Devices Floor 3C SC 3.N1 Final Finishes
-
07/07→07/20
3C
Electrical
Light Fixtures in Grid
SC3C-N1-F-420 Floor 3C - Light Fixtures in Grid Floor 3C SC 3.N1 Final Finishes
-
07/07→07/13
4
Flooring/Finishes
Floor 4 South - Prime & 1st Coat
GBW-610 Floor 4 South - Prime & 1st Coat Floor 4 Testing/Commissioning/Life Safety
-
07/07→07/13
4A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC4A-N1-F-920 Floor 4A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 4A SC 4.N2 Final Finishes
-
07/07→07/15
5C
Drywall/Framing
Hang Drywall Ceilings
SC5C-N1-IR-310 Floor 5C - Hang Drywall Ceilings Floor 5C SC 5.N1 Overhead Roughs
-
07/07→07/13
8
Drywall/Framing
Tape & Finish
FL8-N1-630 Floor 8 - Tape & Finish Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/08→07/13
1
Electrical
N1503 - Install Grounding Buss
TEL-1-140 Floor 1 - N1503 - Install Grounding Buss Telecom Room Lv-1 N1503
-
07/08→07/10
10
Electrical
Floor 10 N10504 - OH Conduit Rough-In
TEL-10-140 Floor 10 N10504 - OH Conduit Rough-In Telecom Room Lv-10 N10504
-
07/08→08/04
10A
Plumbing
OH Plumbing Rough In/Insulation & QC
10A-IR-N1-1110 Floor 10A - OH Plumbing Rough In/Insulation & QC Floor 10A East Overhead Roughs
-
07/08→07/17
10A
Fire/Sprinkler
OH Sprinkler Rough In& QC
10A-IR-N1-1140 Floor 10A - OH Sprinkler Rough In& QC Floor 10A East Overhead Roughs
-
07/08→07/10
11
Other
Floor 11 North - Set Bathroom Pods
GBW-1330 Floor 11 North - Set Bathroom Pods Floor 11 Testing/Commissioning/Life Safety
-
07/08→07/21
11A
Other
Install Pre-Fab Headwalls
11A-IR-N1-1130 Floor 11A - Install Pre-Fab Headwalls Floor 11A East Framing & Interior Roughs
-
07/08→07/28
12
Fire/Sprinkler
Floor 12 North - Firestopping, Layout, Frame & Insulate Walls
GBW-1470 Floor 12 North - Firestopping, Layout, Frame & Insulate Walls Floor 12 Go Back Work - Pads North
-
07/08→07/09
1B
Electrical
OH Inspections - Electrical
SC1B-N1-IR-270 Floor 1B - OH Inspections - Electrical Floor 1B SC 1.N2 Overhead & Finishes
-
07/08→07/28
1B
Plumbing
OH Install Med Gas Main
SC1B-N1-IR-220 Floor 1B - OH Install Med Gas Main Floor 1B SC 1.N2 Overhead & Finishes
-
07/08→07/28
4B
Data
Pull Wire For All Low Voltage Systems
SC4B-N3-F-140 Floor 4B - Pull Wire For All Low Voltage Systems Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
07/08→07/14
4C
Ceilings
Install Ceiling Grid
SC4C-N1-F-360 Floor 4C - Install Ceiling Grid Floor 4C SC 4.N1 Final Finishes
-
07/08→07/14
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 3-3
AHU3-3-1020 AHU Drops/Duct Connections AHU 3-3 6th Floor AHU 3-3
-
07/08→07/14
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 3-3
AHU3-3-1010 AHU Drops/Piping Connections AHU 3-3 6th Floor AHU 3-3
-
07/08→07/10
6
Inspections/QC
In-Wall Inspections - MEPF
FL6-1020 6th Floor - In-Wall Inspections - MEPF Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
07/08→07/14
6B
Other
6B N6505A - Fans
6B-1090 6B N6505A - Fans 6B AHU
-
07/08→07/21
9A
Drywall/Framing
Blocking/Backing/Plywood
9A-IR-N1-1090 Floor 9A - Blocking/Backing/Plywood Floor 9A East Framing & Interior Roughs
-
07/09→07/22
·
Other
Level 7 - Backwelding
BW-1060 Level 7 - Backwelding Detailing (Back Welding)
-
Thu 07/09
10
Flooring/Finishes
Floor 10 N10501 - Paint Plywood Back Boards
TEL-10-380 Floor 10 N10501 - Paint Plywood Back Boards Telecom Room Lv-10 N10501
-
07/09→07/13
5
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
5EXT-210 Floor 05 - Apply Fluid Applied Roofing on Eyebrow 5th Floor
-
07/10→07/14
10
Electrical
Floor 10 N10501 - OH Conduit Rough-In
TEL-10-180 Floor 10 N10501 - OH Conduit Rough-In Telecom Room Lv-10 N10501
-
07/10→08/06
10A
Electrical
OH Electrical & I.T. Rough In & QC
10A-IR-N1-1120 Floor 10A - OH Electrical & I.T. Rough In & QC Floor 10A East Overhead Roughs
-
07/10→07/23
11
Electrical
Floor 11 (N11505) - Pull & Terminate Feeders
ELC-11-160 Floor 11 (N11505) - Pull & Terminate Feeders Electrical Room Lv-11 N11505 11A East, 11B East, 11C East
-
07/10→07/14
13
Other
Level 13 - Anchors For Pergola
L13RA-100 Level 13 - Anchors For Pergola Level 13 Roofing & Assembly
-
07/10→08/06
1B
Other
Install Dance Floor
SC1B-N1-IR-290 Floor 1B - Install Dance Floor Floor 1B SC 1.N2 Overhead & Finishes
-
07/10→07/16
4A
Fire/Sprinkler
Sprinkler Drops/Heads
SC4A-N2-F-330 Floor 4A - Sprinkler Drops/Heads Floor 4A SC 4.N2 Final Finishes
-
07/10→07/30
5A
Drywall/Framing
Finish Drywall
SC5A-N2-F-190 Floor 5A - Finish Drywall Floor 5A SC 5.N2 Final Finishes
-
07/10→07/30
9B
Plumbing
In-Wall Plumbing Rough QC
9B-IR-N2-1020 Floor 9B - In-Wall Plumbing Rough QC West 9B West Framing & Interior Roughs
-
07/13→07/14
·
Inspections/QC
IMRIS R10 - Overhead MEP Inspections Complete
REV10-1400 IMRIS R10 - Overhead MEP Inspections Complete IMRIS Overhead Roughs - Rev. 10
-
07/13→07/16
10
Electrical
Floor 10 N10504 - Install Grounding Buss
TEL-10-170 Floor 10 N10504 - Install Grounding Buss Telecom Room Lv-10 N10504
-
07/13→07/14
11
Flooring/Finishes
Floor 11 (N11504)- Prime & 1st Finish Coat
TEL-11-110 Floor 11 (N11504)- Prime & 1st Finish Coat Telecom Room Lv-11 N11504
-
07/13→07/24
11
Other
Floor 11 North - In Wall MEPF Rough In
GBW-1350 Floor 11 North - In Wall MEPF Rough In Floor 11 Testing/Commissioning/Life Safety
-
07/13→07/14
5C
Ceilings
Ceilings Gilbane QC
SC5C-N1-F-130 Floor 5C - Ceilings Gilbane QC Floor 5C SC 5.N1 Final Finishes
-
07/13→07/24
6
Drywall/Framing
Batt Insulation & Hang Drywall - Walls, Ceilings, Soffits
FL6-1030 6th Floor - Batt Insulation & Hang Drywall - Walls, Ceilings, Soffits Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
07/13→07/29
6
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
6EXT-200 Floor 06 - Field Measure & Fab. Metal Drip Edge 6th Floor
-
07/14→07/15
1
Flooring/Finishes
N1502 - Prime & 1st Finish Coat
ELC-1-110 Floor 1 - N1502 - Prime & 1st Finish Coat Electrical Room Lv-1 - N1502 - Entire Floor
-
07/14→07/20
1
Data
N1503 - Install Racks & Ladder Tray
TEL-1-150 Floor 1 - N1503 - Install Racks & Ladder Tray Telecom Room Lv-1 N1503
-
07/14→07/15
1
HVAC/Mechanical
Set AHU 1-1
AHU1-1-1000 Set AHU 1-1 Floor 1 Mechanical Space
-
07/14→07/27
11A
Fire/Sprinkler
OH Sprinkler Rough In& QC
11A-IR-N1-1140 Floor 11A - OH Sprinkler Rough In& QC Floor 11A East Overhead Roughs
-
07/14→08/10
1A
Electrical
In-Wall Electrical Rough In & Control & QC
SC1A-N2-IR-110 Floor 1A - In-Wall Electrical Rough In & Control & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
07/14→08/10
1A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
SC1A-N2-IR-160 Floor 1A - OH Duct/VAV Boxes Rough-In/Insulation Floor 1A SC 1.N1 Framing & Interior Roughs
-
07/14→08/03
4
Electrical
Floor 4 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-620 Floor 4 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 4 Testing/Commissioning/Life Safety
-
07/14→07/23
4A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC4A-N1-F-930 Floor 4A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 4A SC 4.N2 Final Finishes
-
07/14→07/20
5C
Inspections/QC
In-Wall Gilbane QC
SC5C-N1-IR-160 Floor 5C - In-Wall Gilbane QC Floor 5C SC 5.N1 Framing & Interior Roughs
-
07/14→08/10
5C
Electrical
Pull Branch Circuits
SC5C-N1-IR-300 Floor 5C - Pull Branch Circuits Floor 5C SC 5.N1 Overhead Roughs
-
07/14→07/20
8
Data
Pull Wire For All Low Voltage Systems
FL8-N1-680 Floor 8 - Pull Wire For All Low Voltage Systems Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/14→08/03
9B
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
9B-IR-N2-1050 Floor 9B - In-Wall Electrical & I.T. Rough In & Control & QC West 9B West Framing & Interior Roughs
-
07/15→07/28
·
Data
Bridge - Pull Conductor For Data & Low Voltage (Underside Deck 2)
BRIDGE-280 Bridge - Pull Conductor For Data & Low Voltage (Underside Deck 2) New Bridge
-
07/15→07/21
·
Concrete/Structure
Bridge - Set Windows & Louvers
BRIDGE-300 Bridge - Set Windows & Louvers New Bridge
-
07/15→07/16
·
Drywall/Framing
IMRIS R10 - Install Door Frames
REV10-1410 IMRIS R10 - Install Door Frames IMRIS Interior Roughs & RF scope - Rev. 10
-
07/15→07/20
10
Electrical
Floor 10 N10501 - Install Grounding Buss
TEL-10-200 Floor 10 N10501 - Install Grounding Buss Telecom Room Lv-10 N10501
-
07/15→07/16
11
Flooring/Finishes
Floor 11 (N11501) - Prime & 1st Finish Coat
TEL-11-150 Floor 11 (N11501) - Prime & 1st Finish Coat Telecom Room Lv-11 N11501
-
07/15→07/20
11
Other
Floor 11 (N11504) - Install Plywood Back Boards
TEL-11-130 Floor 11 (N11504) - Install Plywood Back Boards Telecom Room Lv-11 N11504
-
07/15→07/20
13
Other
Level 13 - Place LWIC - Roof
L13RA-110 Level 13 - Place LWIC - Roof Level 13 Roofing & Assembly
-
07/15→07/21
2B
Inspections/QC
AHCA 80% Inspection For Areas (A, B & C)
SC2B-N3-F-350 Floor 2B - AHCA 80% Inspection For Areas (A, B & C) Floor 2B SC 2.N3
-
07/15→07/28
4A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC4A-N2-F-270 Floor 4A - HVAC Drops & Diffusers/Grid Floor 4A SC 4.N2 Final Finishes
-
07/15→07/17
4C
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC4C-N1-F-400 Floor 4C - Drop Borders & Trade Cuts Ceiling Tiles Floor 4C SC 4.N1 Final Finishes
-
07/15→07/21
5C
Ceilings
MEP Inspections in Hard Ceiling
SC5C-N1-F-160 Floor 5C - MEP Inspections in Hard Ceiling Floor 5C SC 5.N1 Final Finishes
-
07/15→07/23
6
HVAC/Mechanical
BMS Controls AHU 3-3
AHU3-3-1030 BMS Controls AHU 3-3 6th Floor AHU 3-3
-
07/15→07/28
6
Electrical
Install & Electronically Connect VFD's AHU 3-3
AHU3-3-1040 Install & Electronically Connect VFD's AHU 3-3 6th Floor AHU 3-3
-
07/15→07/21
6
HVAC/Mechanical
Set AHU 6-3
AHU6-3-1000 Set AHU 6-3 6th Floor AHU 6-3
-
07/16→07/22
1
HVAC/Mechanical
AHU Drops/Duct Connections AHU-1-1 N1501
AHU1-1-1020 AHU Drops/Duct Connections AHU-1-1 N1501 Floor 1 Mechanical Space
-
07/16→07/22
1
HVAC/Mechanical
AHU Drops/Piping Connections AHU 1-1
AHU1-1-1010 AHU Drops/Piping Connections AHU 1-1 Floor 1 Mechanical Space
-
07/16→07/22
1
Electrical
N1502 - Install Electrical Panels/Equipment
ELC-1-130 Floor 1 - N1502 - Install Electrical Panels/Equipment Electrical Room Lv-1 - N1502 - Entire Floor
-
07/16→07/22
10
HVAC/Mechanical
AHU Drops/Duct Connections 10th Floor N10503
10-M-120 AHU Drops/Duct Connections 10th Floor N10503 Floor 10 Mechanical Space N10503
-
07/16→08/05
11A
HVAC/Mechanical
OH HVAC Controls& QC
11A-IR-N1-1150 Floor 11A - OH HVAC Controls& QC Floor 11A East Overhead Roughs
-
07/16→07/20
2
Other
Temporary Cooling Floor 2
TEMP-2 Temporary Cooling Floor 2 Temporary Cooling
-
07/16→08/05
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull 15KV Feeders From CEPN 4th Floor HVL-EN 5 & 6 to Floor. 6th (SDJEN1, SDJEN2)
CEPN-E-4220 Floor 4 (Gen& El. Rm.) - Pull 15KV Feeders From CEPN 4th Floor HVL-EN 5 & 6 to Floor. 6th (SDJEN1, SDJEN2) Electrical 4th floor (Generator & Main Electrical Rooms)
-
07/16→07/17
4B
Plumbing
Med Gas Pre Certification
SC4B-N3-IR-330 Floor 4B - Med Gas Pre Certification Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
07/16→08/12
5
Other
Floor 5 South - OH MEPF Rougth In
GBW-700 Floor 5 South - OH MEPF Rougth In Floor 5 Testing/Commissioning/Life Safety
-
07/16→08/19
5B
Drywall/Framing
Frame Soffits/Hard Ceilings
SC5B-N3-IR-300 Floor 5B - Frame Soffits/Hard Ceilings Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/16→08/05
5B
Electrical
Install OH Cable Tray
SC5B-N3-IR-500 Floor 5B - Install OH Cable Tray Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/16→07/22
5B
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC5B-N3-IR-480 Floor 5B - OH Sprinkler Rough In & QC Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/16→07/29
6
Other
Floor 6 South - In Wall MEPF Rough In
GBW-830 Floor 6 South - In Wall MEPF Rough In Floor 6 Testing/Commissioning/Life Safety
-
07/16→07/17
6
Inspections/QC
OH Inspections - MEPF
FL6-1130 6th Floor - OH Inspections - MEPF Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
07/17→07/21
·
Drywall/Framing
IMRIS R10 - Hang Drywall/Tape IMRIS Procedure Room
REV10-1420 IMRIS R10 - Hang Drywall/Tape IMRIS Procedure Room IMRIS Interior Roughs & RF scope - Rev. 10
-
Fri 07/17
10
Concrete/Structure
Floor 10 N10504 - Seal Concrete Floor
TEL-10-370 Floor 10 N10504 - Seal Concrete Floor Telecom Room Lv-10 N10504
-
07/17→07/22
11
Other
Floor 11 (N11501) - Install Plywood Back Boards
TEL-11-160 Floor 11 (N11501) - Install Plywood Back Boards Telecom Room Lv-11 N11501
-
07/17→07/21
4C
Electrical
Light Fixtures in Hard Ceiling
SC4C-N1-F-240 Floor 4C - Light Fixtures in Hard Ceiling Floor 4C SC 4.N1 Final Finishes
-
07/17→07/23
5A
Fire/Sprinkler
Fire Stopping/Labeling
SC5A-N2-F-180 Floor 5A - Fire Stopping/Labeling Floor 5A SC 5.N2 Final Finishes
-
07/17→07/21
7
Ceilings
Install Ceiling Grid
FL7-N1-350 Floor 7 - Install Ceiling Grid Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/17→08/13
8
Plumbing
OH Plumbing Rough In/Insulation & QC
FL8-N1-530 Floor 8 - OH Plumbing Rough In/Insulation & QC Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/17→07/30
9A
Drywall/Framing
Frame Soffits/Hard Ceilings
9A-IR-N1-1230 Floor 9A - Frame Soffits/Hard Ceilings Floor 9A East Overhead Roughs
-
07/17→08/06
9A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
9A-F-N1-1010 Floor 9A - HVAC Drops & Diffusers in Soffit Floor 9A East Overhead Roughs
-
07/17→08/13
9A
Plumbing
OH & In Wall MED Gas Rough In & QC
9A-IR-N1-1100 Floor 9A - OH & In Wall MED Gas Rough In & QC Floor 9A East Overhead Roughs
-
07/20→07/24
·
Other
North - Exterior Sealant
NWW-370 North - Exterior Sealant North Window Washing Support Steel / Equipment
-
07/20→07/24
10
Data
Floor 10 N10504 - Install Racks & Ladder Tray
TEL-10-190 Floor 10 N10504 - Install Racks & Ladder Tray Telecom Room Lv-10 N10504
-
07/20→08/07
2
Other
CEP Floor 2 Fuel Oil Controls
CEP-2-4010 CEP Floor 2 Fuel Oil Controls 2nd Floor (Fuel Oil Systems)
-
07/20→07/31
2
Other
CEP Floor 2 Fuel Piping to 4th Floor
CEP-2-4020 CEP Floor 2 Fuel Piping to 4th Floor 2nd Floor (Fuel Oil Systems)
-
07/20→08/28
3
Other
CEP Floor 3 - BMS Point to Point Verification
CEPN-M-3060 CEP Floor 3 - BMS Point to Point Verification Mechanical 3rd Flr (Chillers & Pumps)
-
07/20→07/29
3B
Flooring/Finishes
Paint Prime & First Coat
SC3B-N3-F-230 Floor 3B - Paint Prime & First Coat Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
07/20→08/28
4
Electrical
Floor 4 (Gen& El. Rm.) - Pull & Terminate Feeders to Mechanical Equipment
CEPN-E-4120 Floor 4 (Gen& El. Rm.) - Pull & Terminate Feeders to Mechanical Equipment Electrical 4th floor (Generator & Main Electrical Rooms)
-
07/20→07/24
4C
Fire/Sprinkler
Sprinkler Drops/Heads
SC4C-N1-F-440 Floor 4C - Sprinkler Drops/Heads Floor 4C SC 4.N1 Final Finishes
-
07/21→08/17
·
Other
Elevator 1-2 - Install Rails
ELV-400 Elevator 1-2 - Install Rails Elevator 1-2
-
Tue 07/21
10
Concrete/Structure
Floor 10 N10501 - Seal Concrete Floor
TEL-10-390 Floor 10 N10501 - Seal Concrete Floor Telecom Room Lv-10 N10501
-
Tue 07/21
11
Flooring/Finishes
Floor 11 (N11504) - Paint Plywood Back Boards
TEL-11-360 Floor 11 (N11504) - Paint Plywood Back Boards Telecom Room Lv-11 N11504
-
07/21→07/27
13
Concrete/Structure
Level 13 - Install TPO Roof System
L13RA-120 Level 13 - Install TPO Roof System Level 13 Roofing & Assembly
-
07/21→08/10
2A
Flooring/Finishes
Rubber Flooring/Ceramic Tile
SC2A-N2-F-410 Floor 2A - Rubber Flooring/Ceramic Tile Floor 2A SC 2.N2 Final Finishes
-
07/21→08/05
2C
Flooring/Finishes
Soft Flooring & Base
SC2C-N1-F-310 Floor 2C - Soft Flooring & Base Floor 2C SC 2.N1 Final Finishes
-
07/21→07/27
3C
Electrical
Remove Temp Light Fixtures
SC3C-N1-F-330 Floor 3C - Remove Temp Light Fixtures Floor 3C SC 3.N1 Final Finishes
-
07/21→08/10
4A
Electrical
Light Fixtures in Grid
SC4A-N2-F-320 Floor 4A - Light Fixtures in Grid Floor 4A SC 4.N2 Final Finishes
-
07/21→07/22
5C
Inspections/QC
In-Wall Inspections - MEPF
SC5C-N1-IR-180 Floor 5C - In-Wall Inspections - MEPF Floor 5C SC 5.N1 Framing & Interior Roughs
-
07/21→07/23
8
Flooring/Finishes
Prime & 1st Coat
FL8-N1-690 Floor 8 - Prime & 1st Coat Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/22→07/24
·
Other
Bridge - Interior Layout Level 2 & 3
BRIDGE-310 Bridge - Interior Layout Level 2 & 3 New Bridge
-
Wed 07/22
·
Other
IMRIS R10 - Verify RF Shield Checklist (MS)
REV10-1430 IMRIS R10 - Verify RF Shield Checklist (MS) IMRIS Interior Roughs & RF scope - Rev. 10
-
07/22→07/28
10
Data
Floor 10 N10501 - Install Racks & Ladder Tray
TEL-10-210 Floor 10 N10501 - Install Racks & Ladder Tray Telecom Room Lv-10 N10501
-
07/22→07/23
11
Flooring/Finishes
Floor 11 (N11502) - Prime & 1st Finish Coat
ELC-11-130 Floor 11 (N11502) - Prime & 1st Finish Coat Electrical Room Lv-11 N11502 11A West, 11B West, 11C West
-
07/22→07/24
11
Electrical
Floor 11 (N11504) - OH Conduit Rough-In
TEL-11-140 Floor 11 (N11504) - OH Conduit Rough-In Telecom Room Lv-11 N11504
-
07/22→07/23
11
HVAC/Mechanical
Set AHU N11503
11-M-100 Set AHU N11503 Floor 11 Mechanical Space N11503
-
07/22→08/11
11A
Electrical
Electrical Terminations to Headwall
11A-IR-N1-1170 Floor 11A - Electrical Terminations to Headwall Floor 11A East Framing & Interior Roughs
-
07/22→08/04
11A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall & QC
11A-IR-N1-1160 Floor 11A - Med Gas Zone Valve Boxes/Terminations to Headwall & QC Floor 11A East Framing & Interior Roughs
-
07/22→08/18
12A
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
12A-IR-N1-1010 Floor 12A - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 12 A East Framing & Interior Roughs
-
07/22→08/25
13
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
13B-IR-N2-110 Floor 13 - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 13 A Framing & Interior Roughs
-
07/22→07/23
2B
Ceilings
Ceiling Grid QC
SC2B-N3-F-420 Floor 2B - Ceiling Grid QC Floor 2B SC 2.N3
-
07/22→08/11
5C
Data
Pull Wire For All Low Voltage Systems
SC5C-N1-F-140 Floor 5C - Pull Wire For All Low Voltage Systems Floor 5C SC 5.N1 Overhead Roughs
-
07/22→07/28
6
HVAC/Mechanical
AHU Drops/Duct Connections AHU 6-3
AHU6-3-1020 AHU Drops/Duct Connections AHU 6-3 6th Floor AHU 6-3
-
07/22→07/28
6
HVAC/Mechanical
AHU Drops/Piping Connections AHU 6-3
AHU6-3-1010 AHU Drops/Piping Connections AHU 6-3 6th Floor AHU 6-3
-
07/22→07/24
7
HVAC/Mechanical
HVAC Trim / Diffusers
FL7-N1-380 Floor 7 - HVAC Trim / Diffusers Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/22→07/23
9A
Drywall/Framing
Framing Inspections
9A-F-N1-1030 Floor 9A - Framing Inspections Floor 9A East Framing & Interior Roughs
-
07/22→08/04
9B
Electrical
Install OH Cable Tray
9B-IR-N2-1230 Floor 9B - Install OH Cable Tray West 9B West Overhead Roughs
-
07/23→08/12
·
Ceilings
IMRIS R10 - R.F. Shielding Ceiling
REV10-1440 IMRIS R10 - R.F. Shielding Ceiling IMRIS Interior Roughs & RF scope - Rev. 10
-
07/23→07/29
·
Fire/Sprinkler
Level 7 - Perimeter Firestopping
FSP-1050 Level 7 - Perimeter Firestopping Firestopping
-
07/23→08/05
·
Other
Level 8 - Backwelding
BW-1070 Level 8 - Backwelding Detailing (Back Welding)
-
07/23→07/31
1
HVAC/Mechanical
BMS Controls AHU 1-1
AHU1-1-1060 BMS Controls AHU 1-1 Floor 1 Mechanical Space
-
07/23→08/05
1
Electrical
Install & Electronically Connect VFD's AHU 1-1
AHU1-1-1150 Install & Electronically Connect VFD's AHU 1-1 Floor 1 Mechanical Space
-
07/23→08/05
1
Electrical
N1502 - Pull & Terminate Feeders
ELC-1-140 Floor 1 - N1502 - Pull & Terminate Feeders Electrical Room Lv-1 - N1502 - Entire Floor
-
07/23→07/31
10
HVAC/Mechanical
BMS Controls AHU N10503
10-M-130 BMS Controls AHU N10503 Floor 10 Mechanical Space N10503
-
07/23→08/05
4B
Electrical
Rough-in Can Lights
SC4B-N3-IR-490 Floor 4B - Rough-in Can Lights Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
07/23→09/02
5B
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
SC5B-N3-IR-160 Floor 5B - In-Wall Electrical & I.T. Rough In & Control & QC Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/23→08/19
5B
Plumbing
Med Gas Zone Valve Boxes/Terminations
SC5B-N3-IR-310 Floor 5B - Med Gas Zone Valve Boxes/Terminations Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/23→08/19
5B
Plumbing
OR Modular Ceilings Med Gas Hangers & Piping Rough
SC5B-N3-IR-140 Floor 5B - OR Modular Ceilings Med Gas Hangers & Piping Rough Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/23→08/05
5C
Drywall/Framing
Blocking/Backing/Plywood
SC5C-N1-IR-220 Floor 5C - Blocking/Backing/Plywood Floor 5C SC 5.N1 Framing & Interior Roughs
-
07/24→07/28
11
Electrical
Floor 11 (N11501) - OH Conduit Rough-In
TEL-11-180 Floor 11 (N11501) - OH Conduit Rough-In Telecom Room Lv-11 N11501
-
07/24→07/30
11
Electrical
Floor 11 (N11502) - Install Electrical Panels/Equipment
ELC-11-170 Floor 11 (N11502) - Install Electrical Panels/Equipment Electrical Room Lv-11 N11502 11A West, 11B West, 11C West
-
07/24→07/30
5A
Flooring/Finishes
Grout Bed for Floor Tile
SC5A-N2-F-210 Floor 5A - Grout Bed for Floor Tile Floor 5A SC 5.N2 Final Finishes
-
07/24→07/30
8
Data
All Low Voltage Devices
FL8-N1-1170 Floor 8 - All Low Voltage Devices Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/24→07/28
8
Ceilings
Install Ceiling Grid
FL8-N1-700 Floor 8 - Install Ceiling Grid Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/27→08/07
·
Drywall/Framing
Bridge - Interior Framing on Level 2 & 3
BRIDGE-320 Bridge - Interior Framing on Level 2 & 3 New Bridge
-
07/27→07/28
·
Inspections/QC
North - Inspections
NWW-380 North - Inspections North Window Washing Support Steel / Equipment
-
07/27→08/07
10
Drywall/Framing
Floor 10 North - Hang Drywall & Finish Drywall
GBW-1210 Floor 10 North - Hang Drywall & Finish Drywall Floor 10 Testing/Commissioning/Life Safety
-
07/27→08/07
10A
HVAC/Mechanical
OH HVAC Controls& QC
10A-IR-N1-1150 Floor 10A - OH HVAC Controls& QC Floor 10A East Overhead Roughs
-
07/27→07/30
11
Electrical
Floor 11 (N11504) - Install Grounding Buss
TEL-11-170 Floor 11 (N11504) - Install Grounding Buss Telecom Room Lv-11 N11504
-
07/27→08/21
11
Other
Floor 11 North - OH MEPF Rougth In
GBW-1340 Floor 11 North - OH MEPF Rougth In Floor 11 Testing/Commissioning/Life Safety
-
07/27→08/07
6
Fire/Sprinkler
In Wall Sprinkler Rough-In
FL6-1200 6th Floor - In Wall Sprinkler Rough-In Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
07/27→07/30
6
Other
Set HHW Exchanger
6A-4000 Set HHW Exchanger 6th Floor HHW Exchanger
-
07/27→07/28
7
Ceilings
Install Lights in Grid
FL7-N1-390 Floor 7 - Install Lights in Grid Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/27→07/31
7
Inspections/QC
Test & Balance
FL7-N1-510 Floor 7 - Test & Balance Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/27→08/07
9
Drywall/Framing
Floor 9 North - Hang Drywall & Finish Drywall
GBW-1040 Floor 9 North - Hang Drywall & Finish Drywall Floor 9 Testing/Commissioning/Life Safety
-
07/28→07/30
13
Other
Level 13 - Install Pergola
L13RA-125 Level 13 - Install Pergola Level 13 Roofing & Assembly
-
07/28→08/24
1A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
SC1A-N2-IR-200 Floor 1A - OH HVAC Piping/Controls/Insulation & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
07/28→08/03
2A
Flooring/Finishes
Doors & Hardware
SC2A-N2-F-430 Floor 2A - Doors & Hardware Floor 2A SC 2.N2 Final Finishes
-
07/28→07/29
3C
Ceilings
Ceiling Grid QC
SC3C-N1-F-440 Floor 3C - Ceiling Grid QC Floor 3C SC 3.N1 Final Finishes
-
07/28→08/17
4A
Data
All Low Voltage Devices
SC4A-N2-F-340 Floor 4A - All Low Voltage Devices Floor 4A SC 4.N2 Final Finishes
-
07/28→07/30
4A
Electrical
Remove Temp Light Fixtures
SC4A-N2-F-290 Floor 4A - Remove Temp Light Fixtures Floor 4A SC 4.N2 Final Finishes
-
07/28→08/03
5A
Flooring/Finishes
Paint Prime & First Coat
SC5A-N2-F-230 Floor 5A - Paint Prime & First Coat Floor 5A SC 5.N2 Final Finishes
-
07/29→08/06
·
Concrete/Structure
Install Precast Panels Levels 8-12 (Set 9 WS)
SW-780 Install Precast Panels Levels 8-12 (Set 9 WS) Precast
-
07/29→08/03
·
Inspections/QC
Install Punch Windows - Set 8
EXG-1070 Install Punch Windows - Set 8 Exterior Glass & Glazing South Elevation (Punch Windows)
-
07/29→08/04
·
Other
North - Remove Access Platform System
NWW-390 North - Remove Access Platform System North Window Washing Support Steel / Equipment
-
07/29→08/03
11
Electrical
Floor 11 (N11501) - Install Grounding Buss
TEL-11-200 Floor 11 (N11501) - Install Grounding Buss Telecom Room Lv-11 N11501
-
07/29→07/31
12
Other
Floor 12 North - Set Bathroom Pods
GBW-1480 Floor 12 North - Set Bathroom Pods Floor 12 Go Back Work - Pads North
-
07/29→07/30
1B
Plumbing
OH Inspections - Plumbing
SC1B-N1-IR-260 Floor 1B - OH Inspections - Plumbing Floor 1B SC 1.N2 Overhead & Finishes
-
07/29→08/18
2
Data
N2501 - Pull LV Riser Cable MDF
2-TEL-460 Floor 2 - N2501 - Pull LV Riser Cable MDF Telecom Room Lv-2 N2501 MDF
-
07/29→08/04
2
Data
N2503 - Pull LV Riser Cable
2-TEL-360 Floor 2 - N2503 - Pull LV Riser Cable Telecom Room Lv-2 N2503
-
07/29→07/31
3
Other
Temporary Cooling Floor 3
TEMP-3 Temporary Cooling Floor 3 Temporary Cooling
-
07/29→08/04
4C
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC4C-N1-F-370 Floor 4C - HVAC Drops & Diffusers/Grid Floor 4C SC 4.N1 Final Finishes
-
07/29→08/06
6
HVAC/Mechanical
BMS Controls AHU 6-3
AHU6-3-1030 BMS Controls AHU 6-3 6th Floor AHU 6-3
-
07/29→08/11
6
Electrical
Install & Electronically Connect VFD's AHU 6-3
AHU6-3-1040 Install & Electronically Connect VFD's AHU 6-3 6th Floor AHU 6-3
-
07/29→07/31
7
Fire/Sprinkler
Sprinkler Drops/Heads At Grid
FL7-N1-400 Floor 7 - Sprinkler Drops/Heads At Grid Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/29→07/31
8
HVAC/Mechanical
HVAC Trim / Diffusers
FL8-N1-720 Floor 8 - HVAC Trim / Diffusers Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
07/30→08/04
2A
Flooring/Finishes
Base
SC2A-N2-F-440 Floor 2A - Base Floor 2A SC 2.N2 Final Finishes
-
07/30→08/10
3B
Ceilings
Install Ceiling Grid
SC3B-N3-F-250 Floor 3B - Install Ceiling Grid Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
07/30→08/10
3B
Electrical
Light Fixtures in Hard Lids
SC3B-N3-F-260 Floor 3B - Light Fixtures in Hard Lids Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
07/30→09/10
5B
Electrical
OR Ceilings Overhead Electrical & Lighting Rough
SC5B-N3-IR-340 Floor 5B - OR Ceilings Overhead Electrical & Lighting Rough Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
07/30→08/03
6
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
6EXT-210 Floor 06 - Apply Fluid Applied Roofing on Eyebrow 6th Floor
-
07/30→08/26
6
Other
Floor 6 South - OH MEPF Rougth In
GBW-820 Floor 6 South - OH MEPF Rougth In Floor 6 Testing/Commissioning/Life Safety
-
07/31→08/20
10A
Plumbing
In-Wall Plumbing Rough QC
10A-IR-N1-1020 Floor 10A - In-Wall Plumbing Rough QC Floor 10A East Framing & Interior Roughs
-
07/31→08/13
11
Electrical
Floor 11 (N11502) - Pull & Terminate Feeders
ELC-11-200 Floor 11 (N11502) - Pull & Terminate Feeders Electrical Room Lv-11 N11502 11A West, 11B West, 11C West
-
Fri 07/31
11
Concrete/Structure
Floor 11 (N11504) - Seal Concrete Floor
TEL-11-370 Floor 11 (N11504) - Seal Concrete Floor Telecom Room Lv-11 N11504
-
07/31→08/05
13
Electrical
Level 13 - Rough In Lighting & Controls
REV7-CEPPL-190 Level 13 - Rough In Lighting & Controls Level 13 Roofing & Assembly
-
07/31→08/04
4C
Electrical
Remove Temp Light Fixtures
SC4C-N1-F-390 Floor 4C - Remove Temp Light Fixtures Floor 4C SC 4.N1 Final Finishes
-
07/31→08/10
5A
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC5A-N2-F-220 Floor 5A - Ceramic Tile / Grout - Bathrooms Floor 5A SC 5.N2 Final Finishes
-
07/31→08/06
6
HVAC/Mechanical
Set HHW Exchanger Drops/Duct Connections
6A-4020 Set HHW Exchanger Drops/Duct Connections 6th Floor HHW Exchanger
-
07/31→08/06
6
Other
Set HHW Exchanger Drops/Piping Connections
6A-4010 Set HHW Exchanger Drops/Piping Connections 6th Floor HHW Exchanger
-
07/31→08/04
6B
Other
6B N6505 - Steam Skid Set
6B-1050 6B N6505 - Steam Skid Set 6B AHU
-
07/31→08/13
9A
Data
OH Low Voltage Pipe Rough-In
9A-F-N1-1000 Floor 9A - OH Low Voltage Pipe Rough-In Floor 9A East Overhead Roughs
-
07/31→08/20
9A
Electrical
RI Light Fixtures Hard Ceilings & Soffits
9A-F-N1-1020 Floor 9A - RI Light Fixtures Hard Ceilings & Soffits Floor 9A East Overhead Roughs
-
08/03→08/07
11
Data
Floor 11 (N11504) - Install Racks & Ladder Tray
TEL-11-190 Floor 11 (N11504) - Install Racks & Ladder Tray Telecom Room Lv-11 N11504
-
08/03→08/14
12
Other
Floor 12 North - In Wall MEPF Rough In
GBW-1500 Floor 12 North - In Wall MEPF Rough In Floor 12 Go Back Work - Pads North
-
08/03→08/18
3A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC3A-N2-F-240 Floor 3A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 3A SC 3.N2 Final Finishes
-
08/03→08/07
3B
Flooring/Finishes
Casework/Countertops
SC3B-N3-F-240 Floor 3B - Casework/Countertops Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/03→08/04
3C
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC3C-N1-F-900 Floor 3C - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 3C SC 3.N1 Final Finishes
-
08/03→08/05
4
Other
Temporary Cooling Floor 4
TEMP-4 Temporary Cooling Floor 4 Temporary Cooling
-
08/03→08/05
5
Other
Temporary Cooling Floor 5
TEMP-5 Temporary Cooling Floor 5 Temporary Cooling
-
08/03→08/07
7
Inspections/QC
MEPF Overhead Inspections
FL7-N1-180 Floor 7 - MEPF Overhead Inspections Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/03→08/04
8
Ceilings
Install Lights in Grid
FL8-N1-730 Floor 8 - Install Lights in Grid Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/04→08/07
2A
Flooring/Finishes
Building Specialties
SC2A-N2-F-420 Floor 2A - Building Specialties Floor 2A SC 2.N2 Final Finishes
-
08/04→08/17
2C
Flooring/Finishes
Doors & Hardware
SC2C-N1-F-330 Floor 2C - Doors & Hardware Floor 2C SC 2.N1 Final Finishes
-
08/04→08/12
3B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC3B-N3-F-270 Floor 3B - HVAC Drops & Diffusers/Grid Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/04→08/13
5A
Ceilings
Install Ceiling Grid
SC5A-N2-F-250 Floor 5A - Install Ceiling Grid Floor 5A SC 5.N2 Final Finishes
-
08/04→08/24
5A
Electrical
Light Fixtures in Soffit
SC5A-N2-F-260 Floor 5A - Light Fixtures in Soffit Floor 5A SC 5.N2 Final Finishes
-
08/04→08/05
9B
Inspections/QC
In-Wall Inspections - MEPF
9B-IR-N2-1070 Floor 9B - In-Wall Inspections - MEPF West 9B West Framing & Interior Roughs
-
08/04→08/06
9B
HVAC/Mechanical
OH HVAC Controls& QC
9B-IR-N2-1150 Floor 9B - OH HVAC Controls& QC West 9B West Overhead Roughs
-
08/05→08/11
11
Data
Floor 11 (N11501) - Install Racks & Ladder Tray
TEL-11-210 Floor 11 (N11501) - Install Racks & Ladder Tray Telecom Room Lv-11 N11501
-
08/05→08/18
12A
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
12A-IR-N1-1103 Floor 12A - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) Floor 12 A East Overhead Roughs
-
Wed 08/05
2
Data
N2503 - Install I. T. Rooms Doors
2-TEL-370 Floor 2 - N2503 - Install I. T. Rooms Doors Telecom Room Lv-2 N2503
-
08/05→08/18
5A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC5A-N2-F-270 Floor 5A - HVAC Drops & Diffusers/Grid Floor 5A SC 5.N2 Final Finishes
-
08/05→08/18
6B
Other
Steam Main to Riser
6B-1110 6B - Steam Main to Riser 6B AHU
-
08/05→08/07
8
Fire/Sprinkler
Sprinkler Drops/Heads at Grid
FL8-N1-740 Floor 8 - Sprinkler Drops/Heads at Grid Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/06→08/12
·
Fire/Sprinkler
Level 8 - Perimeter Firestopping
FSP-1060 Level 8 - Perimeter Firestopping Firestopping
-
08/06→08/19
13
Other
Level 13 - Install Pavers & Trim
L13RA-130 Level 13 - Install Pavers & Trim Level 13 Roofing & Assembly
-
08/06→08/26
2
Inspections/QC
N2503 - Terminate & Test IT Systems Cabling
2-TEL-380 Floor 2 - N2503 - Terminate & Test IT Systems Cabling Telecom Room Lv-2 N2503
-
08/06→08/12
4B
Ceilings
OR Ceilings GBCo Above Ceiling Inspections
SC4B-N3-IR-420 Floor 4B - OR Ceilings GBCo Above Ceiling Inspections Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
08/06→08/07
4B
Drywall/Framing
OR Ceilings Owner/AE Final Layout Approval Prior Drywall
SC4B-N3-IR-430 Floor 4B - OR Ceilings Owner/AE Final Layout Approval Prior Drywall Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
08/06→08/07
4C
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC4C-N1-F-900 Floor 4C - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 4C SC 4.N1 Final Finishes
-
08/06→08/07
4C
Plumbing
Common Area Plumbing Trim Out
SC4C-N1-F-280 Floor 4C - Common Area Plumbing Trim Out Floor 4C SC 4.N1 Final Finishes
-
08/06→08/12
4C
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC4C-N1-F-270 Floor 4C - Install Special Wall Finishes (incl. Wall Protection) Floor 4C SC 4.N1 Final Finishes
-
08/06→08/07
5A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC5A-N2-F900 Floor 5A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 5A SC 5.N2 Final Finishes
-
08/06→08/07
5C
Drywall/Framing
Framing Inspections
SC5C-N1-F-150 Floor 5C - Framing Inspections Floor 5C SC 5.N1 Framing & Interior Roughs
-
08/06→08/14
9B
Drywall/Framing
Blocking/Backing/Plywood
9B-IR-N2-1090 Floor 9B - Blocking/Backing/Plywood West 9B West Framing & Interior Roughs
-
08/07→08/17
·
Concrete/Structure
Install Precast Panels Levels 8-12 (Set10 WS)
W-790 Install Precast Panels Levels 8-12 (Set10 WS) Precast
-
08/07→08/12
·
Inspections/QC
Install Punch Windows - Set 9
EXG-1080 Install Punch Windows - Set 9 Exterior Glass & Glazing South Elevation (Punch Windows)
-
08/07→08/27
10A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
10A-IR-N1-1050 Floor 10A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 10A East Framing & Interior Roughs
-
08/07→08/20
10A
Electrical
Install OH Cable Tray
10A-IR-N1-1250 Floor 10A - Install OH Cable Tray Floor 10A East Overhead Roughs
-
08/07→09/03
1B
Drywall/Framing
Frame Ceiling
SC1B-N1-IR-180 Floor 1B - Frame Ceiling Floor 1B SC 1.N2 Overhead & Finishes
-
08/07→08/11
3B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC3B-N3-F-330 Floor 3B - Drop Borders & Trade Cuts Ceiling Tiles Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/07→08/18
5C
Drywall/Framing
Finish Drywall
SC5C-N1-F-210 Floor 5C - Finish Drywall Floor 5C SC 5.N1 Final Finishes
-
08/07→08/17
6
Other
Set HHW Exchanger BMS Controls
6A-4030 Set HHW Exchanger BMS Controls 6th Floor HHW Exchanger
-
08/10→08/14
10
Flooring/Finishes
Floor 10 North - Prime & 1st Coat
GBW-1220 Floor 10 North - Prime & 1st Coat Floor 10 Testing/Commissioning/Life Safety
-
08/10→08/21
2
HVAC/Mechanical
Bridge - OH Mechanical Duct and Piping 2nd Floor
BRIDGE-330 Bridge - OH Mechanical Duct and Piping 2nd Floor New Bridge
-
08/10→08/21
2C
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC2C-N1-F-320 Floor 2C - Building Specialties (incl. Curtain Track) Floor 2C SC 2.N1 Final Finishes
-
08/10→08/14
4
Inspections/QC
Floor 4 (Gen& El. Rm.) - Fuel Oil System Inspection
CEPN-E-4200 Floor 4 (Gen& El. Rm.) - Fuel Oil System Inspection Electrical 4th floor (Generator & Main Electrical Rooms)
-
08/10→08/14
4C
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC4C-N1-F-910 Floor 4C - Flooring - SV Flooring + Cove Base` (FL-1) Floor 4C SC 4.N1 Final Finishes
-
08/10→08/14
5A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC5A-N2-F910 Floor 5A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 5A SC 5.N2 Final Finishes
-
08/10→08/14
5C
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC5C-N1-F-170 Floor 5C - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 5C SC 5.N1 Final Finishes
-
08/10→08/14
5C
Fire/Sprinkler
Fire Stopping/Labeling
SC5C-N1-F-180 Floor 5C - Fire Stopping/Labeling Floor 5C SC 5.N1 Final Finishes
-
08/10→08/19
6
Drywall/Framing
Finish Drywall
FL6-1040 6th Floor - Finish Drywall Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/10→08/14
9
Flooring/Finishes
Floor 9 North - Prime & 1st Coat
GBW-1050 Floor 9 North - Prime & 1st Coat Floor 9 Testing/Commissioning/Life Safety
-
08/11→09/08
1A
Plumbing
OH & In Wall MED Gas Rough In & QC
SC1A-N2-IR-170 Floor 1A - OH & In Wall MED Gas Rough In & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
08/11→09/08
1A
Plumbing
OH Plumbing Rough In/Insulation & QC
SC1A-N2-IR-190 Floor 1A - OH Plumbing Rough In/Insulation & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
08/11→08/19
2A
Plumbing
Plumbing Fixtures
SC2A-N2-F-460 Floor 2A - Plumbing Fixtures Floor 2A SC 2.N2 Final Finishes
-
08/11→08/17
2A
Flooring/Finishes
Set Casework/Countertops
SC2A-N2-F-250 Floor 2A - Set Casework/Countertops Floor 2A SC 2.N2 Final Finishes
-
08/11→08/24
4C
Electrical
Light Fixtures in Grid
SC4C-N1-F-430 Floor 4C - Light Fixtures in Grid Floor 4C SC 4.N1 Final Finishes
-
08/12→09/01
3B
Data
All Low Voltage Devices
SC3B-N3-F-380 Floor 3B - All Low Voltage Devices Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/12→09/01
3B
Electrical
Light Fixtures in Grid
SC3B-N3-F-350 Floor 3B - Light Fixtures in Grid Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/12→08/18
3B
Fire/Sprinkler
Sprinkler Drops/Heads
SC3B-N3-F-360 Floor 3B - Sprinkler Drops/Heads Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
08/12→08/18
5A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC5A-N2-F-300 Floor 5A - Drop Borders & Trade Cuts Ceiling Tiles Floor 5A SC 5.N2 Final Finishes
-
08/12→08/21
6
Flooring/Finishes
Paint Prime & First Coat
FL6-1050 6th Floor - Paint Prime & First Coat Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/13→08/26
·
Inspections/QC
IMRIS R10 - R.F. Shielding Walls & Floor & Test
REV10-1450 IMRIS R10 - R.F. Shielding Walls & Floor & Test IMRIS Interior Roughs & RF scope - Rev. 10
-
08/13→08/19
4B
Inspections/QC
OH Gilbane QC
SC4B-N3-IR-290 Floor 4B - OH Gilbane QC Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
08/13→08/26
5
Drywall/Framing
Floor 5 South - Hang Drywall & Finish Drywall
GBW-720 Floor 5 South - Hang Drywall & Finish Drywall Floor 5 Testing/Commissioning/Life Safety
-
08/13→09/10
5B
Electrical
OR Modular Ceilings Electrical Rough to Clean-Suite
SC5B-N3-IR-380 Floor 5B - OR Modular Ceilings Electrical Rough to Clean-Suite Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/13→08/24
8
Drywall/Framing
Floor 8 N8503 - Hang/Tape/Finish Wall Board
TEL-8-105 Floor 8 N8503 - Hang/Tape/Finish Wall Board Telecom Room Lv-8 N8503
-
08/14→09/03
10A
Plumbing
Head Wall Med Gas
10A-IR-N1-1041 Floor 10A - Head Wall Med Gas Floor 10A East Framing & Interior Roughs
-
08/14→08/27
5A
Electrical
Remove Temp Light Fixtures
SC5A-N2-F-290 Floor 5A - Remove Temp Light Fixtures Floor 5A SC 5.N2 Final Finishes
-
08/14→08/20
5A
Fire/Sprinkler
Sprinkler Drops/Heads
SC5A-N2-F-330 Floor 5A - Sprinkler Drops/Heads Floor 5A SC 5.N2 Final Finishes
-
08/14→08/17
9A
Inspections/QC
OH Inspections - MEPF
9A-IR-N1-1200 Floor 9A - OH Inspections - MEPF Floor 9A East Overhead Roughs
-
08/14→09/11
9A
Data
Pull Wire For All Low Voltage Systems
9A-F-N1-1070 Floor 9A - Pull Wire For All Low Voltage Systems Floor 9A East Overhead Roughs
-
08/14→08/27
9B
Plumbing
OH & In Wall MED Gas Rough In & QC
9B-IR-N2-1100 Floor 9B - OH & In Wall MED Gas Rough In & QC West 9B West Overhead Roughs
-
08/14→08/27
9B
Data
OH Low Voltage Pipe Rough-In
9B-F-N2-1000 Floor 9B - OH Low Voltage Pipe Rough-In West 9B West Overhead Roughs
-
08/17→08/21
10
HVAC/Mechanical
AHU Drops/Piping Connections AHU N10503
10-M-110 AHU Drops/Piping Connections AHU N10503 Floor 10 Mechanical Space N10503
-
08/17→09/04
10
Electrical
Floor 10 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1230 Floor 10 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 10 Testing/Commissioning/Life Safety
-
08/17→09/14
11A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QCH HVAC Piping & QC
11A-IR-N1-2000 Floor 11A - OH HVAC Piping/Controls/Insulation & QCH HVAC Piping & QC Floor 11A East Overhead Roughs
-
08/17→09/14
12
Other
Floor 12 North - OH MEPF Rougth In
GBW-1490 Floor 12 North - OH MEPF Rougth In Floor 12 Go Back Work - Pads North
-
08/17→08/21
4
Other
Floor 4 (Gen& El. Rm.) - Fill Fuel Oil System
CEPN-E-4210 Floor 4 (Gen& El. Rm.) - Fill Fuel Oil System Electrical 4th floor (Generator & Main Electrical Rooms)
-
08/17→08/21
4C
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC4C-N1-F-920 Floor 4C - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 4C SC 4.N1 Final Finishes
-
08/17→08/21
5A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC5A-N2-F920 Floor 5A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 5A SC 5.N2 Final Finishes
-
08/17→08/21
5C
Flooring/Finishes
Grout Bed for Tile
SC5C-N1-F-200 Floor 5C - Grout Bed for Tile Floor 5C SC 5.N1 Final Finishes
-
08/17→08/21
5C
Ceilings
Install Ceiling Grid
SC5C-N1-F-360 Floor 5C - Install Ceiling Grid Floor 5C SC 5.N1 Final Finishes
-
08/17→08/21
7
Inspections/QC
80% AHCA Inspections
FL7-N1-370 Floor 7 - 80% AHCA Inspections Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/17→08/26
8
Drywall/Framing
Floor 8 N8504 - Hang/Tape/Finish Wall Board
TEL-8-120 Floor 8 N8504 - Hang/Tape/Finish Wall Board Telecom Room Lv-8 N8504
-
08/17→09/04
9
Electrical
Floor 9 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1060 Floor 9 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 9 Testing/Commissioning/Life Safety
-
08/17→08/18
9B
Drywall/Framing
Framing Inspections
9B-F-N2-1030 Floor 9B - Framing Inspections West 9B West Framing & Interior Roughs
-
08/18→09/15
·
Other
Elevator 1-2 - Install Cab & Machine
ELV-480 Elevator 1-2 - Install Cab & Machine Elevator 1-2
-
08/18→09/10
·
Concrete/Structure
Install Precast Panels Levels 12-Roof (Set 11 WS)
SE-800 Install Precast Panels Levels 12-Roof (Set 11 WS) Precast
-
08/18→08/27
·
Inspections/QC
Install Punch Windows - Set 10
EXG-1090 Install Punch Windows - Set 10 Exterior Glass & Glazing South Elevation (Punch Windows)
-
08/18→08/31
·
Other
Level 9 - Backwelding
BW-1080 Level 9 - Backwelding Detailing (Back Welding)
-
08/18→09/08
2A
Plumbing
Plumbing Trim Out
SC2A-N2-F-400 Floor 2A - Plumbing Trim Out Floor 2A SC 2.N2 Final Finishes
-
08/18→08/31
2B
Flooring/Finishes
Doors & Hardware
SC2B-N3-F-370 Floor 2B - Doors & Hardware Floor 2B SC 2.N3
-
08/18→09/02
2C
Flooring/Finishes
Install Casework/Countertops
SC2C-N1-F-240 Floor 2C - Install Casework/Countertops Floor 2C SC 2.N1 Final Finishes
-
08/18→08/24
4A
Ceilings
Ceiling Grid QC
SC4A-N2-F-350 Floor 4A - Ceiling Grid QC Floor 4A SC 4.N2 Final Finishes
-
08/18→09/08
4C
Data
All Low Voltage Devices
SC4C-N1-F-450 Floor 4C - All Low Voltage Devices Floor 4C SC 4.N1 Final Finishes
-
Tue 08/18
5C
Milestone
Finish Drywall ◆
M660 Floor 5C - Finish Drywall Construction Milestones
-
08/19→08/25
1
Data
N1503 - Pull LV Riser Cable
TEL-1-160 Floor 1 - N1503 - Pull LV Riser Cable Telecom Room Lv-1 N1503
-
08/19→09/16
11A
Plumbing
OH Plumbing Rough In/Insulation & QC
11A-IR-N1-1110 Floor 11A - OH Plumbing Rough In/Insulation & QC Floor 11A East Overhead Roughs
-
08/19→08/28
12
Drywall/Framing
N12504 - Hang/Tape/Finish Wall Board
TEL-12-100 Floor 12 - N12504 - Hang/Tape/Finish Wall Board Telecom Room Lv-12 N12504
-
08/19→08/20
12
Flooring/Finishes
N12505 - Prime & 1st Finish Coat
ELC-12-110 Floor 12 - N12505 - Prime & 1st Finish Coat Electrical Room Lv-12 N12505 Corridor 1 12A East, 12B East, 12C East
-
08/19→09/09
12A
Other
Install Pre-Fab Headwalls
12A-IR-N1-1130 Floor 12A - Install Pre-Fab Headwalls Floor 12 A East Framing & Interior Roughs
-
08/19→09/16
12B
Drywall/Framing
Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms
12B-IR-N2-1010 Floor 12B - Frame Walls & Hang Top Board/Including Mechanical & Electrical Rooms Floor 12 B West Framing & Interior Roughs
-
Wed 08/19
2
Data
N2501 - Install I. T. Rooms Doors
2-TEL-470 Floor 2 - N2501 - Install I. T. Rooms Doors Telecom Room Lv-2 N2501 MDF
-
08/19→08/25
3
Data
N3501 - Pull LV Riser Cable
TEL-3010 Floor 3 - N3501 - Pull LV Riser Cable Telecom Room Lv-3 N3501
-
08/19→09/09
3A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC3A-N2-F-340 Floor 3A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 3A SC 3.N2 Final Finishes
-
08/19→08/21
5C
Flooring/Finishes
Paint Prime & First Coat
SC5C-N1-F-230 Floor 5C - Paint Prime & First Coat Floor 5C SC 5.N1 Final Finishes
-
08/19→09/01
6B
Other
Insulation
6B-1070 6B - Insulation 6B AHU
-
08/20→09/02
13
Other
Level 13 - Install Glass Railing
L13RA-140 Level 13 - Install Glass Railing Level 13 Roofing & Assembly
-
08/20→09/10
2
Inspections/QC
N2501 - Terminate & Test IT Systems Cabling
2-TEL-480 Floor 2 - N2501 - Terminate & Test IT Systems Cabling Telecom Room Lv-2 N2501 MDF
-
08/20→09/02
2A
Other
Div 10 Accessories
SC2A-N2-F-500 Floor 2A - Div 10 Accessories Floor 2A SC 2.N2 Final Finishes
-
08/20→09/17
4B
Drywall/Framing
Finish Drywall
SC4B-N3-F-190 Floor 4B - Finish Drywall Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
08/20→08/21
4B
Inspections/QC
OH Inspections - MEPF
SC4B-N3-IR-460 Floor 4B - OH Inspections - MEPF Floor 4B SC 4.N3 (7 OR's) Overhead Roughs
-
08/20→08/26
5B
Electrical
Electrical Rough in Soffit
SC5B-N3-F-120 Floor 5B - Electrical Rough in Soffit Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/20→08/26
5B
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
SC5B-N3-F-110 Floor 5B - HVAC Drops & Diffusers in Soffit Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/20→08/25
5B
Data
OH Low Voltage Pipe Rough-In
SC5B-N3-F-100 Floor 5B - OH Low Voltage Pipe Rough-In Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/20→09/02
5B
Plumbing
OR Ceilings Med Gas Connection to Clean Suite
SC5B-N3-IR-360 Floor 5B - OR Ceilings Med Gas Connection to Clean Suite Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/21→09/01
10A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall & QC
10A-IR-N1-1160 Floor 10A - Med Gas Zone Valve Boxes/Terminations to Headwall & QC Floor 10A East Framing & Interior Roughs
-
08/21→09/18
10A
Data
Pull Wire For All Low Voltage Systems
10A-IR-N1-1070 Floor 10A - Pull Wire For All Low Voltage Systems Floor 10A East Overhead Roughs
-
08/21→09/01
12
Drywall/Framing
N12501 - Hang/Tape/Finish Wall Board
TEL-12-120 Floor 12 - N12501 - Hang/Tape/Finish Wall Board Telecom Room Lv-12 N12501
-
08/21→08/27
12
Electrical
N12505 - Install Electrical Panels/Equipment
ELC-12-150 Floor 12 - N12505 - Install Electrical Panels/Equipment Electrical Room Lv-12 N12505 Corridor 1 12A East, 12B East, 12C East
-
Fri 08/21
5C
Milestone
Install Ceiling Grid ◆
M690 Floor 5C - Install Ceiling Grid Construction Milestones
-
08/21→08/27
9A
Ceilings
MEP Inspections in Soffits
9A-F-N1-1050 Floor 9A - MEP Inspections in Soffits Floor 9A East Overhead Roughs
-
08/24→09/04
10
Electrical
Install & Electronically Connect VFD's N10503
10-M-150 Install & Electronically Connect VFD's N10503 Floor 10 Mechanical Space N10503
-
08/24→09/04
11
Drywall/Framing
Floor 11 North - Hang Drywall & Finish Drywall
GBW-1360 Floor 11 North - Hang Drywall & Finish Drywall Floor 11 Testing/Commissioning/Life Safety
-
Mon 08/24
13
Milestone
Exterior Glass & Glazing (13-Roof) ◆
M640 FL13 - Exterior Glass & Glazing (13-Roof) Construction Milestones
-
08/24→09/02
2
Electrical
Bridge - OH Electrical 2nd Floor
BRIDGE-350 Bridge - OH Electrical 2nd Floor New Bridge
-
08/24→09/04
2B
Flooring/Finishes
Building Specialties
SC2B-N3-F-340 Floor 2B - Building Specialties Floor 2B SC 2.N3
-
08/24→09/21
2B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC2B-N3-F-260 Floor 2B - Install Special Wall Finishes (incl. Wall Protection) Floor 2B SC 2.N3
-
08/24→09/04
2C
Plumbing
Plumbing Fixtures
SC2C-N1-F-290 Floor 2C - Plumbing Fixtures Floor 2C SC 2.N1 Final Finishes
-
08/24→09/04
3
HVAC/Mechanical
Bridge - OH Mechanical Duct and Piping 3rd Floor
BRIDGE-340 Bridge - OH Mechanical Duct and Piping 3rd Floor New Bridge
-
08/24→09/04
4
Other
Floor 4 (Gen& El. Rm.) - Fuel System Start-up
CEPN-E-4190 Floor 4 (Gen& El. Rm.) - Fuel System Start-up Electrical 4th floor (Generator & Main Electrical Rooms)
-
08/24→09/21
4B
Drywall/Framing
Hang/Tape/Finish Drywall OR Ceilings
SC4B-N3-F-800 Floor 4B - Hang/Tape/Finish Drywall OR Ceilings Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
08/24→09/02
4C
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC4C-N1-F-930 Floor 4C - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 4C SC 4.N1 Final Finishes
-
08/24→09/02
5A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC5A-N2-F930 Floor 5A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 5A SC 5.N2 Final Finishes
-
08/24→09/14
5C
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC5C-N1-F-220 Floor 5C - Ceramic Tile / Grout - Bathrooms Floor 5C SC 5.N1 Final Finishes
-
08/24→08/26
5C
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC5C-N1-F-400 Floor 5C - Drop Borders & Trade Cuts Ceiling Tiles Floor 5C SC 5.N1 Final Finishes
-
08/24→08/28
5C
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC5C-N1-F-370 Floor 5C - HVAC Drops & Diffusers/Grid Floor 5C SC 5.N1 Final Finishes
-
08/24→08/27
6
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
FL6-1320 6th Floor - Ceramic Tile / Grout - Bathrooms Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/24→08/26
6
Other
Chain Link Fence Install In Room N6100
FL6-1110 6th Floor - Chain Link Fence Install In Room N6100 Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/24→09/04
6
Ceilings
Install Ceiling Grid
FL6-1240 6th Floor - Install Ceiling Grid Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/24→09/04
6
Flooring/Finishes
Install Flooring And Base
FL6-1220 6th Floor - Install Flooring And Base Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/24→08/25
7
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
FL7-N1-410 Floor 7 - Drop Borders & Trade Cuts Ceiling Tiles Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/24→08/28
7
Flooring/Finishes
Install Doors & Hardware
FL7-N1-420 Floor 7 - Install Doors & Hardware Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/25→09/08
13
Drywall/Framing
Floor 13 North - Layout, Frame & Insulate Walls
GBW-1600 Floor 13 North - Layout, Frame & Insulate Walls Floor 13 Go Back Work - Pads North
-
08/25→09/15
13
Ceilings
Install EFIS Soffit/Caulk
13EXT-150 Floor 13 - Install EFIS Soffit/Caulk 13th Floor
-
08/25→09/08
13
Concrete/Structure
Install Temp Weather Protection to Dry-In @ 13th Floor Slab
TEMP-1010 Install Temp Weather Protection to Dry-In @ 13th Floor Slab Temporary Roof 13th
-
08/25→09/15
5A
Electrical
Light Fixtures in Grid
SC5A-N2-F-320 Floor 5A - Light Fixtures in Grid Floor 5A SC 5.N2 Final Finishes
-
08/25→08/27
5C
Electrical
Light Fixtures in Hard Ceiling
SC5C-N1-F-240 Floor 5C - Light Fixtures in Hard Ceiling Floor 5C SC 5.N1 Final Finishes
-
08/25→08/26
8
Flooring/Finishes
Floor 8 N8503 - Prime & 1st Finish Coat
TEL-8-110 Floor 8 N8503 - Prime & 1st Finish Coat Telecom Room Lv-8 N8503
-
Wed 08/26
1
Data
N1503 - Install I. T. Rooms Doors
TEL-1-170 Floor 1 - N1503 - Install I. T. Rooms Doors Telecom Room Lv-1 N1503
-
08/26→09/23
11A
Electrical
OH Electrical & I.T. Rough In & QC
11A-IR-N1-1120 Floor 11A - OH Electrical & I.T. Rough In & QC Floor 11A East Overhead Roughs
-
08/26→09/30
13
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
13B-IR-N2-150 Floor 13 - In-Wall Electrical & I.T. Rough In & Control & QC Floor 13 A Framing & Interior Roughs
-
08/26→09/04
13
Drywall/Framing
N13501 - Hang/Tape/Finish Wall Board
TEL-13-120 Floor 13 - N13501 - Hang/Tape/Finish Wall Board Telecom Room Lv-13 N13501
-
08/26→08/27
13
Flooring/Finishes
N13502 - Prime & 1st Finish Coat
ELC-13-130 Floor 13 - N13502 - Prime & 1st Finish Coat Electrical Room Lv-13
-
08/26→09/02
13
Concrete/Structure
Set Steel For Operable Partition
13B-IR-N2-200 Floor 13 - Set Steel For Operable Partition Floor 13 A Overhead Roughs
-
08/26→08/27
13A
Flooring/Finishes
N13504 - Prime & 1st Finish Coat
ELC-13-110 Floor 13A - N13504 - Prime & 1st Finish Coat Electrical Room Lv-13 N13504 13A
-
08/26→08/27
13A
HVAC/Mechanical
N13506 - Set AHU 13-2
13-M-160 Floor 13A - N13506 - Set AHU 13-2 Floor 13 A Mechanical Space N13506
-
08/26→09/01
3
Data
N3504 - Pull LV Riser Cable
TEL-3-230 Floor 3 - N3504 - Pull LV Riser Cable Telecom Room Lv-3 N3504
-
08/26→09/16
5B
Data
Pull Wire For All Low Voltage Systems
SC5B-N3-F-140 Floor 5B - Pull Wire For All Low Voltage Systems Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
08/26→09/01
5C
Fire/Sprinkler
Sprinkler Drops/Heads
SC5C-N1-F-430 Floor 5C - Sprinkler Drops/Heads Floor 5C SC 5.N1 Final Finishes
-
08/26→08/28
7
Ceilings
Install Remainder of Ceiling Tile
FL7-N1-520 Floor 7 - Install Remainder of Ceiling Tile Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/26→08/27
8
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
FL8-N1-750 Floor 8 - Drop Borders & Trade Cuts Ceiling Tiles Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/27→09/02
·
Drywall/Framing
IMRIS R10 - Wood Framing Walls
REV10-1460 IMRIS R10 - Wood Framing Walls IMRIS Interior Roughs & RF scope - Rev. 10
-
08/27→09/17
1
Inspections/QC
N1503 - Terminate & Test IT Systems Cabling
TEL-1-180 Floor 1 - N1503 - Terminate & Test IT Systems Cabling Telecom Room Lv-1 N1503
-
08/27→08/28
2
Data
N2503 - Clean I. T. Room
2-TEL-400 Floor 2 - N2503 - Clean I. T. Room Telecom Room Lv-2 N2503
-
08/27→09/17
2
Inspections/QC
N2504 - Terminate & Test IT Systems Cabling
2-TEL-100 Floor 2 - N2504 - Terminate & Test IT Systems Cabling Telecom Room Lv-2 N2504
-
08/27→09/02
5
Flooring/Finishes
Floor 5 South - Prime & 1st Coat
GBW-730 Floor 5 South - Prime & 1st Coat Floor 5 Testing/Commissioning/Life Safety
-
08/27→09/10
6
Drywall/Framing
Floor 6 South - Hang Drywall & Finish Drywall
GBW-840 Floor 6 South - Hang Drywall & Finish Drywall Floor 6 Testing/Commissioning/Life Safety
-
08/27→09/02
8
Electrical
Floor 8 N8502 - Pull & Terminate Feeders
ELC-8-360 Floor 8 N8502 - Pull & Terminate Feeders Electrical Room Lv-8 N8502
-
08/27→09/01
8
Other
Floor 8 N8503 - Install Plywood Back Boards
TEL-8-130 Floor 8 N8503 - Install Plywood Back Boards Telecom Room Lv-8 N8503
-
08/27→08/28
8
Flooring/Finishes
Floor 8 N8504 - Prime & 1st Finish Coat
TEL-8-150 Floor 8 N8504 - Prime & 1st Finish Coat Telecom Room Lv-8 N8504
-
08/27→09/02
8
Electrical
Floor 8 N8505 - Pull & Terminate Feeders
ELC-8-400 Floor 8 N8505 - Pull & Terminate Feeders Electrical Room Lv-8 N8505
-
08/28→09/25
10A
Plumbing
OH & In Wall MED Gas Rough In & QC
10A-IR-N1-1100 Floor 10A - OH & In Wall MED Gas Rough In & QC Floor 10A East Overhead Roughs
-
08/28→09/11
12
Electrical
N12505 - Pull & Terminate Feeders
ELC-12-160 Floor 12 - N12505 - Pull & Terminate Feeders Electrical Room Lv-12 N12505 Corridor 1 12A East, 12B East, 12C East
-
08/28→09/03
13
Electrical
N13502 - Install Electrical Panels/Equipment
ELC-13-170 Floor 13 - N13502 - Install Electrical Panels/Equipment Electrical Room Lv-13
-
08/28→09/03
13A
Electrical
N13504 - Install Electrical Panels/Equipment
ELC-13-150 Floor 13A - N13504 - Install Electrical Panels/Equipment Electrical Room Lv-13 N13504 13A
-
08/28→09/03
13A
HVAC/Mechanical
N13506 - AHU Drops/Duct Connections
13-M-180 Floor 13A - N13506 - AHU Drops/Duct Connections Floor 13 A Mechanical Space N13506
-
08/28→09/03
13A
HVAC/Mechanical
N13506 - AHU Drops/Piping Connections AHU
13-M-170 Floor 13A - N13506 - AHU Drops/Piping Connections AHU Floor 13 A Mechanical Space N13506
-
08/28→09/01
5C
Electrical
Remove Temp Light Fixtures
SC5C-N1-F-390 Floor 5C - Remove Temp Light Fixtures Floor 5C SC 5.N1 Final Finishes
-
08/28→08/31
6
Other
Div 10 Specalities
FL6-1340 6th Floor - Div 10 Specalities Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/28→08/31
6
Plumbing
Plumbing Fixtures
FL6-1310 6th Floor - Plumbing Fixtures Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
08/28→09/03
8
Inspections/QC
MEPF Overhead Inspections
FL8-N1-600 Floor 8 - MEPF Overhead Inspections Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/28→09/25
9A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
9A-F-N1-1060 Floor 9A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 9A East Final Finishes 9A
-
08/28→08/31
9B
Inspections/QC
OH Inspections - MEPF
9B-IR-N2-1180 Floor 9B - OH Inspections - MEPF West 9B West Overhead Roughs
-
08/28→09/25
9B
Data
Pull Wire For All Low Voltage Systems
9B-F-N2-1040 Floor 9B - Pull Wire For All Low Voltage Systems West 9B West Overhead Roughs
-
08/31→09/28
1
Ceilings
Install EFIS Soffit/Caulk
1EXT-150 Floor 01 - Install EFIS Soffit/Caulk 1st Floor
-
08/31→09/01
12
Flooring/Finishes
N12504- Prime & 1st Finish Coat
TEL-12-110 Floor 12 - N12504- Prime & 1st Finish Coat Telecom Room Lv-12 N12504
-
08/31→09/02
7
Flooring/Finishes
Finish Painting
FL7-N1-460 Floor 7 - Finish Painting Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
08/31→09/03
8
Other
Floor 8 N8504 - Install Plywood Back Boards
TEL-8-160 Floor 8 N8504 - Install Plywood Back Boards Telecom Room Lv-8 N8504
-
08/31→09/04
8
Flooring/Finishes
Install Doors & Hardware
FL8-N1-760 Floor 8 - Install Doors & Hardware Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/01→09/15
·
Other
Level 10 - Backwelding
BW-1090 Level 10 - Backwelding Detailing (Back Welding)
-
09/01→09/08
·
Fire/Sprinkler
Level 9 - Perimeter Firestopping
FSP-1070 Level 9 - Perimeter Firestopping Firestopping
-
09/01→09/15
9B
Drywall/Framing
Frame Soffits/Hard Ceilings
9B-IR-N2-1250 Floor 9B - Frame Soffits/Hard Ceilings West 9B West Overhead Roughs
-
09/01→09/29
9B
Electrical
Pull Branch Circuits
9B-IR-N2-1260 Floor 9B - Pull Branch Circuits West 9B West Overhead Roughs
-
09/02→09/03
12
Flooring/Finishes
N12501 - Prime & 1st Finish Coat
TEL-12-150 Floor 12 - N12501 - Prime & 1st Finish Coat Telecom Room Lv-12 N12501
-
09/02→09/08
12
Other
N12504 - Install Plywood Back Boards
TEL-12-130 Floor 12 - N12504 - Install Plywood Back Boards Telecom Room Lv-12 N12504
-
09/02→09/16
12B
Electrical
Install High OH Electrical Conduit Racks (Corridor & Elect Rms)
12B-IR-N2-2010 Floor 12B - Install High OH Electrical Conduit Racks (Corridor & Elect Rms) Floor 12 B West Overhead Roughs
-
09/02→09/09
3
Data
N3503 - Pull LV Riser Cable
TEL-3-220 Floor 3 - N3503 - Pull LV Riser Cable Telecom Room Lv-3 N3503
-
Wed 09/02
3
Data
N3504 - Install I. T. Rooms Doors
TEL-3-250 Floor 3 - N3504 - Install I. T. Rooms Doors Telecom Room Lv-3 N3504
-
09/02→09/03
3B
Ceilings
Ceiling Grid QC
SC3B-N3-F-400 Floor 3B - Ceiling Grid QC Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
09/02→09/04
3B
Electrical
Remove Temp Light Fixtures
SC3B-N3-F-320 Floor 3B - Remove Temp Light Fixtures Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
Wed 09/02
8
Flooring/Finishes
Floor 8 N8503 - Paint Plywood Back Boards
TEL-8-190 Floor 8 N8503 - Paint Plywood Back Boards Telecom Room Lv-8 N8503
-
09/03→09/04
·
Other
IMRIS R10 - Inwall Controls
REV10-1470 IMRIS R10 - Inwall Controls IMRIS Interior Roughs & RF scope - Rev. 10
-
09/03→09/17
·
Electrical
IMRIS R10 - Inwall Electrical
REV10-1490 IMRIS R10 - Inwall Electrical IMRIS Interior Roughs & RF scope - Rev. 10
-
09/03→09/17
·
Plumbing
IMRIS R10 - Inwall Plumbing/Med Gas
REV10-1480 IMRIS R10 - Inwall Plumbing/Med Gas IMRIS Interior Roughs & RF scope - Rev. 10
-
09/03→10/01
11A
Electrical
OH-Electrical Rough/Racks Systems
11A-IR-N1-1030 Floor 11A - OH-Electrical Rough/Racks Systems Floor 11A East Overhead Roughs
-
09/03→09/08
13
Inspections/QC
Level 13 - Gilbane QC
L13RA-150 Level 13 - Gilbane QC Level 13 Roofing & Assembly
-
09/03→09/17
2A
Flooring/Finishes
Final Paint
SC2A-N2-F-450 Floor 2A - Final Paint Floor 2A SC 2.N2 Final Finishes
-
09/03→09/17
2B
Flooring/Finishes
Set Casework/Countertops
SC2B-N3-F-240 Floor 2B - Set Casework/Countertops Floor 2B SC 2.N3
-
09/03→09/17
2C
Other
Div 10 Accessories
SC2C-N1-F-420 Floor 2C - Div 10 Accessories Floor 2C SC 2.N1 Final Finishes
-
09/03→09/10
4C
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC4C-N1-F-940 Floor 4C - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 4C SC 4.N1 Final Finishes
-
09/03→09/24
5
Electrical
Floor 5 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-740 Floor 5 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 5 Testing/Commissioning/Life Safety
-
09/03→09/10
5A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC5A-N2-F940 Floor 5A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 5A SC 5.N2 Final Finishes
-
09/03→09/10
5B
Inspections/QC
In-Wall Gilbane QC
SC5B-N3-IR-170 Floor 5B - In-Wall Gilbane QC Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
09/03→09/04
5B
Plumbing
Med Gas Pre Certification
SC5B-N3-IR-330 Floor 5B - Med Gas Pre Certification Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
09/03→10/01
5B
Electrical
Pull Branch Circuits
SC5B-N3-IR-250 Floor 5B - Pull Branch Circuits Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
09/03→09/08
7
Other
Construction Clean
FL7-N1-530 Floor 7 - Construction Clean Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/03→09/08
8
Electrical
Floor 8 N8503 - OH Conduit Rough-In
TEL-8-140 Floor 8 N8503 - OH Conduit Rough-In Telecom Room Lv-8 N8503
-
09/04→09/08
10A
Plumbing
In-Wall Inspections - Plumbing
10A-IR-N1-1060 Floor 10A - In-Wall Inspections - Plumbing Floor 10A East Framing & Interior Roughs
-
09/04→09/10
12
Other
N12501 - Install Plywood Back Boards
TEL-12-160 Floor 12 - N12501 - Install Plywood Back Boards Telecom Room Lv-12 N12501
-
09/04→09/18
13
Electrical
N13502 - Pull & Terminate Feeders
ELC-13-200 Floor 13 - N13502 - Pull & Terminate Feeders Electrical Room Lv-13
-
09/04→09/18
13A
Electrical
N13504 - Pull & Terminate Feeders
ELC-13-160 Floor 13A - N13504 - Pull & Terminate Feeders Electrical Room Lv-13 N13504 13A
-
09/04→09/15
13A
HVAC/Mechanical
N13506 - BMS Controls AHU
13-M-190 Floor 13A - N13506 - BMS Controls AHU Floor 13 A Mechanical Space N13506
-
09/04→09/08
1B
Inspections/QC
OH Gilbane QC & Final Inspections
SC1B-N1-IR-230 Floor 1B - OH Gilbane QC & Final Inspections Floor 1B SC 1.N2 Overhead & Finishes
-
Fri 09/04
8
Flooring/Finishes
Floor 8 N8504 - Paint Plywood Back Boards
TEL-8-210 Floor 8 N8504 - Paint Plywood Back Boards Telecom Room Lv-8 N8504
-
09/04→09/09
8
Ceilings
Install Remainder of Ceiling Tile
FL8-N1-840 Floor 8 - Install Remainder of Ceiling Tile Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/08→09/14
11
Flooring/Finishes
Floor 11 North - Prime & 1st Coat
GBW-1370 Floor 11 North - Prime & 1st Coat Floor 11 Testing/Commissioning/Life Safety
-
09/08→09/09
13
Flooring/Finishes
N13501 - Prime & 1st Finish Coat
TEL-13-150 Floor 13 - N13501 - Prime & 1st Finish Coat Telecom Room Lv-13 N13501
-
09/08→09/17
13
Drywall/Framing
N13505 - Hang/Tape/Finish Wall Board
TEL-13-100 Floor 13 - N13505 - Hang/Tape/Finish Wall Board Telecom Room Lv-13 N13505
-
09/08→09/28
2C
Flooring/Finishes
Set Lockers
SC2C-N1-F-350 Floor 2C - Set Lockers Floor 2C SC 2.N1 Final Finishes
-
09/08→09/17
3
Electrical
Bridge - OH Electrical 3rd Floor
BRIDGE-360 Bridge - OH Electrical 3rd Floor New Bridge
-
09/08→09/14
6
Flooring/Finishes
Casework/Countertops
FL6-1230 6th Floor - Casework/Countertops Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/08→09/14
6
Flooring/Finishes
Doors & Hardware
FL6-1300 6th Floor - Doors & Hardware Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/08→09/28
6
Ceilings
MEP Trim Out Devices In Ceilings & Walls
FL6-1060 6th Floor - MEP Trim Out Devices In Ceilings & Walls Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/08→09/21
6
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
FL6-1090 6th Floor - Wall Crash Rails/Hand Rails/Corner Guards Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/08→09/10
8
Flooring/Finishes
Finish Painting
FL8-N1-790 Floor 8 - Finish Painting Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/08→09/10
8
Electrical
Floor 8 N8504 - OH Conduit Rough-In
TEL-8-180 Floor 8 N8504 - OH Conduit Rough-In Telecom Room Lv-8 N8504
-
09/08→09/14
8
Inspections/QC
Test & Balance
FL8-N1-830 Floor 8 - Test & Balance Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/09→09/22
13
Other
Floor 13 North - In Wall MEPF Rough In
GBW-1620 Floor 13 North - In Wall MEPF Rough In Floor 13 Go Back Work - Pads North
-
09/09→09/11
13
Inspections/QC
Level 13 - Final Clean & Punch
L13RA-160 Level 13 - Final Clean & Punch Level 13 Roofing & Assembly
-
09/09→09/29
1A
Plumbing
In-Wall Plumbing Rough & QC
SC1A-N2-IR-120 Floor 1A - In-Wall Plumbing Rough & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/09→10/06
1A
Electrical
OH Electrical Rough In & QC
SC1A-N2-IR-180 Floor 1A - OH Electrical Rough In & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/09→09/22
1A
Data
OH Low Voltage Pipe Rough-In
SC1A-N2-IR-100 Floor 1A - OH Low Voltage Pipe Rough-In Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/09→09/22
1A
Fire/Sprinkler
OH Sprinkler Rough In & QC
SC1A-N2-IR-280 Floor 1A - OH Sprinkler Rough In & QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/09→10/06
1B
Concrete/Structure
Install Sheating & Water Proofing
SC1B-N1-IR-250 Floor 1B - Install Sheating & Water Proofing Floor 1B SC 1.N2 Overhead & Finishes
-
09/09→09/15
2A
Inspections/QC
Final OH MEPF Inspections
SC2A-N2-F-490 Floor 2A - Final OH MEPF Inspections Floor 2A SC 2.N2 Final Finishes
-
09/09→09/22
2C
Plumbing
Plumbing Trim Out
SC2C-N1-F-280 Floor 2C - Plumbing Trim Out Floor 2C SC 2.N1 Final Finishes
-
09/09→09/10
4C
Ceilings
Ceiling Grid QC
SC4C-N1-F-470 Floor 4C - Ceiling Grid QC Floor 4C SC 4.N1 Final Finishes
-
09/09→09/29
5A
Data
All Low Voltage Devices
SC5A-N2-F-340 Floor 5A - All Low Voltage Devices Floor 5A SC 5.N2 Final Finishes
-
09/09→09/15
6
Other
Floor 6 South Set Equipment
GBW-930 Floor 6 South Set Equipment Floor 6 Testing/Commissioning/Life Safety
-
09/09→09/10
7
Inspections/QC
Load Equipment
FL7-N1-540 Floor 7 - Load Equipment Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/09→09/14
8
Electrical
Floor 8 N8503 - Install Grounding Buss
TEL-8-170 Floor 8 N8503 - Install Grounding Buss Telecom Room Lv-8 N8503
-
09/09→09/22
9
Drywall/Framing
Floor 9 South - Layout, Frame & Insulate Walls
GBW-940 Floor 9 South - Layout, Frame & Insulate Walls Floor 9 Testing/Commissioning/Life Safety
-
09/10→09/14
12
Electrical
N12504 - OH Conduit Rough-In
TEL-12-140 Floor 12 - N12504 - OH Conduit Rough-In Telecom Room Lv-12 N12504
-
09/10→09/30
12A
Electrical
Electrical Terminations to Headwall
12A-IR-N1-1170 Floor 12A - Electrical Terminations to Headwall Floor 12 A East Framing & Interior Roughs
-
09/10→09/21
12A
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
12A-IR-N1-1160 Floor 12A - Med Gas Zone Valve Boxes/Terminations to Headwall Floor 12 A East Framing & Interior Roughs
-
09/10→09/15
13
Other
N13501 - Install Plywood Back Boards
TEL-13-160 Floor 13 - N13501 - Install Plywood Back Boards Telecom Room Lv-13 N13501
-
Thu 09/10
3
Data
N3503 - Install I. T. Rooms Doors
TEL-3-240 Floor 3 - N3503 - Install I. T. Rooms Doors Telecom Room Lv-3 N3503
-
09/10→09/16
3
Data
N3504- Pull LV Riser Cable
TEL-3-370 Floor 3 - N3504- Pull LV Riser Cable Telecom Room Lv-3 N3204
-
09/10→09/30
3A
Plumbing
Common Area Plumbing Trim Out
SC3A-N2-F-300 Floor 3A - Common Area Plumbing Trim Out Floor 3A SC 3.N2 Final Finishes
-
09/10→09/23
3A
Electrical
Electrical Wall Fixtures/Devices
SC3A-N2-F-460 Floor 3A - Electrical Wall Fixtures/Devices Floor 3A SC 3.N2 Final Finishes
-
09/10→09/16
3A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC3A-N2-F-342 Floor 3A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 3A SC 3.N2 Final Finishes
-
09/10→09/16
3A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC3A-N2-F-270 Floor 3A - Install Special Wall Finishes (incl. Wall Protection) Floor 3A SC 3.N2 Final Finishes
-
09/11→09/30
·
Concrete/Structure
Install Precast Panels Levels10-12 (Set 12 WS)
E-810 Install Precast Panels Levels10-12 (Set 12 WS) Precast
-
09/11→09/17
·
Inspections/QC
Install Punch Windows - Set 11
EXG-1100 Install Punch Windows - Set 11 Exterior Glass & Glazing South Elevation (Punch Windows)
-
09/11→09/24
10B
Data
OH Low Voltage Pipe Rough-In
10B-IR-N2-1000 Floor 10B - OH Low Voltage Pipe Rough-In Floor 10B West Overhead Roughs
-
09/11→09/14
2
Data
N2501 - Clean I. T. Room
2-TEL-490 Floor 2 - N2501 - Clean I. T. Room Telecom Room Lv-2 N2501 MDF
-
09/11→09/17
2A
Electrical
Electrical Wall Fixtures/Devices
SC2A-N2-F-470 Floor 2A - Electrical Wall Fixtures/Devices Floor 2A SC 2.N2 Final Finishes
-
Fri 09/11
3
Data
N3501 - Install I. T. Rooms Doors
TEL-3070 Floor 3 - N3501 - Install I. T. Rooms Doors Telecom Room Lv-3 N3501
-
09/11→09/14
5A
Plumbing
Common Area Plumbing Trim Out
SC5A-N2-F-400 Floor 5A - Common Area Plumbing Trim Out Floor 5A SC 5.N2 Final Finishes
-
09/11→09/14
5B
Inspections/QC
In-Wall Inspections - MEPF
SC5B-N3-IR-190 Floor 5B - In-Wall Inspections - MEPF Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
09/11→09/24
5B
Electrical
Rough-in Can Lights to Hard Ceiling
SC5B-N3-IR-490 Floor 5B - Rough-in Can Lights to Hard Ceiling Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
09/11→09/14
7
Inspections/QC
Owner Pre AHCA
FL7-N1-550 Floor 7 - Owner Pre AHCA Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/11→09/14
8
Other
Construction Clean
FL8-N1-850 Floor 8 - Construction Clean Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/11→09/16
8
Electrical
Floor 8 N8504 - Install Grounding Buss
TEL-8-200 Floor 8 N8504 - Install Grounding Buss Telecom Room Lv-8 N8504
-
09/14→09/16
12
Electrical
N12501 - OH Conduit Rough-In
TEL-12-180 Floor 12 - N12501 - OH Conduit Rough-In Telecom Room Lv-12 N12501
-
09/14→09/18
3B
Inspections/QC
AHCA 80% Inspection
SC3B-N3-F-340 Floor 3B - AHCA 80% Inspection Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
09/15→10/05
11
Electrical
Floor 11 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1380 Floor 11 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 11 Testing/Commissioning/Life Safety
-
09/15→09/28
12
Drywall/Framing
Floor 12 North - Hang Drywall & Finish Drywall
GBW-1510 Floor 12 North - Hang Drywall & Finish Drywall Floor 12 Go Back Work - Pads North
-
09/15→09/18
12
Electrical
N12504 - Install Grounding Buss
TEL-12-170 Floor 12 - N12504 - Install Grounding Buss Telecom Room Lv-12 N12504
-
09/15→09/28
5B
Drywall/Framing
Blocking/Backing/Plywood
SC5B-N3-IR-260 Floor 5B - Blocking/Backing/Plywood Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
09/15→09/16
5C
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
SC5A-N2-F950 Floor 5C - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 5C SC 5.N1 Final Finishes
-
09/15→09/21
5C
Plumbing
Common Area Plumbing Trim Out
SC5C-N1-F-280 Floor 5C - Common Area Plumbing Trim Out Floor 5C SC 5.N1 Final Finishes
-
09/15→09/21
6
Inspections/QC
80% AHCA
FL6-1150 6th Floor - 80% AHCA Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/15→09/16
7
Inspections/QC
Stocking
FL7-N1-560 Floor 7 - Stocking Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/15→09/28
8
Inspections/QC
Gilbane Functional/Pre-Inspections
P8-1010 Floor 8 - Gilbane Functional/Pre-Inspections Floor 8 Clean & Punch-Out
-
09/15→09/16
8
Inspections/QC
Load Equipment
FL8-N1-860 Floor 8 - Load Equipment Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/16→10/06
·
Electrical
Elevator 1-2 - Install Electrical & Rope
ELV-410 Elevator 1-2 - Install Electrical & Rope Elevator 1-2
-
09/16→09/22
·
Fire/Sprinkler
Level 10 - Perimeter Firestopping
FSP-1080 Level 10 - Perimeter Firestopping Firestopping
-
09/16→09/29
·
Other
Level 11 - Backwelding
BW-1100 Level 11 - Backwelding Detailing (Back Welding)
-
09/16→10/02
13
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
13EXT-200 Floor 13 - Field Measure & Fab. Metal Drip Edge 13th Floor
-
Wed 09/16
13
Flooring/Finishes
N13501 - Paint Plywood Back Boards
TEL-13-360 Floor 13 - N13501 - Paint Plywood Back Boards Telecom Room Lv-13 N13501
-
09/16→09/29
13A
Electrical
N13506 - Install & Electronically Connect VFD's
13-M-200 Floor 13A - N13506 - Install & Electronically Connect VFD's Floor 13 A Mechanical Space N13506
-
09/16→09/29
1A
Data
OH Install Low Voltage RI
SC1A-N2-IR-250 Floor 1A - OH Install Low Voltage RI Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/16→09/17
2A
Ceilings
Install Balance of Ceiling Tile
SC2A-N2-F-510 Floor 2A - Install Balance of Ceiling Tile Floor 2A SC 2.N2 Final Finishes
-
09/16→09/29
5C
Electrical
Light Fixtures in Grid
SC5C-N1-F-440 Floor 5C - Light Fixtures in Grid Floor 5C SC 5.N1 Final Finishes
-
09/16→09/22
6
Flooring/Finishes
Floor 6 South - Prime & 1st Coat
GBW-850 Floor 6 South - Prime & 1st Coat Floor 6 Testing/Commissioning/Life Safety
-
09/16→09/25
9A
Fire/Sprinkler
Fire Stopping/Labeling
9A-F-N1-1040 Floor 9A - Fire Stopping/Labeling Floor 9A East Final Finishes 9A
-
09/16→09/22
9B
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
9B-F-N2-1010 Floor 9B - HVAC Drops & Diffusers in Soffit West 9B West Overhead Roughs
-
09/16→10/06
9B
Electrical
RI Light Fixtures Hard Ceilings & Soffits
9B-F-N2-1020 Floor 9B - RI Light Fixtures Hard Ceilings & Soffits West 9B West Overhead Roughs
-
09/17→09/22
12
Electrical
N12501 - Install Grounding Buss
TEL-12-200 Floor 12 - N12501 - Install Grounding Buss Telecom Room Lv-12 N12501
-
09/17→09/18
12
Flooring/Finishes
N12502 - Prime & 1st Finish Coat
ELC-12-130 Floor 12 - N12502 - Prime & 1st Finish Coat Electrical Room Lv-12 N12502 Corridor 2 12A West, 12B West, 12C West
-
09/17→09/18
12
HVAC/Mechanical
Set AHU 12-1
12-M-100 Set AHU 12-1 Floor 12 B Mechanical Space N12503
-
09/17→09/30
12B
Other
Install Pre-Fab Headwalls
12B-IR-N2-1130 Floor 12B - Install Pre-Fab Headwalls Floor 12 B West Framing & Interior Roughs
-
09/17→09/30
13
Electrical
Install High OH Electrical Conduit Racks
13B-IR-N2-600 Floor 13 - Install High OH Electrical Conduit Racks Floor 13 A Overhead Roughs
-
09/17→09/21
13
Electrical
N13501 - OH Conduit Rough-In
TEL-13-180 Floor 13 - N13501 - OH Conduit Rough-In Telecom Room Lv-13 N13501
-
Thu 09/17
3
Data
N3504- Install I. T. Rooms Doors
TEL-3-430 Floor 3 - N3504- Install I. T. Rooms Doors Telecom Room Lv-3 N3204
-
09/17→09/23
3A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC3A-N2-F-420 Floor 3A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 3A SC 3.N2 Final Finishes
-
09/17→09/30
3A
Plumbing
Plumbing Fixtures
SC3A-N2-F-350 Floor 3A - Plumbing Fixtures Floor 3A SC 3.N2 Final Finishes
-
09/17→09/23
3A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC3A-N2-F-290 Floor 3A - Wall Crash Rails/Hand Rails/Corner Guards Floor 3A SC 3.N2 Final Finishes
-
09/17→09/23
3C
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC3C-N1-F-280 Floor 3C - Install Special Wall Finishes (incl. Wall Protection) Floor 3C SC 3.N1 Final Finishes
-
09/17→09/23
4
Data
Floor 4 N4504 - Pull LV Riser Cable
TEL-4-240 Floor 4 N4504 - Pull LV Riser Cable Telecom Room Lv-4 N4504
-
09/17→09/23
5C
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC5A-N2-F960 Floor 5C - Flooring - SV Flooring + Cove Base` (FL-1) Floor 5C SC 5.N1 Final Finishes
-
09/17→09/18
7
Other
Final Clean
FL7-N1-570 Floor 7 - Final Clean Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/17→09/18
8
Inspections/QC
Owner Pre AHCA
FL8-N1-870 Floor 8 - Owner Pre AHCA Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/18→09/29
·
Other
Bridge - Overhead Fire Protection 2 & 3
BRIDGE-370 Bridge - Overhead Fire Protection 2 & 3 New Bridge
-
09/18→09/22
·
Other
IMRIS R10 - Quench Vent Shield Tie-In
REV10-1500 IMRIS R10 - Quench Vent Shield Tie-In IMRIS Interior Roughs & RF scope - Rev. 10
-
09/18→10/01
·
Concrete/Structure
Install Exterior Louvers South
ELS-100 Install Exterior Louvers South Exterior Louvers
-
09/18→09/21
1
Data
N1503 - Clean I. T. Room
TEL-1-190 Floor 1 - N1503 - Clean I. T. Room Telecom Room Lv-1 N1503
-
09/18→09/21
13
Flooring/Finishes
N13505 - Prime & 1st Finish Coat
TEL-13-110 Floor 13 - N13505 - Prime & 1st Finish Coat Telecom Room Lv-13 N13505
-
09/18→09/21
2
Data
N2504 - Clean I. T. Room
2-TEL-180 Floor 2 - N2504 - Clean I. T. Room Telecom Room Lv-2 N2504
-
09/18→09/24
2A
Flooring/Finishes
Signage
SC2A-N2-F-480 Floor 2A - Signage Floor 2A SC 2.N2 Final Finishes
-
09/18→10/01
2A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC2A-N2-F-390 Floor 2A - Wall Crash Rails/Hand Rails/Corner Guards Floor 2A SC 2.N2 Final Finishes
-
09/18→10/01
2B
Flooring/Finishes
Flooring Base
SC2B-N3-F-400 Floor 2B - Flooring Base Floor 2B SC 2.N3
-
09/18→10/01
2C
Electrical
Electrical Wall Fixtures/Devices
SC2C-N1-F-300 Floor 2C - Electrical Wall Fixtures/Devices Floor 2C SC 2.N1 Final Finishes
-
09/18→10/08
3
Inspections/QC
N3504- Terminate & Test IT Systems Cabling
TEL-3-360 Floor 3 - N3504- Terminate & Test IT Systems Cabling Telecom Room Lv-3 N3204
-
09/21→10/09
10A
Electrical
Electrical Terminations to Headwall
10A-IR-N1-1170 Floor 10A - Electrical Terminations to Headwall Floor 10A East Framing & Interior Roughs
-
09/21→10/16
10B
Data
Pull Wire For All Low Voltage Systems
10B-IR-N2-1040 Floor 10B - Pull Wire For All Low Voltage Systems Floor 10B West Overhead Roughs
-
09/21→10/16
11A
Plumbing
In-Wall Plumbing Rough QC
11A-IR-N1-1020 Floor 11A - In-Wall Plumbing Rough QC Floor 11A East Framing & Interior Roughs
-
09/21→09/25
12
HVAC/Mechanical
AHU Drops/Piping Connections AHU N12503
12-M-110 AHU Drops/Piping Connections AHU N12503 Floor 12 B Mechanical Space N12503
-
09/21→09/25
12
Electrical
N12502 - Install Electrical Panels/Equipment
ELC-12-170 Floor 12 - N12502 - Install Electrical Panels/Equipment Electrical Room Lv-12 N12502 Corridor 2 12A West, 12B West, 12C West
-
09/21→09/22
13A
HVAC/Mechanical
N13503 - Set AHU 13-1
13-M-220 Floor 13A - N13503 - Set AHU 13-1 Floor 13 A Mechanical Space N13503
-
09/21→09/22
8
Inspections/QC
Stocking
FL8-N1-880 Floor 8 - Stocking Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/22→09/28
12
Data
N12504 - Install Racks & Ladder Tray
TEL-12-190 Floor 12 - N12504 - Install Racks & Ladder Tray Telecom Room Lv-12 N12504
-
09/22→09/28
12A
Plumbing
Med Gas Testing
12A-IR-N1-1210 Floor 12A - Med Gas Testing Floor 12 A East Framing & Interior Roughs
-
09/22→09/25
13
Electrical
N13501 - Install Grounding Buss
TEL-13-200 Floor 13 - N13501 - Install Grounding Buss Telecom Room Lv-13 N13501
-
09/22→09/25
13
Other
N13505 - Install Plywood Back Boards
TEL-13-130 Floor 13 - N13505 - Install Plywood Back Boards Telecom Room Lv-13 N13505
-
09/22→09/28
4B
Flooring/Finishes
Paint Prime & First Coat
SC4B-N3-F-230 Floor 4B - Paint Prime & First Coat Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
09/22→09/28
6
Ceilings
Install Balance of Ceiling Tiles
FL6-1330 6th Floor - Install Balance of Ceiling Tiles Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
Wed 09/23
·
Inspections/QC
IMRIS R10 - In Wall Inspection
REV10-1510 IMRIS R10 - In Wall Inspection IMRIS Interior Roughs & RF scope - Rev. 10
-
09/23→10/06
10
Drywall/Framing
Floor 10 South - Layout, Frame & Insulate Walls
GBW-1090 Floor 10 South - Layout, Frame & Insulate Walls Floor 10 Testing/Commissioning/Life Safety
-
09/23→10/20
11A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
11A-IR-N1-1050 Floor 11A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 11A East Framing & Interior Roughs
-
09/23→10/20
13
Other
Floor 13 North - OH MEPF Rougth In
GBW-1610 Floor 13 North - OH MEPF Rougth In Floor 13 Go Back Work - Pads North
-
09/23→09/29
13A
HVAC/Mechanical
N13503 - AHU Drops/Duct Connections
13-M-240 Floor 13A - N13503 - AHU Drops/Duct Connections Floor 13 A Mechanical Space N13503
-
09/23→09/29
13A
HVAC/Mechanical
N13503 - AHU Drops/Piping Connections AHU
13-M-230 Floor 13A - N13503 - AHU Drops/Piping Connections AHU Floor 13 A Mechanical Space N13503
-
09/23→10/13
6
Electrical
Floor 6 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-860 Floor 6 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 6 Testing/Commissioning/Life Safety
-
09/23→09/24
8
Other
Final Clean
FL8-N1-890 Floor 8 - Final Clean Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
09/23→09/25
9
Other
Floor 9 South - Set Bathroom Pods
GBW-1080 Floor 9 South - Set Bathroom Pods Floor 9 Testing/Commissioning/Life Safety
-
09/24→09/29
·
Drywall/Framing
CT R10 - Frame Walls & Top Out
REV10-1520 CT R10 - Frame Walls & Top Out CT Overhead Roughst - Rev. 10
-
09/24→10/07
11A
Electrical
Install OH Cable Tray
11A-IR-N1-1220 Floor 11A - Install OH Cable Tray Floor 11A East Overhead Roughs
-
09/24→09/30
12
Data
N12501 - Install Racks & Ladder Tray
TEL-12-210 Floor 12 - N12501 - Install Racks & Ladder Tray Telecom Room Lv-12 N12501
-
09/24→10/14
3
Inspections/QC
N3504 - Terminate & Test IT Systems Cabling
TEL-3-270 Floor 3 - N3504 - Terminate & Test IT Systems Cabling Telecom Room Lv-3 N3504
-
09/24→10/05
3A
Flooring/Finishes
Doors & Hardware
SC3A-N2-F-330 Floor 3A - Doors & Hardware Floor 3A SC 3.N2 Final Finishes
-
09/24→09/30
3A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC3A-N2-F-310 Floor 3A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 3A SC 3.N2 Final Finishes
-
09/24→10/07
3B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC3B-N3-F-280 Floor 3B - Install Special Wall Finishes (incl. Wall Protection) Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
09/24→10/07
3C
Electrical
Electrical Wall Fixtures/Devices
SC3C-N1-F-300 Floor 3C - Electrical Wall Fixtures/Devices Floor 3C SC 3.N1 Final Finishes
-
09/24→09/30
3C
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC3C-N1-F-260 Floor 3C - Wall Crash Rails/Hand Rails/Corner Guards Floor 3C SC 3.N1 Final Finishes
-
09/24→09/30
4
Data
Floor 4 N4501 - Pull LV Riser Cable
TEL-4-460 Floor 4 N4501 - Pull LV Riser Cable Telecom Room Lv-4 N4501
-
Thu 09/24
4
Data
Floor 4 N4504 - Install I. T. Rooms Doors
TEL-4-260 Floor 4 N4504 - Install I. T. Rooms Doors Telecom Room Lv-4 N4504
-
09/24→09/30
5A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC5A-N2-F-370 Floor 5A - Install Special Wall Finishes (incl. Wall Protection) Floor 5A SC 5.N2 Final Finishes
-
09/24→09/30
5C
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC5A-N2-F970 Floor 5C - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 5C SC 5.N1 Final Finishes
-
09/25→10/15
4
Inspections/QC
Floor 4 N4504 - Terminate & Test IT Systems Cabling
TEL-4-280 Floor 4 N4504 - Terminate & Test IT Systems Cabling Telecom Room Lv-4 N4504
-
09/25→10/01
5B
Ceilings
OR Ceilings GBCo Above Ceiling Inspections
SC5B-N3-IR-420 Floor 5B - OR Ceilings GBCo Above Ceiling Inspections Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
09/25→09/28
5B
Ceilings
OR Ceilings Owner/AE Layout Inspection
SC5B-N3-IR-430 Floor 5B - OR Ceilings Owner/AE Layout Inspection Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
09/28→09/29
10A
Inspections/QC
OH Inspections - MEPF
10A-IR-N1-1200 Floor 10A - OH Inspections - MEPF Floor 10A East Overhead Roughs
-
09/28→10/09
12
Electrical
N12502 - Pull & Terminate Feeders
ELC-12-200 Floor 12 - N12502 - Pull & Terminate Feeders Electrical Room Lv-12 N12502 Corridor 2 12A West, 12B West, 12C West
-
Mon 09/28
13
Concrete/Structure
N13501 - Seal Concrete Floor
TEL-13-370 Floor 13 - N13501 - Seal Concrete Floor Telecom Room Lv-13 N13501
-
09/28→10/09
9
Other
Floor 9 South - In Wall MEPF Rough In
GBW-960 Floor 9 South - In Wall MEPF Rough In Floor 9 Testing/Commissioning/Life Safety
-
09/28→10/23
9
Other
Floor 9 South - OH MEPF Rougth In
GBW-950 Floor 9 South - OH MEPF Rougth In Floor 9 Testing/Commissioning/Life Safety
-
09/28→10/23
9A
Drywall/Framing
Finish Drywall
9A-F-N1-1080 Floor 9A - Finish Drywall Floor 9A East Final Finishes 9A
-
09/29→10/15
1
Concrete/Structure
Field Measure & Fab. Metal Drip Edge
1EXT-200 Floor 01 - Field Measure & Fab. Metal Drip Edge 1st Floor
-
09/29→10/05
12
Flooring/Finishes
Floor 12 North - Prime & 1st Coat
GBW-1520 Floor 12 North - Prime & 1st Coat Floor 12 Go Back Work - Pads North
-
09/29→10/05
13
Data
N13501 - Install Racks & Ladder Tray
TEL-13-210 Floor 13 - N13501 - Install Racks & Ladder Tray Telecom Room Lv-13 N13501
-
09/29→10/01
13
Electrical
N13505 - OH Conduit Rough-In
TEL-13-140 Floor 13 - N13505 - OH Conduit Rough-In Telecom Room Lv-13 N13505
-
09/29→10/14
2C
Flooring/Finishes
Final Paint
SC2C-N1-F-380 Floor 2C - Final Paint Floor 2C SC 2.N1 Final Finishes
-
09/29→10/01
4B
Flooring/Finishes
Grout Bed for Floor Tile
SC4B-N3-F-210 Floor 4B - Grout Bed for Floor Tile Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
09/29→10/07
4B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC4B-N3-F-290 Floor 4B - HVAC Drops & Diffusers/Grid Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
09/29→10/05
4B
Ceilings
Install Ceiling Grid
SC4B-N3-F-260 Floor 4B - Install Ceiling Grid Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
09/29→10/08
4B
Electrical
Light Fixtures in Soffit
SC4B-N3-F-250 Floor 4B - Light Fixtures in Soffit Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
09/29→10/05
5B
Drywall/Framing
Framing Inspections
SC5B-N3-F-160 Floor 5B - Framing Inspections Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
09/29→10/08
6
Flooring/Finishes
Finish Paint
FL6-1070 6th Floor - Finish Paint Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
09/29→10/12
8
Inspections/QC
Gilbane/Contractor Punch-list
P8-1060 Floor 8 - Gilbane/Contractor Punch-list Floor 8 Clean & Punch-Out
-
09/30→10/06
·
Drywall/Framing
Bridge - Frame Soffit on Level 2 & 3
BRIDGE-380 Bridge - Frame Soffit on Level 2 & 3 New Bridge
-
09/30→10/13
·
HVAC/Mechanical
CT R10 - Install O.H. Ductwork
REV10-1550 CT R10 - Install O.H. Ductwork CT Overhead Roughst - Rev. 10
-
09/30→10/13
·
Electrical
CT R10 - O.H. Electrical
REV10-1570 CT R10 - O.H. Electrical CT Overhead Roughst - Rev. 10
-
09/30→10/06
·
Plumbing
CT R10 - O.H. Med Gas
REV10-1540 CT R10 - O.H. Med Gas CT Overhead Roughst - Rev. 10
-
09/30→10/06
·
Plumbing
CT R10 - O.H. Plumbing
REV10-1530 CT R10 - O.H. Plumbing CT Overhead Roughst - Rev. 10
-
09/30→10/13
·
Other
CT R10 - Process Water Piping
REV10-1560 CT R10 - Process Water Piping CT Overhead Roughst - Rev. 10
-
09/30→10/06
·
Fire/Sprinkler
Level 11 - Perimeter Firestopping
FSP-1090 Level 11 - Perimeter Firestopping Firestopping
-
09/30→10/13
·
Other
Level 12 - Backwelding
BW-1110 Level 12 - Backwelding Detailing (Back Welding)
-
09/30→10/13
10A
Drywall/Framing
Frame Soffits/Hard Ceilings
10A-IR-N1-1230 Floor 10A - Frame Soffits/Hard Ceilings Floor 10A East Overhead Roughs
-
09/30→10/27
10A
Electrical
Pull Branch Circuit
10A-IR-N1-1240 Floor 10A - Pull Branch Circuit Floor 10A East Overhead Roughs
-
09/30→10/08
13A
HVAC/Mechanical
N13503 - BMS Controls AHU
13-M-250 Floor 13A - N13503 - BMS Controls AHU Floor 13 A Mechanical Space N13503
-
09/30→10/01
1A
Inspections/QC
In-Wall Gilbane QC
SC1A-N2-IR-130 Floor 1A - In-Wall Gilbane QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/30→10/01
1A
Plumbing
In-Wall Inspections - Plumbing
SC1A-N2-IR-140 Floor 1A - In-Wall Inspections - Plumbing Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/30→10/06
1A
Electrical
Install OH Cable Tray
SC1A-N2-IR-310 Floor 1A - Install OH Cable Tray Floor 1A SC 1.N1 Framing & Interior Roughs
-
09/30→10/01
5A
Ceilings
Ceiling Grid QC
SC5A-N2-F-350 Floor 5A - Ceiling Grid QC Floor 5A SC 5.N2 Final Finishes
-
09/30→10/20
5C
Data
All Low Voltage Devices
SC5C-N1-F-450 Floor 5C - All Low Voltage Devices Floor 5C SC 5.N1 Final Finishes
-
10/01→10/22
·
Concrete/Structure
Install Precast Panels Levels 12-Roof (Set 13 WS)
E-820 Install Precast Panels Levels 12-Roof (Set 13 WS) Precast
-
10/01→10/07
·
Inspections/QC
Install Punch Windows - Set 12
EXG-1140 Install Punch Windows - Set 12 Exterior Glass & Glazing South Elevation (Punch Windows)
-
10/01→10/21
12B
Electrical
Electrical Terminations to Headwall
12B-IR-N2-1170 Floor 12B - Electrical Terminations to Headwall Floor 12 B West Framing & Interior Roughs
-
10/01→10/05
3A
Other
Div 10 Accessories
SC3A-N2-F-450 Floor 3A - Div 10 Accessories Floor 3A SC 3.N2 Final Finishes
-
10/01→10/07
3A
Inspections/QC
Final OH MEPF Inspections
SC3A-N2-F-500 Floor 3A - Final OH MEPF Inspections Floor 3A SC 3.N2 Final Finishes
-
10/01→10/07
3B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC3B-N3-F-310 Floor 3B - Wall Crash Rails/Hand Rails/Corner Guards Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
10/01→10/07
3C
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
SC3C-N1-F-910 Floor 3C - Flooring - SV Flooring + Cove Base` (FL-1) Floor 3C SC 3.N1 Final Finishes
-
Thu 10/01
4
Data
Floor 4 N4501 - Install I. T. Rooms Doors
TEL-4-470 Floor 4 N4501 - Install I. T. Rooms Doors Telecom Room Lv-4 N4501
-
10/01→10/07
4
Data
Floor 4 N4503 - Pull LV Riser Cable
TEL-4-220 Floor 4 N4503 - Pull LV Riser Cable Telecom Room Lv-4 N4503
-
10/01→10/07
4A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC4A-N2-F-390 Floor 4A - Wall Crash Rails/Hand Rails/Corner Guards Floor 4A SC 4.N2 Final Finishes
-
10/01→10/12
5C
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC5A-N2-F980 Floor 5C- Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 5C SC 5.N1 Final Finishes
-
10/01→10/07
5C
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC5C-N1-F-270 Floor 5C - Install Special Wall Finishes (incl. Wall Protection) Floor 5C SC 5.N1 Final Finishes
-
10/02→10/07
13
Electrical
N13505 - Install Grounding Buss
TEL-13-170 Floor 13 - N13505 - Install Grounding Buss Telecom Room Lv-13 N13505
-
10/02→10/05
1A
Electrical
In-Wall Inspections - Electrical
SC1A-N2-IR-150 Floor 1A - In-Wall Inspections - Electrical Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/02→10/08
2A
Other
Construction Clean
SC2A-N2-F-520 Floor 2A - Construction Clean Floor 2A SC 2.N2 Final Finishes
-
10/02→10/08
2B
Electrical
Electrical Wall Fixtures/Devices
SC2B-N3-F-450 Floor 2B - Electrical Wall Fixtures/Devices Floor 2B SC 2.N3
-
10/02→10/15
2B
Plumbing
Plumbing Fixtures
SC2B-N3-F-440 Floor 2B - Plumbing Fixtures Floor 2B SC 2.N3
-
10/02→10/29
2B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC2B-N3-F-310 Floor 2B - Wall Crash Rails/Hand Rails/Corner Guards Floor 2B SC 2.N3
-
10/02→10/08
2C
Inspections/QC
Final OH MEPF Inspections
SC2C-N1-F-490 Floor 2C - Final OH MEPF Inspections Floor 2C SC 2.N1 Final Finishes
-
10/02→10/22
4
Inspections/QC
Floor 4 N4501 - Terminate & Test IT Systems Cabling
TEL-4-490 Floor 4 N4501 - Terminate & Test IT Systems Cabling Telecom Room Lv-4 N4501
-
10/02→10/12
4B
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC4B-N3-F-220 Floor 4B - Ceramic Tile / Grout - Bathrooms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/02→10/08
5B
Inspections/QC
OH Gilbane QC
SC5B-N3-IR-290 Floor 5B - OH Gilbane QC Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
10/05→10/07
13
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
13EXT-210 Floor 13 - Apply Fluid Applied Roofing on Eyebrow 13th Floor
-
10/06→10/26
12
Electrical
Floor 12 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1530 Floor 12 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 12 Go Back Work - Pads North
-
10/06→10/19
1A
Drywall/Framing
Blocking/Backing/Plywood
SC1A-N2-IR-220 Floor 1A - Blocking/Backing/Plywood Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/06→10/19
3A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC3A-N2-F-320 Floor 3A - Building Specialties (incl. Curtain Track) Floor 3A SC 3.N2 Final Finishes
-
10/06→10/19
3C
Flooring/Finishes
Doors & Hardware
SC3C-N1-F-380 Floor 3C - Doors & Hardware Floor 3C SC 3.N1 Final Finishes
-
10/06→10/08
4B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC4B-N3-F-340 Floor 4B - Drop Borders & Trade Cuts Ceiling Tiles Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/06→10/26
4B
Electrical
Light Fixtures in Grid
SC4B-N3-F-330 Floor 4B - Light Fixtures in Grid Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/06→10/08
4B
Electrical
Remove Temp Light Fixtures
SC4B-N3-F-320 Floor 4B - Remove Temp Light Fixtures Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/06→11/09
5B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Soffits
SC5B-N3-F-170 Floor 5B - Batt Insulation & Hang Drywall Bottom - Walls, Soffits Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
10/07→10/16
·
Ceilings
Bridge - Rough-in Soffits on Level 2 & 3
BRIDGE-390 Bridge - Rough-in Soffits on Level 2 & 3 New Bridge
-
10/07→10/13
·
Other
Elevator 1-2 - Install Sills & Entrances
ELV-420 Elevator 1-2 - Install Sills & Entrances Elevator 1-2
-
10/07→10/09
10
Other
Floor 10 South - Set Pods
GBW-1100 Floor 10 South - Set Pods Floor 10 Testing/Commissioning/Life Safety
-
10/07→10/13
11
HVAC/Mechanical
AHU Drops/Duct Connections 11th N11503
11-M-120 AHU Drops/Duct Connections 11th N11503 Floor 11 Mechanical Space N11503
-
10/07→10/20
11
Drywall/Framing
Floor 11 South - Layout, Frame & Insulate Walls
GBW-1240 Floor 11 South - Layout, Frame & Insulate Walls Floor 11 Testing/Commissioning/Life Safety
-
10/07→10/08
1A
Inspections/QC
OH Gilbane QC
SC1A-N2-IR-240 Floor 1A - OH Gilbane QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/07→11/03
1A
Electrical
Pull Branch Circuits
SC1A-N2-IR-210 Floor 1A - Pull Branch Circuits Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/07→10/27
1A
Data
Pull Wire For All Low Voltage Systems
SC1A-N2-IR-125 Floor 1A - Pull Wire For All Low Voltage Systems Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/07→11/03
1B
Concrete/Structure
EFIS Finish
SC1B-N1-IR-300 Floor 1B - EFIS Finish Floor 1B SC 1.N2 Overhead & Finishes
-
10/07→10/08
9B
Ceilings
MEPF Inspections in Soffits
9B-F-N2-1050 Floor 9B - MEPF Inspections in Soffits West 9B West Overhead Roughs
-
10/08→10/28
11A
Data
OH Low Voltage Pipe Rough-In
11A-IR-N1-1000 Floor 11A - OH Low Voltage Pipe Rough-In Floor 11A East Overhead Roughs
-
10/08→10/09
3A
Ceilings
Install Balance of Ceiling Tile
SC3A-N2-F-510 Floor 3A - Install Balance of Ceiling Tile Floor 3A SC 3.N2 Final Finishes
-
10/08→10/28
3B
Flooring/Finishes
Soft Flooring
SC3B-N3-F-300 Floor 3B - Soft Flooring Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
10/08→10/14
3C
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
SC3C-N1-F-920 Floor 3C - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 3C SC 3.N1 Final Finishes
-
Thu 10/08
4
Data
Floor 4 N4503 - Install I. T. Rooms Doors
TEL-4-230 Floor 4 N4503 - Install I. T. Rooms Doors Telecom Room Lv-4 N4503
-
10/08→10/14
4A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC4A-N1-F-940 Floor 4A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 4A SC 4.N2 Final Finishes
-
10/08→10/14
4B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC4B-N3-F-270 Floor 4B - Install Special Wall Finishes (incl. Wall Protection) Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/08→10/14
4B
Fire/Sprinkler
Sprinkler Drops/Heads
SC4B-N3-F-370 Floor 4B - Sprinkler Drops/Heads Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/08→10/14
4C
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC4C-N1-F-260 Floor 4C - Wall Crash Rails/Hand Rails/Corner Guards Floor 4C SC 4.N1 Final Finishes
-
10/08→10/14
5
Data
Floor 5 N5503 - Pull LV Riser Cable
TEL-5-220 Floor 5 N5503 - Pull LV Riser Cable Telecom Room Lv-5 N5503
-
10/09→10/15
13
Data
N13505 - Install Racks & Ladder Tray
TEL-13-190 Floor 13 - N13505 - Install Racks & Ladder Tray Telecom Room Lv-13 N13505
-
10/09→10/22
13A
Electrical
N13503 - Install & Electronically Connect VFD's
13-M-260 Floor 13A - N13503 - Install & Electronically Connect VFD's Floor 13 A Mechanical Space N13503
-
10/09→10/12
1A
Electrical
OH Inspections - Electrical
SC1A-N2-IR-260 Floor 1A - OH Inspections - Electrical Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/09→10/12
1A
HVAC/Mechanical
OH Inspections - Mechanical
SC1A-N2-IR-270 Floor 1A - OH Inspections - Mechanical Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/09→10/12
1A
Plumbing
OH Inspections - Plumbing
SC1A-N2-IR-230 Floor 1A - OH Inspections - Plumbing Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/09→10/12
1A
Fire/Sprinkler
OH Sprinkler Inspection
SC1A-N2-IR-320 Floor 1A - OH Sprinkler Inspection Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/09→10/22
2A
Inspections/QC
Load Equipment
SC2A-N2-F-560 Floor 2A - Load Equipment Floor 2A SC 2.N2 Final Finishes
-
10/09→10/20
2C
Ceilings
Install Balance of Ceiling Tile
SC2C-N1-F-500 Floor 2C - Install Balance of Ceiling Tile Floor 2C SC 2.N1 Final Finishes
-
10/09→10/12
3
Data
N3504 - Clean I. T. Room
TEL-3-440 Floor 3 - N3504 - Clean I. T. Room Telecom Room Lv-3 N3204
-
Fri 10/09
4
Inspections/QC
Floor 4 N4503 - Terminate & Test IT Systems Cabling
TEL-4-250 Floor 4 N4503 - Terminate & Test IT Systems Cabling Telecom Room Lv-4 N4503
-
10/09→10/29
4B
Data
All Low Voltage Devices
SC4B-N3-F-390 Floor 4B - All Low Voltage Devices Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/09→10/12
5B
Inspections/QC
OH Inspections - MEPF
SC5B-N3-IR-460 Floor 5B - OH Inspections - MEPF Floor 5B SC 5.N3 (7 OR's) Overhead Roughs
-
10/09→10/15
6
Flooring/Finishes
Signage
FL6-1290 6th Floor - Signage Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
10/09→11/05
9B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
9B-F-N2-1060 Floor 9B - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits West 9B West Final Finishes
-
10/12→10/23
10
Other
Floor 10 South - In Wall MEPF Rough In
GBW-1120 Floor 10 South - In Wall MEPF Rough In Floor 10 Testing/Commissioning/Life Safety
-
10/12→11/06
10
Other
Floor 10 South - OH MEPF Rougth In
GBW-1110 Floor 10 South - OH MEPF Rougth In Floor 10 Testing/Commissioning/Life Safety
-
10/12→10/13
10A
Inspections/QC
In-Wall Inspections - MEPF
10A-IR-N1-1071 Floor 10A - In-Wall Inspections - MEPF Floor 10A East Framing & Interior Roughs
-
10/12→10/13
4
Data
Floor 4 N4503 - Clean I. T. Room
TEL-4-270 Floor 4 N4503 - Clean I. T. Room Telecom Room Lv-4 N4503
-
10/13→11/09
1A
Drywall/Framing
Framing Soffits & Ceilings
SC1A-N2-IR-330 Floor 1A - Framing Soffits & Ceilings Floor 1A SC 1.N1 Framing & Interior Roughs
-
10/13→11/09
5B
Drywall/Framing
Hang/Tape/Finish Drywall OR Ceilings
SC5B-N3-F-810 Floor 5B - Hang/Tape/Finish Drywall OR Ceilings Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
10/13→10/19
5C
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC5A-N2-F990 Floor 5C - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 5C SC 5.N1 Final Finishes
-
10/13→10/26
8
Inspections/QC
Owner/Design Team Punch List
P8-1030 Floor 8 - Owner/Design Team Punch List Floor 8 Clean & Punch-Out
-
10/14→10/15
·
HVAC/Mechanical
CT R10 - Install Duct Insulation
REV10-1590 CT R10 - Install Duct Insulation CT Overhead Roughst - Rev. 10
-
10/14→10/21
·
HVAC/Mechanical
CT R10 - Install O.H. Ductwork
REV10-1600 CT R10 - Install O.H. Ductwork CT Overhead Roughst - Rev. 10
-
10/14→10/27
·
Other
Elevator 1-2 - Finish Hoistway Elect, Cab & Call Stations
ELV-440 Elevator 1-2 - Finish Hoistway Elect, Cab & Call Stations Elevator 1-2
-
10/14→10/20
·
Fire/Sprinkler
Level 12 - Perimeter Firestopping
FSP-1100 Level 12 - Perimeter Firestopping Firestopping
-
10/14→10/27
·
Other
Level 13 - Backwelding (Low Roof)
BW-1120 Level 13 - Backwelding (Low Roof) Detailing (Back Welding)
-
10/14→11/03
10A
Drywall/Framing
Blocking/Backing/Plywood
10A-IR-N1-1090 Floor 10A - Blocking/Backing/Plywood Floor 10A East Framing & Interior Roughs
-
10/14→10/23
10A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
10A-F-N1-1011 Floor 10A - HVAC Drops & Diffusers in Soffit Floor 10A East Overhead Roughs
-
10/14→11/03
10A
Electrical
RI Light Fixtures Hard Ceilings & Soffits
10A-F-N1-1022 Floor 10A - RI Light Fixtures Hard Ceilings & Soffits Floor 10A East Overhead Roughs
-
10/14→10/22
11
HVAC/Mechanical
BMS Controls AHU N11503
11-M-130 BMS Controls AHU N11503 Floor 11 Mechanical Space N11503
-
10/14→10/27
9A
Flooring/Finishes
Paint Prime & First Coat
9A-F-N1-1090 Floor 9A - Paint Prime & First Coat Floor 9A East Final Finishes 9A
-
10/15→10/16
2C
Flooring/Finishes
Signage
SC2C-N1-F-460 Floor 2C - Signage Floor 2C SC 2.N1 Final Finishes
-
10/15→10/16
3
Data
N3504 - Clean I. T. Room
TEL-3-290 Floor 3 - N3504 - Clean I. T. Room Telecom Room Lv-3 N3504
-
10/15→10/26
3C
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
SC3C-N1-F-930 Floor 3C - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 3C SC 3.N1 Final Finishes
-
10/15→10/21
4B
Inspections/QC
AHCA 80% Inspection
SC4B-N3-F-350 Floor 4B - AHCA 80% Inspection Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
10/15→10/21
5
Data
Floor 5 N5501 - Pull LV Riser Cable
TEL-5-410 Floor 5 N5501 - Pull LV Riser Cable Telecom Room Lv-5 N5501
-
Thu 10/15
5
Data
Floor 5 N5503 - Install I. T. Rooms Doors
TEL-5-230 Floor 5 N5503 - Install I. T. Rooms Doors Telecom Room Lv-5 N5503
-
10/15→10/21
5A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC5A-N2-F-390 Floor 5A - Wall Crash Rails/Hand Rails/Corner Guards Floor 5A SC 5.N2 Final Finishes
-
10/16→10/20
1
Concrete/Structure
Apply Fluid Applied Roofing on Eyebrow
1EXT-210 Floor 01 - Apply Fluid Applied Roofing on Eyebrow 1st Floor
-
10/16→10/29
2B
Other
Div 10 Accessories
SC2B-N3-F-470 Floor 2B - Div 10 Accessories Floor 2B SC 2.N3
-
10/16→10/22
2B
Inspections/QC
Final OH MEPF Inspections
SC2B-N3-F-480 Floor 2B - Final OH MEPF Inspections Floor 2B SC 2.N3
-
10/16→10/19
4
Data
Floor 4 N4504 - Clean I. T. Room
TEL-4-290 Floor 4 N4504 - Clean I. T. Room Telecom Room Lv-4 N4504
-
10/19→10/30
·
Drywall/Framing
Bridge - Hang & Finish Drywall
BRIDGE-400 Bridge - Hang & Finish Drywall New Bridge
-
10/19→11/16
11A
Plumbing
OH & In Wall MED Gas Rough In & QC
11A-IR-N1-1101 Floor 11A - OH & In Wall MED Gas Rough In & QC Floor 11A East Overhead Roughs
-
10/20→10/26
3A
Flooring/Finishes
Final Paint & Wallcovering
SC3A-N2-F-380 Floor 3A - Final Paint & Wallcovering Floor 3A SC 3.N2 Final Finishes
-
10/20→10/26
3C
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC3C-N1-F-360 Floor 3C - Building Specialties (incl. Curtain Track) Floor 3C SC 3.N1 Final Finishes
-
10/20→10/29
3C
Plumbing
Plumbing Fixtures
SC3C-N1-F-320 Floor 3C - Plumbing Fixtures Floor 3C SC 3.N1 Final Finishes
-
10/20→11/02
4A
Flooring/Finishes
Doors & Hardware
SC4A-N2-F-430 Floor 4A - Doors & Hardware Floor 4A SC 4.N2 Final Finishes
-
10/21→10/27
·
Fire/Sprinkler
Level 1 - Perimeter Firestopping
FSP-1110 Level 1 - Perimeter Firestopping Firestopping
-
10/21→10/23
11
Other
Floor 11 South - Set Bathroom Pods
GBW-1250 Floor 11 South - Set Bathroom Pods Floor 11 Testing/Commissioning/Life Safety
-
10/21→10/22
11A
Inspections/QC
In-Wall Inspections - MEPF
11A-IR-N1-1080 Floor 11A - In-Wall Inspections - MEPF Floor 11A East Framing & Interior Roughs
-
10/21→11/18
12A
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
12A-IR-N1-1080 Floor 12A - OH Duct/VAV Boxes Rough-In/Insulation Floor 12 A East Overhead Roughs
-
10/21→11/03
13
Drywall/Framing
Floor 13 North - Hang Drywall & Finish Drywall
GBW-1630 Floor 13 North - Hang Drywall & Finish Drywall Floor 13 Go Back Work - Pads North
-
10/21→10/27
2C
Other
Construction Clean
SC2C-N1-F-510 Floor 2C - Construction Clean Floor 2C SC 2.N1 Final Finishes
-
10/21→10/22
5C
Ceilings
Ceiling Grid QC
SC5C-N1-F-470 Floor 5C - Ceiling Grid QC Floor 5C SC 5.N1 Final Finishes
-
Thu 10/22
·
Inspections/QC
CT R10 - Overhead MEP Inspections
REV10-1610 CT R10 - Overhead MEP Inspections CT Overhead Roughst - Rev. 10
-
Thu 10/22
5
Data
Floor 5 N5501 - Install I. T. Rooms Doors
TEL-5-470 Floor 5 N5501 - Install I. T. Rooms Doors Telecom Room Lv-5 N5501
-
10/22→10/28
5
Data
Floor 5 N5504 - Pull LV Riser Cable
TEL-5-240 Floor 5 N5504 - Pull LV Riser Cable Telecom Room Lv-5 N5504
-
10/22→10/28
5C
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC5C-N1-F-260 Floor 5C - Wall Crash Rails/Hand Rails/Corner Guards Floor 5C SC 5.N1 Final Finishes
-
Fri 10/23
·
Drywall/Framing
CT R10 - Install Door Frames
REV10-1620 CT R10 - Install Door Frames CT Interior Roughs - Rev. 10
-
10/23→11/02
·
Concrete/Structure
Install Precast Panels Levels 12-Roof (Set 14 WS)
SW-830 Install Precast Panels Levels 12-Roof (Set 14 WS) Precast
-
10/23→10/28
·
Inspections/QC
Install Punch Windows - Set 13
EXG-1110 Install Punch Windows - Set 13 Exterior Glass & Glazing South Elevation (Punch Windows)
-
10/23→11/05
11A
Drywall/Framing
Blocking/Backing/Plywood
11A-IR-N1-1090 Floor 11A - Blocking/Backing/Plywood Floor 11A East Framing & Interior Roughs
-
10/23→11/13
2A
Other
Set & Connect Owner Provided Equipment
SC2A-N2-F-580 Floor 2A - Set & Connect Owner Provided Equipment Floor 2A SC 2.N2 Final Finishes
-
10/23→10/29
2A
Inspections/QC
Stocking
SC2A-N2-F-540 Floor 2A - Stocking Floor 2A SC 2.N2 Final Finishes
-
10/23→11/03
2B
Ceilings
Install Balance of Ceiling Tile
SC2B-N3-F-490 Floor 2B - Install Balance of Ceiling Tile Floor 2B SC 2.N3
-
10/23→10/26
4
Data
Floor 4 N4501 - Clean I. T. Room
TEL-4-500 Floor 4 N4501 - Clean I. T. Room Telecom Room Lv-4 N4501
-
10/26→10/28
·
Drywall/Framing
CT R10 - Frame Soffits/Hard Ceilings
REV10-1630 CT R10 - Frame Soffits/Hard Ceilings CT Interior Roughs - Rev. 10
-
10/26→11/06
11
Other
Floor 11 South - In Wall MEPF Rough In
GBW-1270 Floor 11 South - In Wall MEPF Rough In Floor 11 Testing/Commissioning/Life Safety
-
10/26→11/06
9
Drywall/Framing
Floor 9 South - Hang Drywall & Finish Drywall
GBW-970 Floor 9 South - Hang Drywall & Finish Drywall Floor 9 Testing/Commissioning/Life Safety
-
10/27→10/28
3A
Flooring/Finishes
Signage
SC3A-N2-F-470 Floor 3A - Signage Floor 3A SC 3.N2 Final Finishes
-
10/27→10/28
3C
Plumbing
Common Area Plumbing Trim Out
SC3C-N1-F-290 Floor 3C - Common Area Plumbing Trim Out Floor 3C SC 3.N1 Final Finishes
-
10/27→11/02
3C
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
SC3C-N1-F-940 Floor 3C - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 3C SC 3.N1 Final Finishes
-
10/28→11/03
·
Other
Elevator 1-2 - Install Cab Finishes
ELV-460 Elevator 1-2 - Install Cab Finishes Elevator 1-2
-
10/28→11/10
2C
Inspections/QC
Load Equipment
SC2C-N1-F-520 Floor 2C - Load Equipment Floor 2C SC 2.N1 Final Finishes
-
10/28→11/03
9A
Ceilings
Install Ceiling Grid
9A-F-N1-1100 Floor 9A - Install Ceiling Grid Floor 9A East Final Finishes 9A
-
10/29→11/04
·
Electrical
CT R10 - Electrical Soffits/Hard Ceilings Rough In
REV10-1640 CT R10 - Electrical Soffits/Hard Ceilings Rough In CT Interior Roughs - Rev. 10
-
10/29→11/04
·
HVAC/Mechanical
CT R10 - Mechanical Soffits/Hard Ceilings Rough In
REV10-1650 CT R10 - Mechanical Soffits/Hard Ceilings Rough In CT Interior Roughs - Rev. 10
-
10/29→11/30
11A
Data
Pull Wire For All Low Voltage Systems
11A-IR-N1-1071 Floor 11A - Pull Wire For All Low Voltage Systems Floor 11A East Overhead Roughs
-
10/29→11/04
3A
Other
Construction Cleaning
SC3A-N2-F-520 Floor 3A - Construction Cleaning Floor 3A SC 3.N2 Final Finishes
-
10/29→11/09
3B
Flooring/Finishes
Doors & Hardware
SC3B-N3-F-390 Floor 3B - Doors & Hardware Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
10/29→11/04
4B
Flooring/Finishes
Soft Flooring & Base
SC4B-N3-F-300 Floor 4B - Soft Flooring & Base Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
Thu 10/29
5
Data
Floor 5 N5504 - Install I. T. Rooms Doors
TEL-5-260 Floor 5 N5504 - Install I. T. Rooms Doors Telecom Room Lv-5 N5504
-
10/29→11/04
6
Data
Floor 6 N6501 - Pull LV Riser Cable
TEL-6-220 Floor 6 N6501 - Pull LV Riser Cable Telecom Room Lv-6 N6501
-
10/29→11/09
9B
Fire/Sprinkler
Fire Stopping/Labeling
9B-F-N2-1070 Floor 9B - Fire Stopping/Labeling West 9B West Final Finishes
-
10/30→11/03
3C
Other
Div 10 Accessories
SC3C-N1-F-470 Floor 3C - Div 10 Accessories Floor 3C SC 3.N1 Final Finishes
-
10/30→11/05
3C
Inspections/QC
Final OH MEPF Inspections
SC3C-N1-F-480 Floor 3C - Final OH MEPF Inspections Floor 3C SC 3.N1 Final Finishes
-
10/30→11/05
3C
Flooring/Finishes
Set Lockers
SC3C-N1-F-460 Floor 3C - Set Lockers Floor 3C SC 3.N1 Final Finishes
-
10/30→11/02
4B
Ceilings
Ceiling Grid QC
SC4B-N3-F-400 Floor 4B - Ceiling Grid QC Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
11/02→11/12
·
Flooring/Finishes
Bridge - Prime & 1st Coat of Finish Paint
BRIDGE-410 Bridge - Prime & 1st Coat of Finish Paint New Bridge
-
11/02→11/23
12A
HVAC/Mechanical
OH HVAC Controls& QC
12A-IR-N1-1150 Floor 12A - OH HVAC Controls& QC Floor 12 A East Overhead Roughs
-
11/03→11/12
·
Concrete/Structure
Install Precast Panels Levels 12-Roof (Set 15 WS)
W-840 Install Precast Panels Levels 12-Roof (Set 15 WS) Precast
-
11/03→11/06
·
Inspections/QC
Install Punch Windows - Set 14
EXG-1120 Install Punch Windows - Set 14 Exterior Glass & Glazing South Elevation (Punch Windows)
-
11/03→11/17
12
Drywall/Framing
Floor 12 South - Layout, Frame & Insulate Walls
GBW-1390 Floor 12 South - Layout, Frame & Insulate Walls Floor 12 Testing/Commissioning/Life Safety
-
11/03→11/06
4A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC4A-N2-F-420 Floor 4A - Building Specialties (incl. Curtain Track) Floor 4A SC 4.N2 Final Finishes
-
11/03→11/17
4A
Plumbing
Plumbing Fixtures
SC4A-N2-F-460 Floor 4A - Plumbing Fixtures Floor 4A SC 4.N2 Final Finishes
-
11/03→11/05
4C
Flooring/Finishes
Doors & Hardware
SC4C-N1-F-330 Floor 4C - Doors & Hardware Floor 4C SC 4.N1 Final Finishes
-
11/04→11/10
·
Concrete/Structure
Elevator 1-2 - Complete CMU at Shafts
ELV-430 Elevator 1-2 - Complete CMU at Shafts Elevator 1-2
-
11/04→11/05
10A
Drywall/Framing
Framing Inspections
10A-F-N1-1033 Floor 10A - Framing Inspections Floor 10A East Framing & Interior Roughs
-
11/04→11/05
10A
Ceilings
MEPF Inspections in Soffits
10A-F-N1-1053 Floor 10A - MEPF Inspections in Soffits Floor 10A East Overhead Roughs
-
11/04→11/10
13
Flooring/Finishes
Floor 13 North - Prime & 1st Coat
GBW-1640 Floor 13 North - Prime & 1st Coat Floor 13 Go Back Work - Pads North
-
11/04→11/18
1B
Electrical
Electrical, Security, FA, Data Trim
SC1B-N1-IR-310 Floor 1B - Electrical, Security, FA, Data Trim Floor 1B SC 1.N2 Overhead & Finishes
-
11/04→11/10
1B
Fire/Sprinkler
Sprinkler Trim
SC1B-N1-IR-320 Floor 1B - Sprinkler Trim Floor 1B SC 1.N2 Overhead & Finishes
-
11/04→11/10
2B
Other
Construction Clean
SC2B-N3-F-500 Floor 2B - Construction Clean Floor 2B SC 2.N3
-
11/04→11/18
2B
Flooring/Finishes
Final Paint
SC2B-N3-F-410 Floor 2B - Final Paint Floor 2B SC 2.N3
-
11/04→11/12
9A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
9A-F-N1-1130 Floor 9A - Drop Borders & Trade Cuts Ceiling Tiles Floor 9A East Final Finishes 9A
-
11/04→11/10
9A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
9A-F-N1-1110 Floor 9A - HVAC Drops & Diffusers/Grid Floor 9A East Final Finishes 9A
-
11/04→11/16
9A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
9A-F-N1-1150 Floor 9A - Install Special Wall Finishes (incl. Wall Protection) Floor 9A East Final Finishes 9A
-
11/04→11/25
9A
Electrical
Light Fixtures in Grid
9A-F-N1-1140 Floor 9A - Light Fixtures in Grid Floor 9A East Final Finishes 9A
-
11/04→11/18
9A
Electrical
Remove Temp Light Fixtures
9A-F-N1-1330 Floor 9A - Remove Temp Light Fixtures Floor 9A East Final Finishes 9A
-
Thu 11/05
·
Ceilings
CT R10 - Soffit/Hard Ceilings MEP Inspections
REV10-1660 CT R10 - Soffit/Hard Ceilings MEP Inspections CT Interior Roughs - Rev. 10
-
11/05→11/19
3A
Inspections/QC
Load Equipment
SC3A-N2-F-530 Floor 3A - Load Equipment Floor 3A SC 3.N2 Final Finishes
-
11/05→11/12
4B
Flooring/Finishes
Casework/Countertops
SC4B-N3-F-240 Floor 4B - Casework/Countertops Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
11/05→11/12
4B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC4B-N3-F-310 Floor 4B - Wall Crash Rails/Hand Rails/Corner Guards Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
Thu 11/05
6
Data
Floor 6 N6501 - Install I. T. Rooms Doors
TEL-6-230 Floor 6 N6501 - Install I. T. Rooms Doors Telecom Room Lv-6 N6501
-
11/05→11/12
6
Data
Floor 6 N6509 - Pull LV Riser Cable
TEL-6-240 Floor 6 N6509 - Pull LV Riser Cable Telecom Room Lv-6 N6509
-
11/05→11/12
9
Other
Floor 9 South - Set Equipment
GBW-980 Floor 9 South - Set Equipment Floor 9 Testing/Commissioning/Life Safety
-
Fri 11/06
·
Other
CT R10 - Install Controls
REV10-1670 CT R10 - Install Controls CT Interior Roughs - Rev. 10
-
11/06→12/01
10A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
10A-F-N1-1061 Floor 10A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 10A East Final Finishes
-
11/06→11/13
11
HVAC/Mechanical
AHU Drops/Piping Connections AHU N11503
11-M-110 AHU Drops/Piping Connections AHU N11503 Floor 11 Mechanical Space N11503
-
11/06→12/01
12A
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
12A-IR-N1-2000 Floor 12A - OH HVAC Piping/Controls/Insulation & QC Floor 12 A East Overhead Roughs
-
11/06→11/13
3C
Flooring/Finishes
Final Paint & Wallcovering
SC3C-N1-F-430 Floor 3C - Final Paint & Wallcovering Floor 3C SC 3.N1 Final Finishes
-
11/06→11/13
3C
Ceilings
Install Balance of Ceiling Tile
SC3C-N1-F-500 Floor 3C - Install Balance of Ceiling Tile Floor 3C SC 3.N1 Final Finishes
-
11/06→11/20
5A
Flooring/Finishes
Doors & Hardware
SC5A-N2-F-430 Floor 5A - Doors & Hardware Floor 5A SC 5.N2 Final Finishes
-
11/06→12/01
6
Inspections/QC
Floor 6 N6501 - Terminate & Test IT Systems Cabling
TEL-6-250 Floor 6 N6501 - Terminate & Test IT Systems Cabling Telecom Room Lv-6 N6501
-
11/06→12/08
9B
Drywall/Framing
Finish Drywall
9B-F-N2-1080 Floor 9B - Finish Drywall West 9B West Final Finishes
-
11/09→11/16
·
Plumbing
CT R10 - In-Wall Plumbing/Med Gas
REV10-1680 CT R10 - In-Wall Plumbing/Med Gas CT Interior Roughs - Rev. 10
-
11/09→11/23
10
Drywall/Framing
Floor 10 South - Hang Drywall & Finish Drywall
GBW-1130 Floor 10 South - Hang Drywall & Finish Drywall Floor 10 Testing/Commissioning/Life Safety
-
11/09→12/09
11
Other
Floor 11 South - OH MEPF Rougth In
GBW-1260 Floor 11 South - OH MEPF Rougth In Floor 11 Testing/Commissioning/Life Safety
-
11/09→11/13
4C
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC4C-N1-F-320 Floor 4C - Building Specialties (incl. Curtain Track) Floor 4C SC 4.N1 Final Finishes
-
11/10→11/20
10A
Fire/Sprinkler
Fire Stopping/Labeling
10A-F-N1-1040 Floor 10A - Fire Stopping/Labeling Floor 10A East Final Finishes
-
11/10→12/10
12A
Plumbing
OH Plumbing Rough In/Insulation & QC
12A-IR-N1-1110 Floor 12A - OH Plumbing Rough In/Insulation & QC Floor 12 A East Overhead Roughs
-
11/10→11/12
1A
Ceilings
Soffits & Ceilings Gilbane QC
SC1A-N2-IR-115 Floor 1A - Soffits & Ceilings Gilbane QC Floor 1A SC 1.N1 Framing & Interior Roughs
-
11/10→11/17
3B
Flooring/Finishes
Base
SC3B-N3-F-420 Floor 3B - Base Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
11/10→11/16
3B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC3B-N3-F-370 Floor 3B - Building Specialties (incl. Curtain Track) Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
11/10→11/13
4B
Flooring/Finishes
Doors & Hardware
SC4B-N3-F-380 Floor 4B - Doors & Hardware Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
11/10→12/10
5B
Drywall/Framing
Finish Drywall
SC5B-N3-F-190 Floor 5B - Finish Drywall Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
11/10→11/17
5B
Fire/Sprinkler
Fire Stopping/Labeling
SC5B-N3-F-180 Floor 5B - Fire Stopping/Labeling Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
11/10→11/16
5B
Flooring/Finishes
Moisture Mitigation for Floor Tile
SC5B-N3-F-200 Floor 5B - Moisture Mitigation for Floor Tile Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
11/12→11/18
·
Other
Elevator 1-2 - Finishing Cab Finished Elevator 1-2
ELV-470 Elevator 1-2 - Finishing Cab Finished Elevator 1-2 Elevator 1-2
-
11/12→11/25
12A
Fire/Sprinkler
OH Sprinkler Rough In& QC
12A-IR-N1-1140 Floor 12A - OH Sprinkler Rough In& QC Floor 12 A East Overhead Roughs
-
11/12→12/04
13
Electrical
Floor 13 North - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1650 Floor 13 North - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 13 Go Back Work - Pads North
-
11/12→11/25
2B
Inspections/QC
Load Equipment
SC2B-N3-F-510 Floor 2B - Load Equipment Floor 2B SC 2.N3
-
11/12→11/18
2C
Inspections/QC
Stocking
SC2C-N1-F-540 Floor 2C - Stocking Floor 2C SC 2.N1 Final Finishes
-
11/12→11/16
9
Other
Temporary Cooling Floor 9
TEMP-9 Temporary Cooling Floor 9 Temporary Cooling
-
11/12→11/18
9A
Fire/Sprinkler
Sprinkler Drops/Heads
9A-F-N1-1160 Floor 9A - Sprinkler Drops/Heads Floor 9A East Final Finishes 9A
-
11/13→11/20
·
Ceilings
Bridge - Install Ceiling Grid on Level 2 & 3
BRIDGE-420 Bridge - Install Ceiling Grid on Level 2 & 3 New Bridge
-
11/13→11/18
·
Inspections/QC
Install Punch Windows - Set 15
EXG-1130 Install Punch Windows - Set 15 Exterior Glass & Glazing South Elevation (Punch Windows)
-
11/13→11/30
·
Other
Level 13 - Backwelding (13-Roof)
BW-1130 Level 13 - Backwelding (13-Roof) Detailing (Back Welding)
-
11/13→11/19
1A
Drywall/Framing
Wall & Ceilings Framing Inspections
SC1A-N-2IR-131 Floor 1A - Wall & Ceilings Framing Inspections Floor 1A SC 1.N1 Framing & Interior Roughs
-
Fri 11/13
6
Data
Floor 6 N6509 - Install I. T. Rooms Doors
TEL-6-260 Floor 6 N6509 - Install I. T. Rooms Doors Telecom Room Lv-6 N6509
-
11/13→11/19
7
Data
Floor 7 N7501 - Pull LV Riser Cable
TEL-7-240 Floor 7 N7501 - Pull LV Riser Cable Telecom Room Lv-7 N7501
-
11/13→11/19
9
Flooring/Finishes
Floor 9 South - Prime & 1st Coat
GBW-990 Floor 9 South - Prime & 1st Coat Floor 9 Testing/Commissioning/Life Safety
-
11/13→12/07
9A
Data
All Low Voltage Devices In Grid
9A-F-N1-1115 Floor 9A - All Low Voltage Devices In Grid Floor 9A East Final Finishes 9A
-
11/16→12/01
11
Electrical
Install & Electronically Connect VFD's N11503
11-M-150 Install & Electronically Connect VFD's N11503 Floor 11 Mechanical Space N11503
-
11/16→11/18
2A
Other
Final Clean
SC2A-N2-F-570 Floor 2A - Final Clean Floor 2A SC 2.N2 Final Finishes
-
11/16→11/20
3C
Flooring/Finishes
Signage
SC3C-N1-F-490 Floor 3C - Signage Floor 3C SC 3.N1 Final Finishes
-
11/16→12/01
5A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC5A-N2-F-420 Floor 5A - Building Specialties (incl. Curtain Track) Floor 5A SC 5.N2 Final Finishes
-
11/17→12/09
·
Electrical
CT R10 - In-Wall Electrical
REV10-1690 CT R10 - In-Wall Electrical CT Interior Roughs - Rev. 10
-
11/17→11/18
11A
Inspections/QC
OH Inspections - MEPF
11A-IR-N1-1190 Floor 11A - OH Inspections - MEPF Floor 11A East Overhead Roughs
-
11/17→11/20
4B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC4B-N3-F-360 Floor 4B - Building Specialties (incl. Curtain Track) Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
11/17→11/18
9A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
9A-F-N1-1355 Floor 9A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 9A East Final Finishes 9A
-
11/18→11/20
12
Other
Floor 12 South - Set Bathroom Pods
GBW-1400 Floor 12 South - Set Bathroom Pods Floor 12 Testing/Commissioning/Life Safety
-
11/18→12/10
12A
Electrical
OH Electrical & I.T. Rough In& QC
12A-IR-N1-1120 Floor 12A - OH Electrical & I.T. Rough In& QC Floor 12 A East Overhead Roughs
-
11/18→12/03
3B
Plumbing
Plumbing Fixtures
SC3B-N3-F-440 Floor 3B - Plumbing Fixtures Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
11/18→11/20
4A
Other
Div 10 Accessories
SC4A-N2-F-500 Floor 4A - Div 10 Accessories Floor 4A SC 4.N2 Final Finishes
-
11/18→11/24
4A
Inspections/QC
Final OH MEPF Inspections
SC4A-N2-F-490 Floor 4A - Final OH MEPF Inspections Floor 4A SC 4.N2 Final Finishes
-
11/18→12/03
4C
Plumbing
Plumbing Fixtures
SC4C-N1-F-290 Floor 4C - Plumbing Fixtures Floor 4C SC 4.N1 Final Finishes
-
11/19→11/25
·
Other
Elevator 1-2 - Adjust & Inspect Elevator 1-2
ELV-450 Elevator 1-2 - Adjust & Inspect Elevator 1-2 Elevator 1-2
-
11/19→12/02
·
Concrete/Structure
Install Exterior Louvers West
ELW-300 Install Exterior Louvers West Exterior Louvers
-
11/19→12/04
11A
Drywall/Framing
Frame Soffits/Hard Ceilings
11A-IR-N1-1230 Floor 11A - Frame Soffits/Hard Ceilings Floor 11A East Overhead Roughs
-
11/19→12/18
11A
Electrical
Pull Branch Circuits
11A-IR-N1-1240 Floor 11A - Pull Branch Circuits Floor 11A East Overhead Roughs
-
11/19→12/04
1B
Other
Remove Dance Floor
SC1B-N1-IR-330 Floor 1B - Remove Dance Floor Floor 1B SC 1.N2 Overhead & Finishes
-
11/19→11/25
2B
Flooring/Finishes
Signage
SC2B-N3-F-460 Floor 2B - Signage Floor 2B SC 2.N3
-
11/19→11/25
2C
Other
Final Clean
SC2C-N1-F-550 Floor 2C - Final Clean Floor 2C SC 2.N1 Final Finishes
-
11/19→11/25
9A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
9A-F-N1-1180 Floor 9A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 9A East Final Finishes 9A
-
11/20→11/30
10
Other
Floor 10 South Set Equipment
GBW-1140 Floor 10 South Set Equipment Floor 10 Testing/Commissioning/Life Safety
-
11/20→12/14
1A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
SC1A-N2-F-140 Floor 1A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 1A SC 1.N1 Final Finishes
-
11/20→11/30
3A
Inspections/QC
Stocking
SC3A-N2-F-550 Floor 3A - Stocking Floor 3A SC 3.N2 Final Finishes
-
11/20→11/30
7
Inspections/QC
Floor 7 N7501 - Terminate & Test IT Systems Cabling
TEL-7-280 Floor 7 N7501 - Terminate & Test IT Systems Cabling Telecom Room Lv-7 N7501
-
11/20→11/30
7
Data
Floor 7 N7504 - Pull LV Riser Cable
TEL-7-220 Floor 7 N7504 - Pull LV Riser Cable Telecom Room Lv-7 N7504
-
11/20→12/14
9
Electrical
Floor 9 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1000 Floor 9 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 9 Testing/Commissioning/Life Safety
-
11/23→12/08
·
Electrical
Bridge - Mechanical/Electrical/ Fire Protection Trim Out
BRIDGE-430 Bridge - Mechanical/Electrical/ Fire Protection Trim Out New Bridge
-
11/23→12/08
10A
Drywall/Framing
Finish Drywall
10A-F-N1-1081 Floor 10A - Finish Drywall Floor 10A East Final Finishes
-
11/23→12/08
12
Other
Floor 12 South - In Wall MEPF Rough In
GBW-1420 Floor 12 South - In Wall MEPF Rough In Floor 12 Testing/Commissioning/Life Safety
-
11/23→12/22
12
Other
Floor 12 South - OH MEPF Rougth In
GBW-1410 Floor 12 South - OH MEPF Rougth In Floor 12 Testing/Commissioning/Life Safety
-
11/23→12/01
3C
Other
Construction Clean
SC3C-N1-F-510 Floor 3C - Construction Clean Floor 3C SC 3.N1 Final Finishes
-
11/23→12/01
4A
Flooring/Finishes
Final Paint & Wallcovering
SC4A-N2-F-450 Floor 4A - Final Paint & Wallcovering Floor 4A SC 4.N2 Final Finishes
-
11/23→12/01
5C
Flooring/Finishes
Doors & Hardware
SC5C-N1-F-330 Floor 5C - Doors & Hardware Floor 5C SC 5.N1 Final Finishes
-
Wed 11/25
·
Milestone
Install (2) Elevators for Construction Use ◆
M710 Install (2) Elevators for Construction Use Construction Milestones
-
11/25→12/10
12A
Data
OH Low Voltage Pipe Rough-In
12A-IR-N1-1004 Floor 12A - OH Low Voltage Pipe Rough-In Floor 12 A East Overhead Roughs
-
11/25→12/24
12A
Electrical
OH-Electrical Rough/Racks Systems
12A-IR-N1-1030 Floor 12A - OH-Electrical Rough/Racks Systems Floor 12 A East Overhead Roughs
-
11/25→12/17
1A
Drywall/Framing
Finish Drywall
SC1A-N2-F-160 Floor 1A - Finish Drywall Floor 1A SC 1.N1 Final Finishes
-
11/30→12/28
·
Other
Elevator 3-4 - Install Rails
ELV-490 Elevator 3-4 - Install Rails Elevator 3-4
-
11/30→12/28
·
Other
Elevator 5-6 - Install Rails
ELV-580 Elevator 5-6 - Install Rails Elevator 5-6
-
11/30→12/01
2B
Inspections/QC
Owner Pre AHCA For Areas (A, B & C)
SC2B-N3-F-520 Floor 2B - Owner Pre AHCA For Areas (A, B & C) Floor 2B SC 2.N3
-
11/30→12/04
9A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
9A-F-N1-1365 Floor 9A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 9A East Final Finishes 9A
-
12/01→12/07
·
Fire/Sprinkler
Level 13 - Perimeter Firestopping
FSP-1120 Level 13 - Perimeter Firestopping Firestopping
-
12/01→12/14
·
Other
South - Set Up Access Platform System
SWW-100 South - Set Up Access Platform System South Window Washing Support Steel / Equipment
-
12/01→12/07
10
Flooring/Finishes
Floor 10 South - Prime & 1st Coat
GBW-1150 Floor 10 South - Prime & 1st Coat Floor 10 Testing/Commissioning/Life Safety
-
12/01→12/07
3A
Other
Final Cleaning
SC3A-N2-F-560 Floor 3A - Final Cleaning Floor 3A SC 3.N2 Final Finishes
-
12/01→12/02
7
Data
Floor 7 N7501 - Clean I. T. Room
TEL-7-310 Floor 7 N7501 - Clean I. T. Room Telecom Room Lv-7 N7501
-
Tue 12/01
7
Data
Floor 7 N7504 - Install I. T. Rooms Doors
TEL-7-230 Floor 7 N7504 - Install I. T. Rooms Doors Telecom Room Lv-7 N7504
-
12/01→12/07
8
Data
Floor 8 N8503 - Pull LV Riser Cable
TEL-8-220 Floor 8 N8503 - Pull LV Riser Cable Telecom Room Lv-8 N8503
-
Wed 12/02
·
Milestone
Building Weather Tight - All Floors ◆
M300 Building Weather Tight - All Floors Construction Milestones
-
12/02→12/08
2B
Inspections/QC
Stocking
SC2B-N3-F-530 Floor 2B - Stocking Floor 2B SC 2.N3
-
12/02→12/15
3C
Inspections/QC
Load Equipment
SC3C-N1-F-520 Floor 3C - Load Equipment Floor 3C SC 3.N1 Final Finishes
-
12/02→12/15
4A
Electrical
Electrical Wall Fixtures/Devices
SC4A-N2-F-470 Floor 4A - Electrical Wall Fixtures/Devices Floor 4A SC 4.N2 Final Finishes
-
12/02→12/08
4A
Flooring/Finishes
Signage
SC4A-N2-F-480 Floor 4A - Signage Floor 4A SC 4.N2 Final Finishes
-
12/02→12/07
5C
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC5C-N1-F-320 Floor 5C - Building Specialties (incl. Curtain Track) Floor 5C SC 5.N1 Final Finishes
-
12/02→12/03
6
Data
Floor 6 N6501 - Clean I. T. Room
TEL-6-270 Floor 6 N6501 - Clean I. T. Room Telecom Room Lv-6 N6501
-
12/02→12/22
6
Inspections/QC
Floor 6 N6509 - Terminate & Test IT Systems Cabling
TEL-6-280 Floor 6 N6509 - Terminate & Test IT Systems Cabling Telecom Room Lv-6 N6509
-
12/02→12/08
7
Inspections/QC
Floor 7 N7504 - Terminate & Test IT Systems Cabling
TEL-7-250 Floor 7 N7504 - Terminate & Test IT Systems Cabling Telecom Room Lv-7 N7504
-
12/02→12/15
9B
Flooring/Finishes
Paint Prime & First Coat
9B-F-N2-1090 Floor 9B - Paint Prime & First Coat West 9B West Final Finishes
-
12/04→12/08
3B
Other
Div 10 Accessories
SC3B-N3-F-490 Floor 3B - Div 10 Accessories Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/04→12/10
3B
Inspections/QC
Final OH MEPF Inspections
SC3B-N3-F-480 Floor 3B - Final OH MEPF Inspections Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/04→12/24
4
Inspections/QC
CEP Floor 4 - Gilbane Functional/Pre-Inspections
PN-4-4050 CEP Floor 4 - Gilbane Functional/Pre-Inspections CEP 4th Flr Clean & Punch-Out
-
12/04→12/17
4B
Plumbing
Plumbing Fixtures
SC4B-N3-F-440 Floor 4B - Plumbing Fixtures Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
12/04→12/08
4C
Other
Div 10 Accessories
SC4C-N1-F-420 Floor 4C - Div 10 Accessories Floor 4C SC 4.N1 Final Finishes
-
12/04→12/10
4C
Inspections/QC
Final OH MEPF Inspections
SC4C-N1-F-490 Floor 4C - Final OH MEPF Inspections Floor 4C SC 4.N1 Final Finishes
-
12/04→12/10
4C
Flooring/Finishes
Set Lockers
SC4C-N1-F-350 Floor 4C - Set Lockers Floor 4C SC 4.N1 Final Finishes
-
12/04→12/17
5A
Plumbing
Plumbing Fixtures
SC5A-N2-F-460 Floor 5A - Plumbing Fixtures Floor 5A SC 5.N2 Final Finishes
-
12/07→12/18
·
Other
Install PCC East Elevation
EXT-E-3000 Install PCC East Elevation Buck Hoist Infill Exterior Facade & Envelope
-
12/07→12/31
1B
Drywall/Framing
Place & Finish Concrete At Columns For Framing
SC1B-N1-IR-160 Floor 1B - Place & Finish Concrete At Columns For Framing Floor 1B SC 1.N2 Overhead & Finishes
-
12/07→12/16
9A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
9A-F-N1-1200 Floor 9A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 9A East Final Finishes 9A
-
12/08→12/29
10
Electrical
Floor 10 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1160 Floor 10 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 10 Testing/Commissioning/Life Safety
-
12/08→12/21
13
Drywall/Framing
Floor 13 South - Layout, Frame & Insulate Walls
GBW-1540 Floor 13 South - Layout, Frame & Insulate Walls Floor 13 Go Back Work - Pads South
-
12/08→12/14
1A
Fire/Sprinkler
Fire Stopping/Labeling
SC1A-N2-F-150 Floor 1A - Fire Stopping/Labeling Floor 1A SC 1.N1 Final Finishes
-
Tue 12/08
8
Data
Floor 8 N8503 - Install I. T. Rooms Doors
TEL-8-230 Floor 8 N8503 - Install I. T. Rooms Doors Telecom Room Lv-8 N8503
-
12/08→12/14
8
Data
Floor 8 N8504 - Pull LV Riser Cable
TEL-8-240 Floor 8 N8504 - Pull LV Riser Cable Telecom Room Lv-8 N8504
-
12/09→12/10
·
Ceilings
Bridge - Above Ceiling Inspection
BRIDGE-460 Bridge - Above Ceiling Inspection New Bridge
-
12/09→12/16
·
Flooring/Finishes
Bridge - Finish Paint
BRIDGE-440 Bridge - Finish Paint New Bridge
-
12/09→12/11
10A
Flooring/Finishes
Paint Prime & First Coat
10A-F-N1-1093 Floor 10A - Paint Prime & First Coat Floor 10A East Final Finishes
-
12/09→12/11
2B
Other
Final Clean
SC2B-N3-F-540 Floor 2B - Final Clean Floor 2B SC 2.N3
-
12/09→12/18
3B
Flooring/Finishes
Final Paint & Wallcovering
SC3B-N3-F-430 Floor 3B - Final Paint & Wallcovering Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/09→12/10
4A
Ceilings
Install Balance of Ceiling Tile
SC4A-N2-F-510 Floor 4A - Install Balance of Ceiling Tile Floor 4A SC 4.N2 Final Finishes
-
12/09→12/10
7
Data
Floor 7 N7504 - Clean I. T. Room
TEL-7-270 Floor 7 N7504 - Clean I. T. Room Telecom Room Lv-7 N7504
-
12/09→12/15
8
Inspections/QC
Floor 8 N8503 - Terminate & Test IT Systems Cabling
TEL-8-260 Floor 8 N8503 - Terminate & Test IT Systems Cabling Telecom Room Lv-8 N8503
-
Thu 12/10
·
Inspections/QC
CT R10 - In Wall Inspection
REV10-1700 CT R10 - In Wall Inspection CT Interior Roughs - Rev. 10
-
12/10→12/23
11
Drywall/Framing
Floor 11 South - Hang Drywall & Finish Drywall
GBW-1280 Floor 11 South - Hang Drywall & Finish Drywall Floor 11 Testing/Commissioning/Life Safety
-
12/11→12/15
·
Ceilings
Bridge - Drop Ceiling Tile
BRIDGE-470 Bridge - Drop Ceiling Tile New Bridge
-
Fri 12/11
·
Drywall/Framing
CT R10 - Blocking & Framing Inspection
REV10-1710 CT R10 - Blocking & Framing Inspection CT Interior Roughs - Rev. 10
-
12/11→01/04
12A
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
12A-IR-N1-1050 Floor 12A - In-Wall Electrical & I.T. Rough In & Control & QC Floor 12 A East Framing & Interior Roughs
-
12/11→01/04
12A
Plumbing
In-Wall Plumbing Rough QC
12A-IR-N1-1020 Floor 12A - In-Wall Plumbing Rough QC Floor 12 A East Framing & Interior Roughs
-
12/11→12/24
12A
Electrical
Install OH Cable Tray
12A-IR-N1-1260 Floor 12A - Install OH Cable Tray Floor 12 A East Overhead Roughs
-
12/11→12/17
3B
Ceilings
Install Balance of Ceiling Tile
SC3B-N3-F-530 Floor 3B - Install Balance of Ceiling Tile Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/11→12/17
4C
Flooring/Finishes
Final Paint & Wallcovering
SC4C-N1-F-380 Floor 4C - Final Paint & Wallcovering Floor 4C SC 4.N1 Final Finishes
-
12/11→12/15
5B
Flooring/Finishes
Paint Prime & First Coat
SC5B-N3-F-230 Floor 5B - Paint Prime & First Coat Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
Mon 12/14
·
Inspections/QC
IMRIS/CT R10 - Rough-In & Inspections Complete
REV10-1720 IMRIS/CT R10 - Rough-In & Inspections Complete IMRIS / CT Closeout - Rev. 10
-
12/14→12/23
10A
Ceilings
Install Ceiling Grid
10A-F-N1-1101 Floor 10A - Install Ceiling Grid Floor 10A East Final Finishes
-
12/14→12/23
10A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
10A-F-N1-1153 Floor 10A - Install Special Wall Finishes (incl. Wall Protection) Floor 10A East Final Finishes
-
12/15→01/20
·
Other
IMRIS R10 - Power/Data/Controls Integration + Trim (terminations, final connections)
REV10-1730 IMRIS R10 - Power/Data/Controls Integration + Trim (terminations, final connections) IMRIS / CT Closeout - Rev. 10
-
12/15→12/31
·
Other
South - Install Monorails
SWW-125 South - Install Monorails South Window Washing Support Steel / Equipment
-
12/15→01/06
12A
Plumbing
OH & In Wall MED Gas Rough In & QC
12A-IR-N1-1100 Floor 12A - OH & In Wall MED Gas Rough In & QC Floor 12 A East Overhead Roughs
-
12/15→12/31
1A
Ceilings
Install Ceiling Grid
SC1A-N2-F-190 Floor 1A - Install Ceiling Grid Floor 1A SC 1.N1 Final Finishes
-
Tue 12/15
8
Data
Floor 8 N8504 - Install I. T. Rooms Doors
TEL-8-250 Floor 8 N8504 - Install I. T. Rooms Doors Telecom Room Lv-8 N8504
-
12/15→12/21
9
Data
Floor 9 N8504 - Pull LV Riser Cable
TEL-9-220 Floor 9 N8504 - Pull LV Riser Cable Telecom Room Lv-9 N9504
-
12/16→12/22
·
Inspections/QC
Bridge - Clean and Punch
BRIDGE-480 Bridge - Clean and Punch New Bridge
-
12/16→12/22
3C
Inspections/QC
Stocking
SC3C-N1-F-540 Floor 3C - Stocking Floor 3C SC 3.N1 Final Finishes
-
12/16→12/22
4A
Other
Construction Clean
SC4A-N2-F-520 Floor 4A - Construction Clean Floor 4A SC 4.N2 Final Finishes
-
12/16→12/22
5B
Flooring/Finishes
Casework/Countertops
SC5B-N3-F-250 Floor 5B - Casework/Countertops Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/16→12/18
5B
Flooring/Finishes
Grout Bed for Floor Tile
SC5B-N3-F-210 Floor 5B - Grout Bed for Floor Tile Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/16→12/22
5B
Ceilings
Install Ceiling Grid
SC5B-N3-F-280 Floor 5B - Install Ceiling Grid Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/16→12/28
5B
Electrical
Light Fixtures in Soffit
SC5B-N3-F-240 Floor 5B - Light Fixtures in Soffit Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/16→12/17
8
Data
Floor 8 N8503 - Clean I. T. Room
TEL-8-270 Floor 8 N8503 - Clean I. T. Room Telecom Room Lv-8 N8503
-
12/16→12/22
8
Inspections/QC
Floor 8 N8504 - Terminate & Test IT Systems Cabling
TEL-8-280 Floor 8 N8504 - Terminate & Test IT Systems Cabling Telecom Room Lv-8 N8504
-
12/16→12/17
9B
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
9B-F-N2-1410 Floor 9B - Casework - Lower Base (For SV Flooring)` (CW-1) West 9B West Final Finishes
-
12/16→12/22
9B
Ceilings
Install Ceiling Grid
9B-F-N2-1100 Floor 9B - Install Ceiling Grid West 9B West Final Finishes
-
12/17→12/29
·
Flooring/Finishes
Bridge - Flooring
BRIDGE-450 Bridge - Flooring New Bridge
-
12/17→12/22
9A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
9A-F-N1-1510 Floor 9A - Building Specialties (incl. Curtain Track) Floor 9A East Final Finishes 9A
-
12/17→12/29
9A
Flooring/Finishes
Ceramic Tile / Grout @ Entry Sink
9A-F-N1-1240 Floor 9A - Ceramic Tile / Grout @ Entry Sink Floor 9A East Final Finishes 9A
-
12/17→01/08
9A
Plumbing
Plumbing Trim Out
9A-F-N1-1250 Floor 9A - Plumbing Trim Out Floor 9A East Final Finishes 9A
-
12/17→12/23
9A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
9A-F-N1-1375 Floor 9A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 9A East Final Finishes 9A
-
12/17→12/23
9A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
9A-F-N1-1500 Floor 9A - Wall Crash Rails/Hand Rails/Corner Guards Floor 9A East Final Finishes 9A
-
12/18→01/04
1A
Flooring/Finishes
Paint Prime & First Coat
SC1A-N2-F-170 Floor 1A - Paint Prime & First Coat Floor 1A SC 1.N1 Final Finishes
-
12/18→12/22
4B
Other
Div 10 Accessories
SC4B-N3-F-490 Floor 4B - Div 10 Accessories Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
12/18→12/24
4B
Inspections/QC
Final OH MEPF Inspections
SC4B-N3-F-480 Floor 4B - Final OH MEPF Inspections Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
12/18→01/04
4C
Electrical
Electrical Wall Fixtures/Devices
SC4C-N1-F-300 Floor 4C - Electrical Wall Fixtures/Devices Floor 4C SC 4.N1 Final Finishes
-
12/18→12/21
4C
Flooring/Finishes
Signage
SC4C-N1-F-460 Floor 4C - Signage Floor 4C SC 4.N1 Final Finishes
-
12/18→01/04
5A
Other
Div 10 Accessories
SC5A-N2-F-500 Floor 5A - Div 10 Accessories Floor 5A SC 5.N2 Final Finishes
-
12/18→12/24
5A
Inspections/QC
Final OH MEPF Inspections
SC5A-N2-F-490 Floor 5A - Final OH MEPF Inspections Floor 5A SC 5.N2 Final Finishes
-
12/18→12/24
5B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC5B-N3-F-260 Floor 5B - Install Special Wall Finishes (incl. Wall Protection) Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/18→01/04
5C
Plumbing
Plumbing Fixtures
SC5C-N1-F-290 Floor 5C - Plumbing Fixtures Floor 5C SC 5.N1 Final Finishes
-
12/18→12/24
9B
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
9B-F-N2-1190 Floor 9B - Flooring - SV Flooring + Cove Base` (FL-1) West 9B West Final Finishes
-
12/21→12/28
·
Concrete/Structure
Exterior Glass & Glazing - East Elevation
EXT-E-3010 Exterior Glass & Glazing - East Elevation Buck Hoist Infill Exterior Facade & Envelope
-
12/21→01/05
·
Other
Install PCC West Elevation
EXT-W-400 Install PCC West Elevation Buck Hoist Infill Exterior Facade & Envelope
-
12/21→12/23
10
Other
Temporary Cooling Floor 10
TEMP-10 Temporary Cooling Floor 10 Temporary Cooling
-
12/21→01/05
3B
Electrical
Electrical Wall Fixtures/Devices
SC3B-N3-F-460 Floor 3B - Electrical Wall Fixtures/Devices Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/21→02/02
3B
Other
Hang Booms by Owner
SC3B-N3-F-450 Floor 3B - Hang Booms by Owner Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/21→12/31
3B
Flooring/Finishes
Signage
SC3B-N3-F-470 Floor 3B - Signage Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
12/21→12/30
5B
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC5B-N3-F-220 Floor 5B - Ceramic Tile / Grout - Bathrooms Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/22→12/30
10A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
10A-F-N1-1133 Floor 10A - Drop Borders & Trade Cuts Ceiling Tiles Floor 10A East Final Finishes
-
12/22→12/29
11
Other
Floor 11 South Set Equipment
GBW-1290 Floor 11 South Set Equipment Floor 11 Testing/Commissioning/Life Safety
-
12/22→01/06
13
Other
Floor 13 South - In Wall MEPF Rough In
GBW-1560 Floor 13 South - In Wall MEPF Rough In Floor 13 Go Back Work - Pads South
-
12/22→12/29
5B
Flooring/Finishes
Soft Flooring & Base
SC5B-N3-F-300 Floor 5B - Soft Flooring & Base Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/22→12/29
9
Data
Floor 9 N9501 - Pull LV Riser Cable
TEL-9-240 Floor 9 N9501 - Pull LV Riser Cable Telecom Room Lv-9 N9501
-
Tue 12/22
9
Data
Floor 9 N9504 - Install I. T. Rooms Doors
TEL-9-230 Floor 9 N9504 - Install I. T. Rooms Doors Telecom Room Lv-9 N9504
-
12/23→01/07
12
Drywall/Framing
Floor 12 South - Hang Drywall & Finish Drywall
GBW-1430 Floor 12 South - Hang Drywall & Finish Drywall Floor 12 Testing/Commissioning/Life Safety
-
12/23→12/30
3C
Other
Final Clean
SC3C-N1-F-550 Floor 3C - Final Clean Floor 3C SC 3.N1 Final Finishes
-
12/23→01/07
4A
Inspections/QC
Load Equipment
SC4A-N2-F-530 Floor 4A - Load Equipment Floor 4A SC 4.N2 Final Finishes
-
12/23→12/30
4B
Flooring/Finishes
Final Paint & Wallcovering
SC4B-N3-F-430 Floor 4B - Final Paint & Wallcovering Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
12/23→12/28
5B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC5B-N3-F-340 Floor 5B - Drop Borders & Trade Cuts Ceiling Tiles Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/23→01/04
5B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC5B-N3-F-290 Floor 5B - HVAC Drops & Diffusers/Grid Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/23→12/24
6
Data
Floor 6 N6509 - Clean I. T. Room
TEL-6-290 Floor 6 N6509 - Clean I. T. Room Telecom Room Lv-6 N6509
-
12/23→12/24
8
Data
Floor 8 N8504 - Clean I. T. Room
TEL-8-310 Floor 8 N8504 - Clean I. T. Room Telecom Room Lv-8 N8504
-
12/23→01/05
9B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
9B-F-N2-1140 Floor 9B - Drop Borders & Trade Cuts Ceiling Tiles West 9B West Final Finishes
-
12/23→12/30
9B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
9B-F-N2-1120 Floor 9B - HVAC Drops & Diffusers/Grid West 9B West Final Finishes
-
12/23→01/14
9B
Electrical
Light Fixtures in Grid
9B-F-N2-1150 Floor 9B - Light Fixtures in Grid West 9B West Final Finishes
-
12/23→01/07
9B
Electrical
Remove Temp Light Fixtures
9B-F-N2-1340 Floor 9B - Remove Temp Light Fixtures West 9B West Final Finishes
-
12/24→12/28
10A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
10A-F-N1-1520 Floor 10A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 10A East Final Finishes
-
12/24→01/08
10A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
10A-F-N1-1113 Floor 10A - HVAC Drops & Diffusers/Grid Floor 10A East Final Finishes
-
12/24→01/15
10A
Electrical
Light Fixtures in Grid
10A-F-N1-1143 Floor 10A - Light Fixtures in Grid Floor 10A East Final Finishes
-
12/24→01/08
10A
Electrical
Remove Temp Light Fixtures
10A-F-N1-1340 Floor 10A - Remove Temp Light Fixtures Floor 10A East Final Finishes
-
12/24→01/06
9A
Flooring/Finishes
Doors & Hardware
9A-F-N1-1190 Floor 9A - Doors & Hardware Floor 9A East Final Finishes 9A
-
12/28→01/25
12A
Data
Pull Wire For All Low Voltage Systems
12A-IR-N1-1043 Floor 12A - Pull Wire For All Low Voltage Systems Floor 12 A East Overhead Roughs
-
12/28→01/07
12B
Plumbing
Med Gas Zone Valve Boxes/Terminations to Headwall
12B-IR-N2-1160 Floor 12B - Med Gas Zone Valve Boxes/Terminations to Headwall Floor 12 B West Framing & Interior Roughs
-
12/28→01/25
12B
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation
12B-IR-N2-1080 Floor 12B - OH Duct/VAV Boxes Rough-In/Insulation Floor 12 B West Overhead Roughs
-
12/28→01/25
12B
Electrical
OH-Electrical Rough/Racks Systems
12B-IR-N2-1030 Floor 12B - OH-Electrical Rough/Racks Systems Floor 12 B West Overhead Roughs
-
12/28→01/25
13
HVAC/Mechanical
OH Duct/VAV Boxes Rough-In/Insulation (Includes Food Prep Area)
13B-IR-N2-180 Floor 13 - OH Duct/VAV Boxes Rough-In/Insulation (Includes Food Prep Area) Floor 13 A Overhead Roughs
-
12/28→01/11
4
Inspections/QC
CEP Floor 4 - Gilbane/Contractor Punch-list
PN-4-4010 CEP Floor 4 - Gilbane/Contractor Punch-list CEP 4th Flr Clean & Punch-Out
-
12/28→12/29
4B
Ceilings
Install Balance of Ceiling Tile
SC4B-N3-F-530 Floor 4B - Install Balance of Ceiling Tile Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
12/28→01/04
9B
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
9B-F-N2-1220 Floor 9B - Flooring - All Other (LVT, Etc.)` (FL-2) West 9B West Final Finishes
-
12/29→01/26
·
Other
Elevator 3-4 - Install Cab & Machine
ELV-570 Elevator 3-4 - Install Cab & Machine Elevator 3-4
-
12/29→01/26
·
Other
Elevator 5-6 - Install Cab & Machine
ELV-660 Elevator 5-6 - Install Cab & Machine Elevator 5-6
-
12/29→01/05
·
Other
Exterior Caulking - East Elevation
EXT-E-3020 Exterior Caulking - East Elevation Buck Hoist Infill Exterior Facade & Envelope
-
12/29→01/19
10A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
10A-F-N1-1183 Floor 10A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 10A East Final Finishes
-
12/29→01/12
12A
Drywall/Framing
Frame Soffits/Hard Ceilings
12A-IR-N1-1240 Floor 12A - Frame Soffits/Hard Ceilings Floor 12 A East Overhead Roughs
-
12/29→01/19
5B
Data
All Low Voltage Devices
SC5B-N3-F-400 Floor 5B - All Low Voltage Devices Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/29→01/19
5B
Electrical
Light Fixtures in Grid
SC5B-N3-F-370 Floor 5B - Light Fixtures in Grid Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/29→01/05
5B
Fire/Sprinkler
Sprinkler Drops/Heads
SC5B-N3-F-380 Floor 5B - Sprinkler Drops/Heads Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
12/30→01/06
10
Data
Floor 10 N10504 - Pull LV Riser Cable
TEL-10-220 Floor 10 N10504 - Pull LV Riser Cable Telecom Room Lv-10 N10504
-
12/30→01/11
10A
Fire/Sprinkler
Sprinkler Drops/Heads
10A-F-N1-1163 Floor 10A - Sprinkler Drops/Heads Floor 10A East Final Finishes
-
12/30→01/06
11
Flooring/Finishes
Floor 11 South - Prime & 1st Coat
GBW-1300 Floor 11 South - Prime & 1st Coat Floor 11 Testing/Commissioning/Life Safety
-
12/30→01/06
5B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC5B-N3-F-310 Floor 5B - Wall Crash Rails/Hand Rails/Corner Guards Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
Wed 12/30
9
Data
Floor 9 N9501 - Install I. T. Rooms Doors
TEL-9-260 Floor 9 N9501 - Install I. T. Rooms Doors Telecom Room Lv-9 N9501
-
12/31→01/07
12
HVAC/Mechanical
AHU Drops/Duct Connections 12B N12503
12-M-120 AHU Drops/Duct Connections 12B N12503 Floor 12 B Mechanical Space N12503
-
01/04→01/22
·
Drywall/Framing
South - Frame Exterior Soffits
SWW-140 South - Frame Exterior Soffits South Window Washing Support Steel / Equipment
-
01/04→01/08
1A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
SC1A-N2-F-270 Floor 1A - Drop Borders & Trade Cuts Ceiling Tiles Floor 1A SC 1.N1 Final Finishes
-
01/04→01/12
1A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
SC1A-N2-F-210 Floor 1A - HVAC Drops & Diffusers/Grid Floor 1A SC 1.N1 Final Finishes
-
01/04→01/15
1A
Electrical
Remove Temp Light Fixtures
SC1A-N2-F-240 Floor 1A - Remove Temp Light Fixtures Floor 1A SC 1.N1 Final Finishes
-
01/04→01/22
1B
Drywall/Framing
Framing At Columns
SC1B-N1-IR-360 Floor 1B - Framing At Columns Floor 1B SC 1.N2 Overhead & Finishes
-
01/04→01/08
4B
Flooring/Finishes
Signage
SC4B-N3-F-470 Floor 4B - Signage Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
01/05→01/25
12B
Plumbing
In-Wall Plumbing Rough QC
12B-IR-N2-1020 Floor 12B - In-Wall Plumbing Rough QC Floor 12 B West Framing & Interior Roughs
-
01/05→02/01
1A
Flooring/Finishes
Carpet Tile, LVT, Sheet Vinyl
SC1A-N2-F-350 Floor 1A - Carpet Tile, LVT, Sheet Vinyl Floor 1A SC 1.N1 Final Finishes
-
01/05→01/25
1A
Flooring/Finishes
Ceramic Tile / Grout - Bathrooms
SC1A-N2-F-325 Floor 1A - Ceramic Tile / Grout - Bathrooms Floor 1A SC 1.N1 Final Finishes
-
01/05→01/07
4C
Ceilings
Install Balance of Ceiling Tile
SC4C-N1-F-500 Floor 4C - Install Balance of Ceiling Tile Floor 4C SC 4.N1 Final Finishes
-
01/05→01/18
5A
Flooring/Finishes
Final Paint & Wallcovering
SC5A-N2-F-450 Floor 5A - Final Paint & Wallcovering Floor 5A SC 5.N2 Final Finishes
-
01/05→01/11
5C
Other
Div 10 Accessories
SC5C-N1-F-420 Floor 5C - Div 10 Accessories Floor 5C SC 5.N1 Final Finishes
-
01/05→01/11
5C
Inspections/QC
Final OH MEPF Inspections
SC5C-N1-F-490 Floor 5C - Final OH MEPF Inspections Floor 5C SC 5.N1 Final Finishes
-
01/05→01/11
5C
Flooring/Finishes
Set Lockers
SC5C-N1-F-350 Floor 5C - Set Lockers Floor 5C SC 5.N1 Final Finishes
-
01/05→01/25
9B
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
9B-F-N2-1200 Floor 9B - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) West 9B West Final Finishes
-
01/06→01/12
·
Concrete/Structure
Exterior Glass & Glazing - West Elevation
EXT-W-410 Exterior Glass & Glazing - West Elevation Buck Hoist Infill Exterior Facade & Envelope
-
01/06→01/12
12
Other
Floor 12 South Set Equipment
GBW-1440 Floor 12 South Set Equipment Floor 12 Testing/Commissioning/Life Safety
-
01/06→01/26
3
Inspections/QC
N3503 - Terminate & Test IT Systems Cabling
TEL-3-260 Floor 3 - N3503 - Terminate & Test IT Systems Cabling Telecom Room Lv-3 N3503
-
01/06→01/19
4B
Electrical
Electrical Wall Fixtures/Devices
SC4B-N3-F-460 Floor 4B - Electrical Wall Fixtures/Devices Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
01/06→01/26
9B
Data
All Low Voltage Devices In Grid
9B-F-N2-1170 Floor 9B - All Low Voltage Devices In Grid West 9B West Final Finishes
-
01/06→01/15
9B
Fire/Sprinkler
Sprinkler Drops/Heads
9B-F-N2-1160 Floor 9B - Sprinkler Drops/Heads West 9B West Final Finishes
-
01/07→01/13
10
Data
Floor 10 N10501 - Pull LV Riser Cable
TEL-10-240 Floor 10 N10501 - Pull LV Riser Cable Telecom Room Lv-10 N10501
-
Thu 01/07
10
Data
Floor 10 N10504 - Install I. T. Rooms Doors
TEL-10-230 Floor 10 N10504 - Install I. T. Rooms Doors Telecom Room Lv-10 N10504
-
01/07→01/27
11
Electrical
Floor 11 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1310 Floor 11 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 11 Testing/Commissioning/Life Safety
-
01/07→01/08
12A
Inspections/QC
OH Inspections - MEPF
12A-IR-N1-1190 Floor 12A - OH Inspections - MEPF Floor 12 A East Overhead Roughs
-
01/07→01/27
12B
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
12B-IR-N2-2000 Floor 12B - OH HVAC Piping/Controls/Insulation & QC Floor 12 B West Overhead Roughs
-
01/07→02/03
13
Other
Floor 13 South - OH MEPF Rougth In
GBW-1550 Floor 13 South - OH MEPF Rougth In Floor 13 Go Back Work - Pads South
-
01/07→01/11
5B
Flooring/Finishes
Doors & Hardware
SC5B-N3-F-350 Floor 5B - Doors & Hardware Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/07→01/27
9A
Other
Div 10 Accessories
9A-F-N1-1280 Floor 9A - Div 10 Accessories Floor 9A East Final Finishes 9A
-
01/07→01/14
9A
Flooring/Finishes
Set Barn Doors At Patient Rooms
9A-F-N1-1230 Floor 9A - Set Barn Doors At Patient Rooms Floor 9A East Final Finishes 9A
-
01/08→01/18
12
HVAC/Mechanical
BMS Controls AHU N12503
12-M-130 BMS Controls AHU N12503 Floor 12 B Mechanical Space N12503
-
01/08→01/11
12B
Plumbing
Med Gas Testing
12B-IR-N2-1210 Floor 12B - Med Gas Testing Floor 12 B West Framing & Interior Roughs
-
01/08→01/28
12B
HVAC/Mechanical
OH HVAC Controls& QC
12B-IR-N2-1150 Floor 12B - OH HVAC Controls& QC Floor 12 B West Overhead Roughs
-
01/08→01/21
12B
Fire/Sprinkler
OH Sprinkler Rough In& QC
12B-IR-N2-1140 Floor 12B - OH Sprinkler Rough In& QC Floor 12 B West Overhead Roughs
-
01/08→01/11
4A
Inspections/QC
Owner Pre AHCA
SC4A-N2-F-540 Floor 4A - Owner Pre AHCA Floor 4A SC 4.N2 Final Finishes
-
01/08→01/14
4C
Other
Construction Clean
SC4C-N1-F-510 Floor 4C - Construction Clean Floor 4C SC 4.N1 Final Finishes
-
01/08→01/19
5A
Ceilings
Install Balance of Ceiling Tile
SC5A-N2-F-510 Floor 5A - Install Balance of Ceiling Tile Floor 5A SC 5.N2 Final Finishes
-
01/11→02/05
12A
Electrical
Pull Branch Circuits
12A-IR-N1-1250 Floor 12A - Pull Branch Circuits Floor 12 A East Overhead Roughs
-
01/11→02/05
12B
Electrical
OH Electrical & I.T. Rough In & QC
12B-IR-N2-1120 Floor 12B - OH Electrical & I.T. Rough In & QC Floor 12 B West Overhead Roughs
-
01/11→02/05
12B
Plumbing
OH Plumbing Rough In/Insulation & QC
12B-IR-N2-1110 Floor 12B - OH Plumbing Rough In/Insulation & QC Floor 12 B West Overhead Roughs
-
01/11→01/22
1A
Flooring/Finishes
Prep For Terrazzo Flooring
SC1A-N2-F-280 Floor 1A - Prep For Terrazzo Flooring Floor 1A SC 1.N1 Final Finishes
-
01/12→01/13
12B
Plumbing
Med Gas Pre Certification
12B-F-N2-1400 Floor 12B - Med Gas Pre Certification Floor 12 B West Final Finishes
-
01/12→02/08
4
Inspections/QC
CEP Floor 4 - Owner/Design Team Punch List
PN-4-4030 CEP Floor 4 - Owner/Design Team Punch List CEP 4th Flr Clean & Punch-Out
-
01/12→01/18
4A
Inspections/QC
Stocking
SC4A-N2-F-550 Floor 4A - Stocking Floor 4A SC 4.N2 Final Finishes
-
01/12→01/25
5A
Electrical
Electrical Wall Fixtures/Devices
SC5A-N2-F-470 Floor 5A - Electrical Wall Fixtures/Devices Floor 5A SC 5.N2 Final Finishes
-
01/12→01/15
5B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC5B-N3-F-320 Floor 5B - Building Specialties (incl. Curtain Track) Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/12→01/25
5B
Plumbing
Plumbing Fixtures
SC5B-N3-F-440 Floor 5B - Plumbing Fixtures Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/13→01/19
·
Other
Exterior Caulking - West Elevation
EXT-W-420 Exterior Caulking - West Elevation Buck Hoist Infill Exterior Facade & Envelope
-
01/13→01/19
12
Flooring/Finishes
Floor 12 South - Prime & 1st Coat
GBW-1450 Floor 12 South - Prime & 1st Coat Floor 12 Testing/Commissioning/Life Safety
-
01/13→01/26
12A
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
12A-F-N1-1010 Floor 12A - HVAC Drops & Diffusers in Soffit Floor 12 A East Overhead Roughs
-
01/13→01/22
1A
Other
Install Dock Levelers
SC1A-N2-F-450 Floor 1A - Install Dock Levelers Floor 1A SC 1.N1 Final Finishes
-
Thu 01/14
10
Data
Floor 10 N10501 - Install I. T. Rooms Doors
TEL-10-260 Floor 10 N10501 - Install I. T. Rooms Doors Telecom Room Lv-10 N10501
-
01/14→01/20
11
Data
Floor 11 (N11504) - Pull LV Riser Cable
TEL-11-220 Floor 11 (N11504) - Pull LV Riser Cable Telecom Room Lv-11 N11504
-
01/15→01/28
4C
Inspections/QC
Load Equipment
SC4C-N1-F-520 Floor 4C - Load Equipment Floor 4C SC 4.N1 Final Finishes
-
01/18→01/29
12B
Data
OH Low Voltage Pipe Rough-In
12B-IR-N2-1004 Floor 12B - OH Low Voltage Pipe Rough-In Floor 12 B West Overhead Roughs
-
01/18→01/22
5B
Inspections/QC
AHCA 80% Inspection
SC5B-N3-F-360 Floor 5B - AHCA 80% Inspection Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/18→01/22
9B
Inspections/QC
AHCA 80% Inspection For Areas (A & B)
9B-F-N2-1130 Floor 9B - AHCA 80% Inspection For Areas (A & B) West 9B West Final Finishes
-
01/19→02/01
12
Electrical
Install & Electronically Connect VFD's N12503
12-M-150 Install & Electronically Connect VFD's N12503 Floor 12 B Mechanical Space N12503
-
01/19→02/15
13
Plumbing
In-Wall Plumbing Rough In QC (Includes Food Prep Area)
13B-IR-N2-120 Floor 13 - In-Wall Plumbing Rough In QC (Includes Food Prep Area) Floor 13 A Framing & Interior Roughs
-
01/19→02/15
13
HVAC/Mechanical
OH HVAC Controls & QC
13B-IR-N2-250 Floor 13 - OH HVAC Controls & QC Floor 13 A Overhead Roughs
-
01/19→01/25
4A
Other
Final Clean
SC4A-N2-F-560 Floor 4A - Final Clean Floor 4A SC 4.N2 Final Finishes
-
01/19→01/21
5A
Flooring/Finishes
Signage
SC5A-N2-F-480 Floor 5A - Signage Floor 5A SC 5.N2 Final Finishes
-
01/19→01/25
5C
Flooring/Finishes
Final Paint & Wallcovering
SC5C-N1-F-380 Floor 5C - Final Paint & Wallcovering Floor 5C SC 5.N1 Final Finishes
-
01/20→05/11
·
Other
Hardscape/Landscape
SITE-1000 Hardscape/Landscape Finish Sitework
-
01/20→01/26
10A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
10A-F-N1-1530 Floor 10A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 10A East Final Finishes
-
01/20→02/09
12
Electrical
Floor 12 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1460 Floor 12 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 12 Testing/Commissioning/Life Safety
-
01/20→01/21
5B
Ceilings
Ceiling Grid QC
SC5B-N3-F-420 Floor 5B - Ceiling Grid QC Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/20→01/22
5B
Electrical
Remove Temp Light Fixtures
SC5B-N3-F-330 Floor 5B - Remove Temp Light Fixtures Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/20→01/26
5C
Ceilings
Install Balance of Ceiling Tile
SC5C-N1-F-500 Floor 5C - Install Balance of Ceiling Tile Floor 5C SC 5.N1 Final Finishes
-
01/21→03/03
·
Other
IMRIS R10 - RF Shielding + Architectural Close-In (seal rooms, final RF test)
REV10-1740 IMRIS R10 - RF Shielding + Architectural Close-In (seal rooms, final RF test) IMRIS / CT Closeout - Rev. 10
-
01/21→01/27
11
Data
Floor 11 (N11501) - Pull LV Riser Cable
TEL-11-240 Floor 11 (N11501) - Pull LV Riser Cable Telecom Room Lv-11 N11501
-
Thu 01/21
11
Data
Floor 11 (N11504) - Install I. T. Rooms Doors
TEL-11-230 Floor 11 (N11504) - Install I. T. Rooms Doors Telecom Room Lv-11 N11504
-
01/21→02/10
12A
Electrical
Light Fixtures Hard Ceilings & Soffits
12A-F-N1-1020 Floor 12A - Light Fixtures Hard Ceilings & Soffits Floor 12 A East Overhead Roughs
-
01/21→01/27
9B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
9B-F-N1-1500 Floor 9B - Wall Crash Rails/Hand Rails/Corner Guards West 9B West Final Finishes
-
01/22→01/28
5A
Other
Construction Clean
SC5A-N2-F-520 Floor 5A - Construction Clean Floor 5A SC 5.N2 Final Finishes
-
01/25→02/12
·
Concrete/Structure
South - Sheathing & Waterproofing
SWW-150 South - Sheathing & Waterproofing South Window Washing Support Steel / Equipment
-
01/25→02/12
12B
Electrical
In-Wall Electrical & I.T. Rough In & Control & QC
12B-IR-N2-1050 Floor 12B - In-Wall Electrical & I.T. Rough In & Control & QC Floor 12 B West Framing & Interior Roughs
-
Mon 01/25
13
Milestone
OH Duct/VAV Boxes rough-In ◆
M650 Floor 13 - OH Duct/VAV Boxes rough-In Construction Milestones
-
01/25→02/19
1A
Flooring/Finishes
Terrazzo Flooring
SC1A-N2-F-250 Floor 1A - Terrazzo Flooring Floor 1A SC 1.N1 Final Finishes
-
01/25→02/03
1B
Electrical
Electrical RI At Columns
SC1B-N1-IR-370 Floor 1B - Electrical RI At Columns Floor 1B SC 1.N2 Overhead & Finishes
-
Mon 01/25
2
Other
N2501 - Energize Power to Rack Receptacles
2-TEL-500 Floor 2 - N2501 - Energize Power to Rack Receptacles Telecom Room Lv-2 N2501 MDF
-
01/25→01/26
2A
Electrical
N2505 - Energize Electrical Room Panels
E-2-150 Floor 2A - N2505 - Energize Electrical Room Panels Electrical Room Lv-2 N2505 2A
-
01/25→02/05
3B
Plumbing
Install Med Gas Trim @ Booms
SC3B-N3-F-500 Floor 3B - Install Med Gas Trim @ Booms Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
01/25→01/26
6
Electrical
Floor 6 N6511 - Energize Electrical Room Panels
ELC-6-350 Floor 6 N6511 - Energize Electrical Room Panels Electrical Room Lv-6 N6511
-
Mon 01/25
6
Milestone
Inspect & Test Normal Power - 6th Floor ◆
M180 Inspect & Test Normal Power - 6th Floor Construction Milestones
-
01/26→01/27
12A
Inspections/QC
In-Wall Inspections - MEPF
12A-IR-N1-1070 Floor 12A - In-Wall Inspections - MEPF Floor 12 A East Framing & Interior Roughs
-
01/26→02/22
13
Fire/Sprinkler
OH Sprinkler Rough In & QC
13B-IR-N2-240 Floor 13 - OH Sprinkler Rough In & QC Floor 13 A Overhead Roughs
-
01/26→02/22
13
Electrical
OH-Electrical Rough/Racks Systems
13B-IR-N2-130 Floor 13 - OH-Electrical Rough/Racks Systems Floor 13 A Overhead Roughs
-
01/26→02/01
2
Data
N2501 - Load Rack I. T. Equipment
2-TEL-510 Floor 2 - N2501 - Load Rack I. T. Equipment Telecom Room Lv-2 N2501 MDF
-
01/26→02/15
5
Inspections/QC
Floor 5 N5504 - Terminate & Test IT Systems Cabling
TEL-5-280 Floor 5 N5504 - Terminate & Test IT Systems Cabling Telecom Room Lv-5 N5504
-
01/26→01/28
5B
Other
Div 10 Accessories
SC5B-N3-F-480 Floor 5B - Div 10 Accessories Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/26→02/01
5B
Inspections/QC
Final OH MEPF Inspections
SC5B-N3-F-490 Floor 5B - Final OH MEPF Inspections Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
01/26→02/08
5C
Electrical
Electrical Wall Fixtures/Devices
SC5C-N1-F-300 Floor 5C - Electrical Wall Fixtures/Devices Floor 5C SC 5.N1 Final Finishes
-
01/26→02/01
5C
Flooring/Finishes
Signage
SC5C-N1-F-460 Floor 5C - Signage Floor 5C SC 5.N1 Final Finishes
-
Tue 01/26
6
Milestone
Floor 6 N6511- Power Panels Energize ◆
FL1-E50 Floor 6 N6511- Power Panels Energize Electrical Room Lv-6 N6511
-
01/26→01/29
9B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
9B-F-N1-1510 Floor 9B - Building Specialties (incl. Curtain Track) West 9B West Final Finishes
-
01/26→02/01
9B
Flooring/Finishes
Ceramic Tile / Grout
9B-F-N2-1240 Floor 9B - Ceramic Tile / Grout West 9B West Final Finishes
-
01/26→02/15
9B
Plumbing
Plumbing Trim Out
9B-F-N2-1250 Floor 9B - Plumbing Trim Out West 9B West Final Finishes
-
01/26→02/01
9B
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
9B-F-N2-1420 Floor 9B - Wall Base (After All Flooring + Casework Tops)` (FL-3) West 9B West Final Finishes
-
01/27→02/16
·
Electrical
Elevator 3-4 - Install Electrical & Rope
ELV-500 Elevator 3-4 - Install Electrical & Rope Elevator 3-4
-
01/27→02/16
·
Electrical
Elevator 5-6 - Install Electrical & Rope
ELV-590 Elevator 5-6 - Install Electrical & Rope Elevator 5-6
-
01/27→02/05
10A
Data
All Low Voltage Devices In Grid
10A-F-N1-1333 Floor 10A - All Low Voltage Devices In Grid Floor 10A East Final Finishes
-
01/27→02/09
10A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
10A-F-N1-1203 Floor 10A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 10A East Final Finishes
-
01/27→01/28
2B
Electrical
2C - N2502 - Energize Electrical Room Panels
ELC-2-150 Floor 2B-2C - N2502 - Energize Electrical Room Panels Electrical Room Lv-2 N2502 2B, 2C
-
01/27→02/16
3
Inspections/QC
N3501 - Terminate & Test IT Systems Cabling
TEL-3000 Floor 3 - N3501 - Terminate & Test IT Systems Cabling Telecom Room Lv-3 N3501
-
01/27→01/28
3
Data
N3503 - Clean I. T. Room
TEL-3-280 Floor 3 - N3503 - Clean I. T. Room Telecom Room Lv-3 N3503
-
Wed 01/27
6
Other
Floor 6 N6501 - Energize Power to Rack Receptacles
TEL-6-340 Floor 6 N6501 - Energize Power to Rack Receptacles Telecom Room Lv-6 N6501
-
01/27→02/09
6
Electrical
Install & Electronically Connect VFD's HHW Exchanger
6A-4050 Install & Electronically Connect VFD's HHW Exchanger 6th Floor HHW Exchanger
-
01/27→01/29
6
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 6A
COM6-660 6th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 6A Floor 6 Testing/Commissioning/Life Safety
-
01/27→02/16
9
Inspections/QC
Floor 9 N9504 - Terminate & Test IT Systems Cabling
TEL-9-250 Floor 9 N9504 - Terminate & Test IT Systems Cabling Telecom Room Lv-9 N9504
-
Thu 01/28
11
Data
Floor 11 (N11501) - Install I. T. Rooms Doors
TEL-11-260 Floor 11 (N11501) - Install I. T. Rooms Doors Telecom Room Lv-11 N11501
-
01/28→02/01
11
Other
Temporary Cooling Floor 11
TEMP-111 Temporary Cooling Floor 11 Temporary Cooling
-
01/28→02/03
12
Data
N12504 - Pull LV Riser Cable
TEL-12-220 Floor 12 - N12504 - Pull LV Riser Cable Telecom Room Lv-12 N12504
-
01/28→02/10
12A
Drywall/Framing
Blocking/Backing/Plywood
12A-IR-N1-1090 Floor 12A - Blocking/Backing/Plywood Floor 12 A East Framing & Interior Roughs
-
01/28→03/03
13
HVAC/Mechanical
OH HVAC Piping/Controls/Insulation & QC
13B-IR-N2-2000 Floor 13 - OH HVAC Piping/Controls/Insulation & QC Floor 13 A Overhead Roughs
-
Thu 01/28
2A
Milestone
N2505 - Power Panels Energize ◆
FL1-E10 Floor 2A - N2505 - Power Panels Energize Electrical Room Lv-2 N2505 2A
-
01/28→02/10
4B
Plumbing
Install Med Gas Trim @ Booms
SC4B-N3-F-500 Floor 4B - Install Med Gas Trim @ Booms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
Thu 01/28
6
Other
Floor 6 N6509 - Energize Power to Rack Receptacles
TEL-6-350 Floor 6 N6509 - Energize Power to Rack Receptacles Telecom Room Lv-6 N6509
-
01/28→02/10
9A
Flooring/Finishes
Final Paint & Wallcovering
9A-F-N1-1270 Floor 9A - Final Paint & Wallcovering Floor 9A East Final Finishes 9A
-
01/28→02/10
9B
Flooring/Finishes
Doors & Hardware
9B-F-N2-1210 Floor 9B - Doors & Hardware West 9B West Final Finishes
-
01/29→02/02
2
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 2A
COM2-210 2nd Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 2A Floor 2 Testing/Commissioning/Life Safety
-
01/29→02/01
3
Electrical
N3505 - Energize Electrical Room Panels
ELC-3-410 Floor 3 - N3505 - Energize Electrical Room Panels Electrical Room Lv-3 N3505 3A, 3B East
-
01/29→02/01
4C
Inspections/QC
Owner Pre AHCA
SC4C-N1-F-530 Floor 4C - Owner Pre AHCA Floor 4C SC 4.N1 Final Finishes
-
01/29→02/11
5A
Inspections/QC
Load Equipment
SC5A-N2-F-530 Floor 5A - Load Equipment Floor 5A SC 5.N2 Final Finishes
-
01/29→02/04
5B
Flooring/Finishes
Final Paint & Wallcovering
SC5B-N3-F-410 Floor 5B - Final Paint & Wallcovering Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
02/01→02/26
13
Electrical
OH Electrical & I.T. Rough In & QC
13B-IR-N2-220 Floor 13 - OH Electrical & I.T. Rough In & QC Floor 13 A Overhead Roughs
-
02/01→02/26
13
Plumbing
OH Plumbing Rough In/Insulation & QC (Includes Food Prep Area)
13B-IR-N2-210 Floor 13 - OH Plumbing Rough In/Insulation & QC (Includes Food Prep Area) Floor 13 A Overhead Roughs
-
02/01→02/03
6
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 6B
COM6-670 6th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 6B Floor 6 Testing/Commissioning/Life Safety
-
02/02→02/08
2
Data
N2501 - Integrate & Test I. T. Systems
2-TEL-520 Floor 2 - N2501 - Integrate & Test I. T. Systems Telecom Room Lv-2 N2501 MDF
-
02/02→02/03
3
Electrical
N3502 - Energize Electrical Room Panels
ELC-3-400 Floor 3 - N3502 - Energize Electrical Room Panels Electrical Room Lv-3 N3502 3B West, 3C
-
02/02→02/08
4C
Inspections/QC
Stocking
SC4C-N1-F-540 Floor 4C - Stocking Floor 4C SC 4.N1 Final Finishes
-
02/02→02/03
5B
Ceilings
Install Balance of Ceiling Tile
SC5B-N3-F-530 Floor 5B - Install Balance of Ceiling Tile Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
02/02→02/08
5C
Other
Construction Clean
SC5C-N1-F-510 Floor 5C - Construction Clean Floor 5C SC 5.N1 Final Finishes
-
02/02→02/11
9B
Other
Div 10 Accessories
9B-F-N2-1290 Floor 9B - Div 10 Accessories West 9B West Final Finishes
-
02/03→02/05
2
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 2B
COM2-220 2nd Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 2B Floor 2 Testing/Commissioning/Life Safety
-
Wed 02/03
3
Milestone
N3505 - Power Panels Energize ◆
FL1-E20 Floor 3 - N3505 - Power Panels Energize Electrical Room Lv-3 N3505 3A, 3B East
-
02/03→03/16
4B
Other
Hang Booms
SC4B-N3-F-450 Floor 4B - Hang Booms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
02/03→02/10
9B
Flooring/Finishes
Set Barn Doors At Patient Rooms
9B-F-N2-1260 Floor 9B - Set Barn Doors At Patient Rooms West 9B West Final Finishes
-
02/04→02/10
12
Data
N12501 - Pull LV Riser Cable
TEL-12-240 Floor 12 - N12501 - Pull LV Riser Cable Telecom Room Lv-12 N12501
-
Thu 02/04
12
Data
N12504 - Install I. T. Rooms Doors
TEL-12-230 Floor 12 - N12504 - Install I. T. Rooms Doors Telecom Room Lv-12 N12504
-
02/04→02/17
13
Drywall/Framing
Floor 13 South - Hang Drywall & Finish Drywall
GBW-1570 Floor 13 South - Hang Drywall & Finish Drywall Floor 13 Go Back Work - Pads South
-
02/04→02/24
1B
Concrete/Structure
Sheathing & Water Proofing At Columns
SC1B-N1-IR-380 Floor 1B - Sheathing & Water Proofing At Columns Floor 1B SC 1.N2 Overhead & Finishes
-
02/04→02/08
3
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 3A
COM3-360 3rd Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 3A Floor 3 Testing/Commissioning/Life Safety
-
02/04→02/05
4
Electrical
Floor 4 N4505 - Energize Electrical Room Panels
ELC-4-210 Floor 4 N4505 - Energize Electrical Room Panels Electrical Room Lv-4 N4505 4A East, 4B East
-
02/04→02/08
6
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 6C
COM6-720 6th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 6C Floor 6 Testing/Commissioning/Life Safety
-
02/04→02/17
9A
Electrical
Electrical Wall Fixtures/Devices
9A-F-N1-1290 Floor 9A - Electrical Wall Fixtures/Devices Floor 9A East Final Finishes 9A
-
02/05→02/11
10A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
10A-F-N1-1500 Floor 10A - Wall Crash Rails/Hand Rails/Corner Guards Floor 10A East Final Finishes
-
02/05→03/04
1A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
SC1A-N2-F-200 Floor 1A - Install Special Wall Finishes (incl. Wall Protection) Floor 1A SC 1.N1 Final Finishes
-
02/05→02/11
5B
Electrical
Electrical Wall Fixtures/Devices
SC5B-N3-F-460 Floor 5B - Electrical Wall Fixtures/Devices Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
02/05→02/08
5B
Flooring/Finishes
Signage
SC5B-N3-F-470 Floor 5B - Signage Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
02/08→02/19
12B
Electrical
Install OH Cable Trays
12B-IR-N2-1260 Floor 12B - Install OH Cable Trays Floor 12 B West Overhead Roughs
-
02/08→02/26
12B
Plumbing
OH & In Wall MED Gas Rough In & QC
12B-IR-N2-1100 Floor 12B - OH & In Wall MED Gas Rough In & QC Floor 12 B West Overhead Roughs
-
02/08→02/09
12B
Inspections/QC
OH Inspections - MEPF
12B-IR-N2-1200 Floor 12B - OH Inspections - MEPF Floor 12 B West Overhead Roughs
-
02/08→02/10
2
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 2C
COM2-310 2nd Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 2C Floor 2 Testing/Commissioning/Life Safety
-
02/08→02/19
3B
Data
Install Low-Voltage Trim @ Booms
SC3B-N3-F-520 Floor 3B - Install Low-Voltage Trim @ Booms Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
02/08→02/09
4
Electrical
Floor 4 N4502 - Energize Electrical Room Panels
ELC-4-190 Floor 4 N4502 - Energize Electrical Room Panels Electrical Room Lv-4 N4502 4A West, 4C
-
02/09→02/11
3
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 3B
COM3-370 3rd Floor- Pre-Test Horns, Strobes, Pulls, Fire Alarm 3B Floor 3 Testing/Commissioning/Life Safety
-
Tue 02/09
4
Milestone
Floor 4 Power Panels Energize ◆
FL1-E30 Floor 4 Power Panels Energize Electrical Room Lv-4 N4505 4A East, 4B East
-
02/09→02/15
4C
Other
Final Clean
SC4C-N1-F-550 Floor 4C - Final Clean Floor 4C SC 4.N1 Final Finishes
-
02/09→02/22
5C
Inspections/QC
Load Equipment
SC5C-N1-F-520 Floor 5C - Load Equipment Floor 5C SC 5.N1 Final Finishes
-
Tue 02/09
6
Inspections/QC
Pre-Test Flows & Tampers
COM6-680 6th Floor - Pre-Test Flows & Tampers Floor 6 Testing/Commissioning/Life Safety
-
02/10→02/15
10A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
10A-F-N1-1510 Floor 10A - Building Specialties (incl. Curtain Track) Floor 10A East Final Finishes
-
02/10→02/19
10A
Flooring/Finishes
Ceramic Tile / Grout @ Entry Sink
10A-F-N1-1243 Floor 10A - Ceramic Tile / Grout @ Entry Sink Floor 10A East Final Finishes
-
02/10→02/23
10A
Plumbing
Plumbing Trim Out
10A-F-N1-1253 Floor 10A - Plumbing Trim Out Floor 10A East Final Finishes
-
02/10→02/16
10A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
10A-F-N1-1540 Floor 10A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 10A East Final Finishes
-
02/10→02/23
12B
Drywall/Framing
Frame Soffits/Hard Ceilings
12B-IR-N2-1240 Floor 12B - Frame Soffits/Hard Ceilings Floor 12 B West Overhead Roughs
-
02/10→03/09
12B
Electrical
Pull Branch Circuits
12B-IR-N2-1250 Floor 12B - Pull Branch Circuits Floor 12 B West Overhead Roughs
-
02/10→03/02
12B
Electrical
RI Light Fixtures Hard Ceilings & Soffits
12B-F-N2-1020 Floor 12B - RI Light Fixtures Hard Ceilings & Soffits Floor 12 B West Overhead Roughs
-
Wed 02/10
4
Other
Floor 4 N4501 - Energize Power to Rack Receptacles
TEL-4-480 Floor 4 N4501 - Energize Power to Rack Receptacles Telecom Room Lv-4 N4501
-
02/10→02/12
4
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 4A
COM4-460 4th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 4A Floor 4 Testing/Commissioning/Life Safety
-
02/10→02/11
5
Electrical
Floor 5 N5505 - Energize Electrical Room Panels
ELC-5-210 Floor 5 N5505 - Energize Electrical Room Panels Electrical Room Lv-5 N5505 5A,5B East
-
02/10→02/11
6
Other
Start-up Check Out Set HHW Exchanger
6A-4040 Start-up Check Out Set HHW Exchanger 6th Floor HHW Exchanger
-
Thu 02/11
12
Data
N12501 - Install I. T. Rooms Doors
TEL-12-260 Floor 12 - N12501 - Install I. T. Rooms Doors Telecom Room Lv-12 N12501
-
02/11→02/12
12A
Drywall/Framing
Framing Inspections
12A-F-N1-1030 Floor 12A - Framing Inspections Floor 12 A East Framing & Interior Roughs
-
02/11→02/17
12A
Ceilings
MEPF Inspections in Soffits
12A-F-N1-1050 Floor 12A - MEPF Inspections in Soffits Floor 12 A East Overhead Roughs
-
02/11→03/03
13
Data
N13501 - Pull LV Riser Cable
TEL-13-240 Floor 13 - N13501 - Pull LV Riser Cable Telecom Room Lv-13 N13501
-
02/11→02/17
4
Data
Floor 4 N4501 - Load Rack I. T. Equipment
TEL-4-510 Floor 4 N4501 - Load Rack I. T. Equipment Telecom Room Lv-4 N4501
-
02/11→02/22
9A
Flooring/Finishes
Install Roller Shades
9A-F-N1-1300 Floor 9A - Install Roller Shades Floor 9A East Final Finishes 9A
-
02/11→02/22
9A
Flooring/Finishes
Signage
9A-F-N1-1310 Floor 9A - Signage Floor 9A East Final Finishes 9A
-
02/12→02/23
10A
Flooring/Finishes
Doors & Hardware
10A-F-N1-1193 Floor 10A - Doors & Hardware Floor 10A East Final Finishes
-
02/12→02/23
12B
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
12B-F-N2-1010 Floor 12B - HVAC Drops & Diffusers in Soffit Floor 12 B West Overhead Roughs
-
02/12→02/16
3
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 3C
COM3-410 3rd Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 3C Floor 3 Testing/Commissioning/Life Safety
-
02/12→02/15
5
Electrical
Floor 5 N5502 - Energize Electrical Room Panels
ELC-5-190 Floor 5 N5502 - Energize Electrical Room Panels Electrical Room Lv-5 N5502 5B West, 5C
-
02/12→03/04
5
Inspections/QC
Floor 5 N5503 - Terminate & Test IT Systems Cabling
TEL-5-250 Floor 5 N5503 - Terminate & Test IT Systems Cabling Telecom Room Lv-5 N5503
-
Fri 02/12
5
Other
Floor 5 N5504 - Energize Power to Rack Receptacles
TEL-5-350 Floor 5 N5504 - Energize Power to Rack Receptacles Telecom Room Lv-5 N5504
-
02/12→02/15
5A
Inspections/QC
Owner Pre AHCA
SC5A-N2-F-540 Floor 5A - Owner Pre AHCA Floor 5A SC 5.N2 Final Finishes
-
02/12→02/23
9B
Flooring/Finishes
Final Paint
9B-F-N2-1270 Floor 9B - Final Paint West 9B West Final Finishes
-
02/15→02/17
·
Concrete/Structure
South - Inspections Waterproofing
SWW-160 South - Inspections Waterproofing South Window Washing Support Steel / Equipment
-
02/15→02/17
4
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 4B
COM4-470 4th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 4B Floor 4 Testing/Commissioning/Life Safety
-
Mon 02/15
5
Milestone
Floor 5 Power Panels Energize ◆
FL1-E40 Floor 5 Power Panels Energize Electrical Room Lv-5 N5505 5A,5B East
-
02/16→02/19
13
Inspections/QC
In-Wall Inspections - MEPF
13B-IR-N2-160 Floor 13 - In-Wall Inspections - MEPF Floor 13 A Framing & Interior Roughs
-
Tue 02/16
5
Other
Floor 5 N5503 - Energize Power to Rack Receptacles
TEL-5-340 Floor 5 N5503 - Energize Power to Rack Receptacles Telecom Room Lv-5 N5503
-
02/16→02/17
5
Data
Floor 5 N5504 - Clean I. T. Room
TEL-5-290 Floor 5 N5504 - Clean I. T. Room Telecom Room Lv-5 N5504
-
02/16→02/22
5A
Inspections/QC
Stocking
SC5A-N2-F-550 Floor 5A - Stocking Floor 5A SC 5.N2 Final Finishes
-
02/16→02/17
9
Electrical
Floor 9 N9505 - Energize Electrical Room Panels
ELC-9-190 Floor 9 N9505 - Energize Electrical Room Panels Electrical Room Lv-9 N9505 9A East, 9B East, 9C East
-
02/17→02/23
·
Other
Elevator 3-4 - Install Sills & Entrances
ELV-510 Elevator 3-4 - Install Sills & Entrances Elevator 3-4
-
02/17→02/23
·
Other
Elevator 5-6 - Install Sills & Entrances
ELV-600 Elevator 5-6 - Install Sills & Entrances Elevator 5-6
-
02/17→02/24
10A
Flooring/Finishes
Set Barn Doors At Patient Rooms
10A-F-N1-1233 Floor 10A - Set Barn Doors At Patient Rooms Floor 10A East Final Finishes
-
02/17→02/18
3
Data
N3501 - Clean I. T. Room
TEL-3080 Floor 3 - N3501 - Clean I. T. Room Telecom Room Lv-3 N3501
-
Wed 02/17
3
Inspections/QC
Pre-Test Flows & Tampers
COM3-380 3rd Floor - Pre-Test Flows & Tampers Floor 3 Testing/Commissioning/Life Safety
-
Wed 02/17
4
Other
Floor 4 N4504 - Energize Power to Rack Receptacles
TEL-4-350 Floor 4 N4504 - Energize Power to Rack Receptacles Telecom Room Lv-4 N4504
-
Wed 02/17
5
Other
Floor 5 N5501 - Energize Power to Rack Receptacles
TEL-5-520 Floor 5 N5501 - Energize Power to Rack Receptacles Telecom Room Lv-5 N5501
-
02/17→02/18
9
Data
Floor 9 N9504 - Clean I. T. Room
TEL-9-270 Floor 9 N9504 - Clean I. T. Room Telecom Room Lv-9 N9504
-
02/18→03/10
·
Concrete/Structure
South - EIFS System
SWW-170 South - EIFS System South Window Washing Support Steel / Equipment
-
02/18→02/24
13
Flooring/Finishes
Floor 13 South - Prime & 1st Coat
GBW-1580 Floor 13 South - Prime & 1st Coat Floor 13 Go Back Work - Pads South
-
02/18→02/24
4
Data
Floor 4 N4501 - Integrate & Test I. T. Systems
TEL-4-520 Floor 4 N4501 - Integrate & Test I. T. Systems Telecom Room Lv-4 N4501
-
Thu 02/18
4
Other
Floor 4 N4503 - Energize Power to Rack Receptacles
TEL-4-340 Floor 4 N4503 - Energize Power to Rack Receptacles Telecom Room Lv-4 N4503
-
02/18→02/22
4
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 4C
COM4-520 4th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 4C Floor 4 Testing/Commissioning/Life Safety
-
02/18→02/19
9
Electrical
Floor 9 N9502 - Energize Electrical Room Panels
ELC-9-210 Floor 9 N9502 - Energize Electrical Room Panels Electrical Room Lv-9 N9502 9A West, 9B West, 9C West
-
02/18→02/19
9
Other
Floor 9 N9504 - Energize Power to Rack Receptacles
TEL-9-340 Floor 9 N9504 - Energize Power to Rack Receptacles Telecom Room Lv-9 N9504
-
02/18→02/24
9A
Inspections/QC
Final OH MEPF Inspections
9A-F-N1-1260 Floor 9A - Final OH MEPF Inspections Floor 9A East Final Finishes 9A
-
Fri 02/19
3
Other
N3504 - Energize Power to Rack Receptacles
TEL-3-340 Floor 3 - N3504 - Energize Power to Rack Receptacles Telecom Room Lv-3 N3504
-
02/19→02/25
4
Data
Floor 4 N4503 - Load Rack I. T. Equipment
TEL-4-300 Floor 4 N4503 - Load Rack I. T. Equipment Telecom Room Lv-4 N4503
-
Fri 02/19
9
Milestone
Floor 9 Power Panels Energize ◆
FL1-E80 Floor 9 Power Panels Energize Floor 9 Electrical Rooms
-
02/22→02/23
10
Electrical
Floor 10 N10502 - Energize Electrical Room Panels
ELC-10-210 Floor 10 N10502 - Energize Electrical Room Panels Electrical Room Lv-10 N10502 10A west, 10B West, 10C West
-
02/22→03/12
12B
Data
Pull Wire For All Low Voltage Systems
12B-IR-N2-1043 Floor 12B - Pull Wire For All Low Voltage Systems Floor 12 B West Overhead Roughs
-
02/22→03/12
13
Drywall/Framing
Blocking/Backing/Plywood
13B-IR-N2-190 Floor 13 - Blocking/Backing/Plywood Floor 13 A Framing & Interior Roughs
-
02/22→03/12
1A
Data
All Low Voltage Devices In Grid
SC1A-N2-F-310 Floor 1A - All Low Voltage Devices In Grid Floor 1A SC 1.N1 Final Finishes
-
02/22→03/02
1A
Flooring/Finishes
Casework/Countertops
SC1A-N2-F-180 Floor 1A - Casework/Countertops Floor 1A SC 1.N1 Final Finishes
-
02/22→03/05
1A
Flooring/Finishes
Doors & Hardware
SC1A-N2-F-330 Floor 1A - Doors & Hardware Floor 1A SC 1.N1 Final Finishes
-
02/22→03/12
1A
Electrical
Light Fixtures in Grid
SC1A-N2-F-260 Floor 1A - Light Fixtures in Grid Floor 1A SC 1.N1 Final Finishes
-
02/22→03/05
1A
Fire/Sprinkler
Sprinkler Drops/Heads In Grid
SC1A-N2-F-300 Floor 1A - Sprinkler Drops/Heads In Grid Floor 1A SC 1.N1 Final Finishes
-
02/22→03/03
1A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
SC1A-N2-F-230 Floor 1A - Wall Crash Rails/Hand Rails/Corner Guards Floor 1A SC 1.N1 Final Finishes
-
02/22→02/23
2A
Other
N2506 - Start-up Check Out 2-2
2A2A-N2-M-140 Floor 2A - N2506 - Start-up Check Out 2-2 Floor 2A AHU 2-2 SC 2.N2 Mechanical Space N2506 Sterile
-
Mon 02/22
3
Other
N3503 - Energize Power to Rack Receptacles
TEL-3-350 Floor 3 - N3503 - Energize Power to Rack Receptacles Telecom Room Lv-3 N3503
-
Mon 02/22
3
Other
N3504- Energize Power to Rack Receptacles
TEL-3-480 Floor 3 - N3504- Energize Power to Rack Receptacles Telecom Room Lv-3 N3204
-
02/22→03/05
3B
Electrical
Install Electrical Finish @ Booms
SC3B-N3-F-510 Floor 3B - Install Electrical Finish @ Booms Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
02/22→03/05
4B
Data
Install Low-Voltage Trim @ Booms
SC4B-N3-F-520 Floor 4B - Install Low-Voltage Trim @ Booms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
02/22→02/23
9
Other
Floor 9 N9501 - Energize Power to Rack Receptacles
TEL-9-350 Floor 9 N9501 - Energize Power to Rack Receptacles Telecom Room Lv-9 N9501
-
02/22→02/26
9
Data
Floor 9 N9504 - Load Rack I. T. Equipment
TEL-9-300 Floor 9 N9504 - Load Rack I. T. Equipment Telecom Room Lv-9 N9504
-
02/23→02/24
2
Other
N2504 - Energize Power to Rack Receptacles
2-TEL-220 Floor 2 - N2504 - Energize Power to Rack Receptacles Telecom Room Lv-2 N2504
-
Tue 02/23
3
Other
N3501 - Energize Power to Rack Receptacles
TEL-3120 Floor 3 - N3501 - Energize Power to Rack Receptacles Telecom Room Lv-3 N3501
-
02/23→03/01
3
Data
N3503 - Load Rack I. T. Equipment
TEL-3-300 Floor 3 - N3503 - Load Rack I. T. Equipment Telecom Room Lv-3 N3503
-
02/23→03/01
3
Data
N3504 - Load Rack I. T. Equipment
TEL-3-450 Floor 3 - N3504 - Load Rack I. T. Equipment Telecom Room Lv-3 N3204
-
02/23→02/24
4
Inspections/QC
Pre-Test Flows & Tampers
COM4-480 4th Floor - Pre-Test Flows & Tampers Floor 4 Testing/Commissioning/Life Safety
-
02/23→03/01
5A
Other
Final Clean
SC5A-N2-F-560 Floor 5A - Final Clean Floor 5A SC 5.N2 Final Finishes
-
02/23→02/24
5C
Inspections/QC
Owner Pre AHCA
SC5C-N1-F-530 Floor 5C - Owner Pre AHCA Floor 5C SC 5.N1 Final Finishes
-
02/24→03/09
·
Other
Elevator 3-4 - Finish Hoistway Elect, Cab & Call Stations
ELV-530 Elevator 3-4 - Finish Hoistway Elect, Cab & Call Stations Elevator 3-4
-
02/24→03/09
·
Other
Elevator 5-6 - Finish Hoistway Elect, Cab & Call Stations
ELV-620 Elevator 5-6 - Finish Hoistway Elect, Cab & Call Stations Elevator 5-6
-
02/24→02/25
10
Electrical
Floor 10 N10505 - Energize Electrical Room Panels
ELC-10-190 Floor 10 N10505 - Energize Electrical Room Panels Electrical Room Lv-10 N10505 10A East, 10B West,10C West
-
02/24→03/05
10A
Other
Div 10 Accessories
10A-F-N1-1280 Floor 10A - Div 10 Accessories Floor 10A East Final Finishes
-
02/24→03/02
10A
Inspections/QC
Final OH MEPF Inspections
10A-F-N1-1263 Floor 10A - Final OH MEPF Inspections Floor 10A East Final Finishes
-
02/24→03/02
10B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
10B-F-N1-1500 Floor 10B - Wall Crash Rails/Hand Rails/Corner Guards Floor 10B West Final Finishes
-
02/24→03/02
2
HVAC/Mechanical
Test & Balance (AHU 2-2)
COM2-2055 2nd Floor - Test & Balance (AHU 2-2) Floor 2 Testing/Commissioning/Life Safety
-
02/24→02/25
2A
HVAC/Mechanical
N2509 - Start-up Check Out AHU 2-1
2C2C-N1-M-340 Floor 2A - N2509 - Start-up Check Out AHU 2-1 Floor 2A AHU 2-1 SC 2.N1 Mechanical Space N2509 SPD
-
02/24→03/09
9B
Electrical
Electrical Wall Fixtures/Devices
9B-F-N2-1310 Floor 9B - Electrical Wall Fixtures/Devices West 9B West Final Finishes
-
02/24→03/05
9B
Flooring/Finishes
Install Roller Shades
9B-F-N2-1320 Floor 9B - Install Roller Shades West 9B West Final Finishes
-
02/24→03/09
9B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
9B-F-N2-1110 Floor 9B - Install Special Wall Finishes (incl. Wall Protection) West 9B West Final Finishes
-
02/24→03/05
9B
Flooring/Finishes
Signage
9B-F-N2-1330 Floor 9B - Signage West 9B West Final Finishes
-
Thu 02/25
10
Milestone
Floor 10 Power Panels Energize ◆
FL1-E90 Floor 10 Power Panels Energize Electrical Room Lv-10 N10505 10A East, 10B West,10C West
-
02/25→03/17
13
Electrical
Floor 13 South - Mechanical, Electrical, Plumbing, Sys & Data Trim
GBW-1590 Floor 13 South - Mechanical, Electrical, Plumbing, Sys & Data Trim Floor 13 Go Back Work - Pads South
-
02/25→03/24
1B
Concrete/Structure
EFIS Finish
SC1B-N1-IR-390 Floor 1B - EFIS Finish Floor 1B SC 1.N2 Overhead & Finishes
-
Thu 02/25
2
Other
N2503 - Energize Power to Rack Receptacles
2-TEL-390 Floor 2 - N2503 - Energize Power to Rack Receptacles Telecom Room Lv-2 N2503
-
02/25→03/03
2
Data
N2504 - Load Rack I. T. Equipment
2-TEL-190 Floor 2 - N2504 - Load Rack I. T. Equipment Telecom Room Lv-2 N2504
-
02/25→03/03
5C
Inspections/QC
Stocking
SC5C-N1-F-540 Floor 5C - Stocking Floor 5C SC 5.N1 Final Finishes
-
02/25→03/08
9A
Ceilings
Install Balance of Ceiling Tile
9A-F-N1-1320 Floor 9A - Install Balance of Ceiling Tile Floor 9A East Final Finishes 9A
-
02/26→03/01
10
Other
Floor 10 N10504 - Energize Power to Rack Receptacles
TEL-10-340 Floor 10 N10504 - Energize Power to Rack Receptacles Telecom Room Lv-10 N10504
-
02/26→03/01
11
Electrical
Floor 11 (N11502) - Energize Electrical Room Panels
ELC-11-210 Floor 11 (N11502) - Energize Electrical Room Panels Electrical Room Lv-11 N11502 11A West, 11B West, 11C West
-
02/26→03/04
2
Data
N2503 - Load Rack I. T. Equipment
2-TEL-410 Floor 2 - N2503 - Load Rack I. T. Equipment Telecom Room Lv-2 N2503
-
02/26→03/01
2C
Other
N2507 - Start-up Check Out 2-3
2C2C-N1-M-140 Floor 2C - N2507 - Start-up Check Out 2-3 Floor 2C AHU 2-3 SC 2.N1 Mechanical Space N2507 SPD
-
02/26→03/04
4
Data
Floor 4 N4503 - Integrate & Test I. T. Systems
TEL-4-320 Floor 4 N4503 - Integrate & Test I. T. Systems Telecom Room Lv-4 N4503
-
02/26→03/04
4
Data
Floor 4 N4504 - Load Rack I. T. Equipment
TEL-4-310 Floor 4 N4504 - Load Rack I. T. Equipment Telecom Room Lv-4 N4504
-
03/01→03/04
10B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
10B-F-N1-1510 Floor 10B - Building Specialties (incl. Curtain Track) Floor 10B West Final Finishes
-
03/01→03/12
13
Electrical
Install OH Cable Tray
13B-IR-N2-140 Floor 13 - Install OH Cable Tray Floor 13 A Overhead Roughs
-
03/01→03/05
9
Data
Floor 9 N9504 - Integrate & Test I. T. Systems
TEL-9-310 Floor 9 N9504 - Integrate & Test I. T. Systems Telecom Room Lv-9 N9504
-
03/02→03/03
10
Other
Floor 10 N10501 - Energize Power to Rack Receptacles
TEL-10-350 Floor 10 N10501 - Energize Power to Rack Receptacles Telecom Room Lv-10 N10501
-
03/02→03/03
11
Electrical
Floor 11 (N11505) - Energize Electrical Room Panels
ELC-11-190 Floor 11 (N11505) - Energize Electrical Room Panels Electrical Room Lv-11 N11505 11A East, 11B East, 11C East
-
03/02→03/04
2
Inspections/QC
Pre-Test Fire Smoke Dampers
COM2-200 2nd Floor - Pre-Test Fire Smoke Dampers Floor 2 Testing/Commissioning/Life Safety
-
Tue 03/02
2
Inspections/QC
Pre-Test Flows & Tampers
COM2-250 2nd Floor - Pre-Test Flows & Tampers Floor 2 Testing/Commissioning/Life Safety
-
03/02→03/08
3
Data
N3501 - Load Rack I. T. Equipment
TEL-3090 Floor 3 - N3501 - Load Rack I. T. Equipment Telecom Room Lv-3 N3501
-
03/02→03/08
3
Data
N3503 - Integrate & Test I. T. Systems
TEL-3-320 Floor 3 - N3503 - Integrate & Test I. T. Systems Telecom Room Lv-3 N3503
-
03/02→03/08
3
Data
N3504 - Integrate & Test I. T. Systems
TEL-3-460 Floor 3 - N3504 - Integrate & Test I. T. Systems Telecom Room Lv-3 N3204
-
03/02→03/08
3
Data
N3504 - Load Rack I. T. Equipment
TEL-3-310 Floor 3 - N3504 - Load Rack I. T. Equipment Telecom Room Lv-3 N3504
-
03/02→03/03
6
Other
Start-up Check Out 3-1
AHU3-1-1070 Start-up Check Out 3-1 6th Floor AHU 3-1
-
Wed 03/03
11
Milestone
Floor 11 Power Panels Energize ◆
FL1-E100 Floor 11 Power Panels Energize Electrical Room Lv-11 N11502 11A West, 11B West, 11C West
-
03/03→03/09
12B
Ceilings
MEPF Inspections in Soffits
12B-F-N2-1050 Floor 12B - MEPF Inspections in Soffits Floor 12 B West Overhead Roughs
-
03/03→03/09
2B
HVAC/Mechanical
2nd Floor 2B - Test & Balance (AHU 2-1)
COM2-2065 2nd Floor 2B - Test & Balance (AHU 2-1) Floor 2 Testing/Commissioning/Life Safety
-
03/04→03/05
·
Ceilings
IMRIS R10 - In-Wall / Above-Ceiling Close-In Inspection
REV10-1750 IMRIS R10 - In-Wall / Above-Ceiling Close-In Inspection IMRIS / CT Closeout - Rev. 10
-
03/04→03/05
11
Other
Floor 11 (N11504) - Energize Power to Rack Receptacles
TEL-11-340 Floor 11 (N11504) - Energize Power to Rack Receptacles Telecom Room Lv-11 N11504
-
03/04→03/09
11A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
11A-F-N1-1510 Floor 11A - Building Specialties (incl. Curtain Track) Floor 11A East Final Finishes
-
03/04→03/10
11A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
11A-F-N1-1500 Floor 11A - Wall Crash Rails/Hand Rails/Corner Guards Floor 11A East Final Finishes
-
03/04→03/05
12
Electrical
N12502 - Energize Electrical Room Panels
ELC-12-210 Floor 12 - N12502 - Energize Electrical Room Panels Electrical Room Lv-12 N12502 Corridor 2 12A West, 12B West, 12C West
-
03/04→03/31
12A
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
12A-F-N1-1060 Floor 12A - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 12 A East Final Finishes
-
Thu 03/04
13
Data
N13501 - Install I. T. Rooms Doors
TEL-13-260 Floor 13 - N13501 - Install I. T. Rooms Doors Telecom Room Lv-13 N13501
-
03/04→03/31
13
Data
N13505 - Pull LV Riser Cable
TEL-13-220 Floor 13 - N13505 - Pull LV Riser Cable Telecom Room Lv-13 N13505
-
03/04→03/09
13
Inspections/QC
OH Inspections - MEPF
13B-IR-N2-280 Floor 13 - OH Inspections - MEPF Floor 13 A Overhead Roughs
-
03/04→03/10
2
Data
N2504 - Integrate & Test I. T. Systems
2-TEL-200 Floor 2 - N2504 - Integrate & Test I. T. Systems Telecom Room Lv-2 N2504
-
03/04→03/10
5C
Other
Final Clean
SC5C-N1-F-550 Floor 5C - Final Clean Floor 5C SC 5.N1 Final Finishes
-
03/04→03/05
6
Other
Start-up Check Out 3-2
AHU3-2-1050 Start-up Check Out 3-2 6th Floor AHU 3-2
-
03/05→03/25
1A
Other
Div 10 Accessories
SC1A-N2-F-420 Floor 1A - Div 10 Accessories Floor 1A SC 1.N1 Final Finishes
-
03/05→03/08
2
Data
Complete Fire Alarm Pre-test Punch List Items
COM2-230 2nd Floor - Complete Fire Alarm Pre-test Punch List Items Floor 2 Testing/Commissioning/Life Safety
-
03/05→03/11
2
Data
N2503 - Integrate & Test I. T. Systems
2-TEL-420 Floor 2 - N2503 - Integrate & Test I. T. Systems Telecom Room Lv-2 N2503
-
03/05→03/08
2
Inspections/QC
Test Fire Smoke Dampers
COM2-240 2nd Floor- Test Fire Smoke Dampers Floor 2 Testing/Commissioning/Life Safety
-
03/05→03/11
4
Data
Floor 4 N4504 - Integrate & Test I. T. Systems
TEL-4-330 Floor 4 N4504 - Integrate & Test I. T. Systems Telecom Room Lv-4 N4504
-
03/05→03/25
5
Inspections/QC
Floor 5 N5501 - Terminate & Test IT Systems Cabling
TEL-5-400 Floor 5 N5501 - Terminate & Test IT Systems Cabling Telecom Room Lv-5 N5501
-
03/05→03/08
5
Data
Floor 5 N5503 - Clean I. T. Room
TEL-5-270 Floor 5 N5503 - Clean I. T. Room Telecom Room Lv-5 N5503
-
03/05→03/11
6
Data
Floor 6 N6501 - Load Rack I. T. Equipment
TEL-6-300 Floor 6 N6501 - Load Rack I. T. Equipment Telecom Room Lv-6 N6501
-
03/08→04/02
·
Inspections/QC
IMRIS R10 - Start-up Support, Vendor Coordination - Punch Ready
REV10-1760 IMRIS R10 - Start-up Support, Vendor Coordination - Punch Ready IMRIS / CT Closeout - Rev. 10
-
03/08→03/19
10A
Flooring/Finishes
Final Paint & Wallcovering
10A-F-N1-1273 Floor 10A - Final Paint & Wallcovering Floor 10A East Final Finishes
-
03/08→03/09
11
Other
Floor 11 (N11501) - Energize Power to Rack Receptacles
TEL-11-350 Floor 11 (N11501) - Energize Power to Rack Receptacles Telecom Room Lv-11 N11501
-
03/08→03/09
12
Electrical
N12505 - Energize Electrical Room Panels
ELC-12-190 Floor 12 - N12505 - Energize Electrical Room Panels Electrical Room Lv-12 N12505 Corridor 1 12A East, 12B East, 12C East
-
03/08→03/19
1A
Plumbing
Plumbing Trim
SC1A-N2-F-400 Floor 1A - Plumbing Trim Floor 1A SC 1.N1 Final Finishes
-
03/08→03/12
3B
Other
Construction Clean
SC3B-N3-F-540 Floor 3B - Construction Clean Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/08→03/19
4B
Electrical
Install Electrical Finish @ Booms
SC4B-N3-F-510 Floor 4B - Install Electrical Finish @ Booms Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
03/08→03/09
6
Other
Start-up Check Out 3-3
AHU3-3-1050 Start-up Check Out 3-3 6th Floor AHU 3-3
-
Tue 03/09
12
Milestone
N12502 - Power Panels Energize ◆
FL1-E110 Floor 12 - N12502 - Power Panels Energize Electrical Room Lv-12 N12502 Corridor 2 12A West, 12B West, 12C West
-
Tue 03/09
2
Inspections/QC
Final Test Horns, Strobes, Pulls 2A
COM2-260 2nd Floor - Final Test Horns, Strobes, Pulls 2A Floor 2 Testing/Commissioning/Life Safety
-
03/09→03/15
3
Data
N3501 - Integrate & Test I. T. Systems
TEL-3100 Floor 3 - N3501 - Integrate & Test I. T. Systems Telecom Room Lv-3 N3501
-
03/09→03/15
3
Data
N3504 - Integrate & Test I. T. Systems
TEL-3-330 Floor 3 - N3504 - Integrate & Test I. T. Systems Telecom Room Lv-3 N3504
-
03/09→03/15
5
Data
Floor 5 N5503 - Load Rack I. T. Equipment
TEL-5-300 Floor 5 N5503 - Load Rack I. T. Equipment Telecom Room Lv-5 N5503
-
03/09→03/15
9A
Other
Construction Clean
9A-F-N1-1340 Floor 9A - Construction Clean Floor 9A East Final Finishes 9A
-
03/10→03/16
·
Other
Elevator 3-4 - Install Cab Finishes
ELV-550 Elevator 3-4 - Install Cab Finishes Elevator 3-4
-
03/10→03/16
·
Other
Elevator 5-6 - Install Cab Finishes
ELV-640 Elevator 5-6 - Install Cab Finishes Elevator 5-6
-
03/10→03/11
12
Other
N12504 - Energize Power to Rack Receptacles
TEL-12-340 Floor 12 - N12504 - Energize Power to Rack Receptacles Telecom Room Lv-12 N12504
-
03/10→03/11
12B
Inspections/QC
In-Wall Inspections - MEPF
12B-IR-N2-1070 Floor 12B - In-Wall Inspections - MEPF Floor 12 B West Framing & Interior Roughs
-
03/10→03/23
13
Drywall/Framing
Frame Soffits/Hard Ceilings
13B-IR-N2-330 Floor 13 - Frame Soffits/Hard Ceilings Floor 13 A Overhead Roughs
-
03/10→03/11
13
Electrical
N13502 - Energize Electrical Room Panels
ELC-13-210 Floor 13 - N13502 - Energize Electrical Room Panels Electrical Room Lv-13
-
03/10→04/06
13
Electrical
Pull Branch Circuits
13B-IR-N2-340 Floor 13 - Pull Branch Circuits Floor 13 A Overhead Roughs
-
Wed 03/10
2
Inspections/QC
Final Test Horns, Strobes, Pulls 2B
COM2-280 2nd Floor - Final Test Horns, Strobes, Pulls 2B Floor 2 Testing/Commissioning/Life Safety
-
03/10→03/16
2C
HVAC/Mechanical
2nd Floor 2C - Test & Balance (AHU 2-3)
COM2-2075 2nd Floor 2C - Test & Balance (AHU 2-3) Floor 2 Testing/Commissioning/Life Safety
-
03/10→03/23
3
Other
CEP Floor 3 - Flush (CHW) Piping @ CEP to Floors 7-13
CEPN-M-3120 CEP Floor 3 - Flush (CHW) Piping @ CEP to Floors 7-13 Mechanical 3rd Flr (Chillers & Pumps)
-
03/10→03/16
3A
HVAC/Mechanical
3rd Floor 3A - Test & Balance (AHU 3-2, AHU 3-3)
COM3-3055 3rd Floor 3A - Test & Balance (AHU 3-2, AHU 3-3) Floor 3 Testing/Commissioning/Life Safety
-
03/10→03/11
6
Other
Start-up Check Out 3-4
AHU3-4-1070 Start-up Check Out 3-4 6th Floor AHU 3-4
-
03/10→03/30
9
Inspections/QC
Floor 9 N9501 - Terminate & Test IT Systems Cabling
TEL-9-280 Floor 9 N9501 - Terminate & Test IT Systems Cabling Telecom Room Lv-9 N9501
-
03/10→03/16
9B
Inspections/QC
Final OH MEPF Inspections
9B-F-N2-1280 Floor 9B - Final OH MEPF Inspections West 9B West Final Finishes
-
03/11→03/22
·
Other
South - Exterior Sealant
SWW-180 South - Exterior Sealant South Window Washing Support Steel / Equipment
-
03/11→04/07
12A
Drywall/Framing
Finish Drywall
12A-F-N1-1080 Floor 12A - Finish Drywall Floor 12 A East Final Finishes
-
Thu 03/11
2
Inspections/QC
Final Test Horns, Strobes, Pulls 2C
COM2-320 2nd Floor - Final Test Horns, Strobes, Pulls 2C Floor 2 Testing/Commissioning/Life Safety
-
03/11→04/07
5
Inspections/QC
Gilbane Functional/Pre-Inspections
5-P-1000 Floor 5 - Gilbane Functional/Pre-Inspections Floor 5 Clean & Punch-Out
-
03/12→03/15
12
Other
N12501 - Energize Power to Rack Receptacles
TEL-12-350 Floor 12 - N12501 - Energize Power to Rack Receptacles Telecom Room Lv-12 N12501
-
03/12→03/25
12B
Drywall/Framing
Blocking/Backing/Plywood
12B-IR-N2-1090 Floor 12B - Blocking/Backing/Plywood Floor 12 B West Framing & Interior Roughs
-
03/12→03/15
13A
Electrical
N13504 - Energize Electrical Room Panels
ELC-13-190 Floor 13A - N13504 - Energize Electrical Room Panels Electrical Room Lv-13 N13504 13A
-
Fri 03/12
2
Inspections/QC
Final Test Flows & Tampers
COM2-270 2nd Floor - Final Test Flows & Tampers Floor 2 Testing/Commissioning/Life Safety
-
03/12→03/18
6
Data
Floor 6 N6501 - Integrate & Test I. T. Systems
TEL-6-310 Floor 6 N6501 - Integrate & Test I. T. Systems Telecom Room Lv-6 N6501
-
03/12→03/18
6
Data
Floor 6 N6509 - Load Rack I. T. Equipment
TEL-6-320 Floor 6 N6509 - Load Rack I. T. Equipment Telecom Room Lv-6 N6509
-
03/12→03/15
6
Other
Start-up Check Out 3-5
AHU3-5-1050 Start-up Check Out 3-5 6th Floor AHU 3-5
-
03/15→03/26
10A
Electrical
Electrical Wall Fixtures/Devices
10A-F-N1-1300 Floor 10A - Electrical Wall Fixtures/Devices Floor 10A East Final Finishes
-
03/15→04/09
13
Data
Pull Wire For All Low Voltage Systems
13B-IR-N2-178 Floor 13 - Pull Wire For All Low Voltage Systems Floor 13 A Overhead Roughs
-
Mon 03/15
13A
Milestone
N13504 - Floor 13 Power Panels Energize ◆
FL1-E120 Floor 13A - N13504 - Floor 13 Power Panels Energize Electrical Room Lv-13 N13504 13A
-
03/15→03/19
1A
Inspections/QC
AHCA - 80% Inspection
SC1A-N2-F-360 AHCA - 80% Inspection Floor 1A SC 1.N1 Final Finishes
-
03/15→03/26
1A
Ceilings
Ceiling Grid QC
SC1A-N2-F-340 Floor 1A - Ceiling Grid QC Floor 1A SC 1.N1 Final Finishes
-
03/15→03/19
2
Inspections/QC
Pre-Test Doors/Final Test Doors
COM2-290 2nd Floor - Pre-Test Doors/Final Test Doors Floor 2 Testing/Commissioning/Life Safety
-
03/15→04/09
3
Inspections/QC
Gilbane Functional/Pre-Inspections
3-P-1050 Floor 3 - Gilbane Functional/Pre-Inspections Floor-3 Clean & Punch-Out
-
03/15→03/26
3B
Inspections/QC
Load Equipment
SC3B-N3-F-550 Floor 3B - Load Equipment Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/16→03/17
1
Electrical
N1502 - Energize Electrical Room Panels
ELC-1-150 Floor 1 - N1502 - Energize Electrical Room Panels Electrical Room Lv-1 - N1502 - Entire Floor
-
03/16→03/17
13
Other
N13505 - Energize Power to Rack Receptacles
TEL-13-340 Floor 13 - N13505 - Energize Power to Rack Receptacles Telecom Room Lv-13 N13505
-
03/16→03/18
3
Inspections/QC
Pre-Test Fire Smoke Dampers
COM3-350 3rd Floor - Pre-Test Fire Smoke Dampers Floor 3 Testing/Commissioning/Life Safety
-
03/16→03/22
5
Data
Floor 5 N5503 - Integrate & Test I. T. Systems
TEL-5-310 Floor 5 N5503 - Integrate & Test I. T. Systems Telecom Room Lv-5 N5503
-
03/16→03/22
5
Data
Floor 5 N5504 - Load Rack I. T. Equipment
TEL-5-320 Floor 5 N5504 - Load Rack I. T. Equipment Telecom Room Lv-5 N5504
-
03/16→03/17
6
HVAC/Mechanical
Start-up Check Out - AHU 4-1
AHU4-1-1050 Start-up Check Out - AHU 4-1 6th Floor AHU 4-1
-
03/16→03/29
9A
Inspections/QC
Load Equipment
9A-F-N1-1350 Floor 9A - Load Equipment Floor 9A East Final Finishes 9A
-
03/17→03/23
·
Concrete/Structure
Elevator 3-4 - Complete CMU at Shafts
ELV-520 Elevator 3-4 - Complete CMU at Shafts Elevator 3-4
-
03/17→03/23
·
Concrete/Structure
Elevator 5-6 - Complete CMU at Shafts
ELV-610 Elevator 5-6 - Complete CMU at Shafts Elevator 5-6
-
Wed 03/17
1
Milestone
N1502 - Power Panels Energize ◆
FL1-E Floor 1 - N1502 - Power Panels Energize Electrical Room Lv-1 - N1502 - Entire Floor
-
03/17→03/23
13
Drywall/Framing
Framing Inspections
13B-F-N2-130 Floor 13 - Framing Inspections Floor 13 A Framing & Interior Roughs
-
03/17→04/13
2
Inspections/QC
Gilbane Functional/Pre-Inspections
2-P-1050 Floor 2 - Gilbane Functional/Pre-Inspections Floor 2 Clean & Punch-Out
-
03/17→03/23
3B
HVAC/Mechanical
3rd Floor 3B - Test & Balance (AHU 3-4, 3-5)
COM3-3065 3rd Floor 3B - Test & Balance (AHU 3-4, 3-5) Floor 3 Testing/Commissioning/Life Safety
-
03/17→04/27
5B
Other
Hang Booms
SC5B-N3-F-450 Floor 5B - Hang Booms Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
03/17→03/26
9B
Ceilings
Install Balance of Ceiling Tile
9B-F-N2-1300 Floor 9B - Install Balance of Ceiling Tile West 9B West Final Finishes
-
03/18→03/24
1
Other
N1503 - Energize Power to Rack Receptacles
TEL-1-340 Floor 1 - N1503 - Energize Power to Rack Receptacles Telecom Room Lv-1 N1503
-
03/18→03/22
1
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 1A
COM1-160 1st Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 1A Floor 1 Testing/Commissioning/Life Safety
-
03/18→03/19
1
HVAC/Mechanical
Start-up Check Out (AHU 1-1)
AHU1-1-1070 Start-up Check Out (AHU 1-1) Floor 1 Mechanical Space
-
03/18→03/19
13
Other
N13501 - Energize Power to Rack Receptacles
TEL-13-350 Floor 13 - N13501 - Energize Power to Rack Receptacles Telecom Room Lv-13 N13501
-
03/18→03/19
6
HVAC/Mechanical
Start-up Check Out - AHU 4-2
AHU4-2-1070 Start-up Check Out - AHU 4-2 6th Floor AHU 4-2
-
03/18→03/19
7
Electrical
Floor 7 N7505 - Energize Electrical Room Panels
ELC-7-410 Floor 7 N7505 - Energize Electrical Room Panels Electrical Room Lv-7 N7505
-
03/19→03/22
3
Data
Complete Fire Alarm Pre-test Punch List Items
COM3-300 3rd Floor - Complete Fire Alarm Pre-test Punch List Items Floor 3 Testing/Commissioning/Life Safety
-
03/19→03/22
3
Inspections/QC
Test Fire Smoke Dampers
COM3-340 3rd Floor - Test Fire Smoke Dampers Floor 3 Testing/Commissioning/Life Safety
-
03/19→03/25
6
Data
Floor 6 N6509 - Integrate & Test I. T. Systems
TEL-6-330 Floor 6 N6509 - Integrate & Test I. T. Systems Telecom Room Lv-6 N6509
-
03/22→03/31
10A
Flooring/Finishes
Install Roller Shades
10A-F-N1-1310 Floor 10A - Install Roller Shades Floor 10A East Final Finishes
-
03/22→03/31
10A
Flooring/Finishes
Signage
10A-F-N1-1320 Floor 10A - Signage Floor 10A East Final Finishes
-
03/22→03/26
1A
Inspections/QC
Final OH MEPF Inspections
SC1A-N2-F-410 Floor 1A - Final OH MEPF Inspections Floor 1A SC 1.N1 Final Finishes
-
Mon 03/22
2
Inspections/QC
Final Test Doors
COM2-300 2nd Floor- Final Test Doors Floor 2 Testing/Commissioning/Life Safety
-
03/22→03/26
4A
HVAC/Mechanical
4th Floor 4A - Test & Balance (AHU 4-2, AHU 4-3)
COM4-4055 4th Floor 4A - Test & Balance (AHU 4-2, AHU 4-3) Floor 4 Testing/Commissioning/Life Safety
-
03/22→03/26
4B
Other
Construction Clean
SC4B-N3-F-560 Floor 4B - Construction Clean Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
03/22→03/23
6
HVAC/Mechanical
Start-up Check Out - AHU 4-3
AHU4-3-1050 Start-up Check Out - AHU 4-3 6th Floor AHU 4-3
-
03/22→03/23
7
Electrical
Floor 7 N7502 - Energize Electrical Room Panels
ELC-7-400 Floor 7 N7502 - Energize Electrical Room Panels Electrical Room Lv-7 N7502
-
03/22→03/23
7
Other
Floor 7 N7504 - Energize Power to Rack Receptacles
TEL-7-340 Floor 7 N7504 - Energize Power to Rack Receptacles Telecom Room Lv-7 N7504
-
03/23→03/25
·
Inspections/QC
South - Inspections
SWW-190 South - Inspections South Window Washing Support Steel / Equipment
-
03/23→03/25
1
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 1B
COM1-170 1st Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 1B Floor 1 Testing/Commissioning/Life Safety
-
03/23→03/29
2B
Inspections/QC
100% AHCA For Areas (A, B & C)
SC2B-N3-F-550 Floor 2B - 100% AHCA For Areas (A, B & C) Floor 2B SC 2.N3
-
Tue 03/23
3
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 3A
COM3-310 3rd Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 3A Floor 3 Testing/Commissioning/Life Safety
-
03/23→03/29
5
Data
Floor 5 N5504 - Integrate & Test I. T. Systems
TEL-5-330 Floor 5 N5504 - Integrate & Test I. T. Systems Telecom Room Lv-5 N5504
-
03/24→03/30
·
Other
Elevator 3-4 - Finishing Cab Finished
ELV-560 Elevator 3-4 - Finishing Cab Finished Elevator 3-4
-
03/24→03/30
·
Other
Elevator 5-6 - Finishing Cab Finished
ELV-650 Elevator 5-6 - Finishing Cab Finished Elevator 5-6
-
03/24→04/02
12A
Fire/Sprinkler
Fire Stopping/Labeling
12A-F-N1-1070 Floor 12A - Fire Stopping/Labeling Floor 12 A East Final Finishes
-
03/24→04/02
13
HVAC/Mechanical
HVAC Drops & Diffusers in Soffit
13B-F-N2-110 Floor 13 - HVAC Drops & Diffusers in Soffit Floor 13 A Overhead Roughs
-
03/24→04/02
13
Electrical
Light Fixtures in Soffit
13B-F-N2-120 Floor 13 - Light Fixtures in Soffit Floor 13 A Overhead Roughs
-
03/24→03/26
3
Other
CEP Floor 3 - Construction Clean
PN-3-3000 CEP Floor 3 - Construction Clean CEP 3rd Flr Clean & Punch-Out
-
Wed 03/24
3
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 3B
COM3-320 3rd Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 3B Floor 3 Testing/Commissioning/Life Safety
-
03/24→03/30
3C
HVAC/Mechanical
3rd Floor 3C - Test & Balance (AHU 3-1)
COM3-3075 3rd Floor 3C - Test & Balance (AHU 3-1) Floor 3 Testing/Commissioning/Life Safety
-
03/24→03/25
6
HVAC/Mechanical
Start-up Check Out - AHU 4-4
AHU4-4-1050 Start-up Check Out - AHU 4-4 6th Floor AHU 4-4
-
03/24→03/25
7
Other
Floor 7 N7501 - Energize Power to Rack Receptacles
TEL-7-350 Floor 7 N7501 - Energize Power to Rack Receptacles Telecom Room Lv-7 N7501
-
03/24→03/30
7
Data
Floor 7 N7504 - Integrate & Test I. T. Systems
TEL-7-300 Floor 7 N7504 - Integrate & Test I. T. Systems Telecom Room Lv-7 N7504
-
03/24→03/25
8
Electrical
Floor 8 N8505 - Energize Electrical Room Panels
ELC-8-410 Floor 8 N8505 - Energize Electrical Room Panels Electrical Room Lv-8 N8505
-
03/25→03/31
1
Data
N1503 - Load Rack I. T. Equipment
TEL-1-200 Floor 1 - N1503 - Load Rack I. T. Equipment Telecom Room Lv-1 N1503
-
03/25→04/14
1B
Electrical
Electrical Trim At Columns
SC1B-N1-IR-400 Floor 1B - Electrical Trim At Columns Floor 1B SC 1.N2 Overhead & Finishes
-
Thu 03/25
3
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 3C
COM3-420 3rd Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 3C Floor 3 Testing/Commissioning/Life Safety
-
03/26→04/08
·
Other
South - Remove Access Platform
SWW-200 South - Remove Access Platform South Window Washing Support Steel / Equipment
-
Fri 03/26
1
Inspections/QC
Pre-Test Flows & Tampers
COM1-180 1st Floor - Pre-Test Flows & Tampers Floor 1 Testing/Commissioning/Life Safety
-
03/26→03/29
12B
Drywall/Framing
Framing Inspections
12B-F-N2-1030 Floor 12B - Framing Inspections Floor 12 B West Framing & Interior Roughs
-
03/26→04/01
1A
Flooring/Finishes
Final Paint
SC1A-N2-F-370 Floor 1A - Final Paint Floor 1A SC 1.N1 Final Finishes
-
Fri 03/26
3
Inspections/QC
Final Test Flows & Tampers
COM3-390 3rd Floor - Final Test Flows & Tampers Floor 3 Testing/Commissioning/Life Safety
-
03/26→03/29
5
Data
Floor 5 N5501 - Clean I. T. Room
TEL-5-480 Floor 5 N5501 - Clean I. T. Room Telecom Room Lv-5 N5501
-
03/26→03/29
6
HVAC/Mechanical
Start-up Check Out - AHU 4-5
AHU4-5-1050 Start-up Check Out - AHU 4-5 6th Floor AHU 4-5
-
03/26→04/01
7
Data
Floor 7 N7501 - Integrate & Test I. T. Systems
TEL-7-330 Floor 7 N7501 - Integrate & Test I. T. Systems Telecom Room Lv-7 N7501
-
03/26→03/29
8
Electrical
Floor 8 N8502 - Energize Electrical Room Panels
ELC-8-390 Floor 8 N8502 - Energize Electrical Room Panels Electrical Room Lv-8 N8502
-
03/26→03/29
8
Other
Floor 8 N8504 - Energize Power to Rack Receptacles
TEL-8-350 Floor 8 N8504 - Energize Power to Rack Receptacles Telecom Room Lv-8 N8504
-
03/29→04/16
10
Inspections/QC
Floor 10 N10504 - Terminate & Test IT Systems Cabling
TEL-10-250 Floor 10 N10504 - Terminate & Test IT Systems Cabling Telecom Room Lv-10 N10504
-
03/29→04/02
1A
Ceilings
Install Balance of Ceiling Tile
SC1A-N2-F-430 Floor 1A - Install Balance of Ceiling Tile Floor 1A SC 1.N1 Final Finishes
-
03/29→04/16
3
Inspections/QC
CEP Floor 3 - Gilbane Functional/Pre-Inspections
PN-3-3050 CEP Floor 3 - Gilbane Functional/Pre-Inspections CEP 3rd Flr Clean & Punch-Out
-
03/29→04/02
3
Inspections/QC
Pre-Test Doors/Final Test Doors
COM3-330 3rd Floor - Pre-Test Doors/Final Test Doors Floor 3 Testing/Commissioning/Life Safety
-
03/29→03/30
3B
Inspections/QC
Owner Pre AHCA For Areas (A, B & C)
SC3B-N3-F-560 Floor 3B - Owner Pre AHCA For Areas (A, B & C) Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/29→04/23
4
Inspections/QC
Gilbane/Contractor Punch-list
4-P-1010 Floor 4 - Gilbane/Contractor Punch-list Floor-4 Clean & Punch-Out
-
03/29→04/09
4B
Inspections/QC
Load Equipment
SC4B-N3-F-570 Floor 4B - Load Equipment Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
03/29→04/02
4C
HVAC/Mechanical
4th Floor 4C - Test & Balance (AHU 4-1)
COM4-4065 4th Floor 4C - Test & Balance (AHU 4-1) Floor 4 Testing/Commissioning/Life Safety
-
03/29→04/02
9B
Other
Construction Clean
9B-F-N2-1350 Floor 9B - Construction Clean West 9B West Final Finishes
-
03/30→04/26
12B
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
12B-F-N2-1060 Floor 12B - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 12 B West Final Finishes
-
03/30→04/01
4
Inspections/QC
Pre-Test Fire Smoke Dampers
COM4-450 4th Floor - Pre-Test Fire Smoke Dampers Floor 4 Testing/Commissioning/Life Safety
-
03/30→04/05
5
Data
Floor 5 N5501 - Load Rack I. T. Equipment
TEL-5-490 Floor 5 N5501 - Load Rack I. T. Equipment Telecom Room Lv-5 N5501
-
03/30→03/31
6
HVAC/Mechanical
Start-up Check Out - AHU 5-1
AHU5-1-1050 Start-up Check Out - AHU 5-1 6th Floor AHU 5-1
-
03/30→03/31
8
Other
Floor 8 N8503 - Energize Power to Rack Receptacles
TEL-8-340 Floor 8 N8503 - Energize Power to Rack Receptacles Telecom Room Lv-8 N8503
-
03/30→04/05
9A
Inspections/QC
Stocking
9A-F-N1-1370 Floor 9A - Stocking Floor 9A East Final Finishes 9A
-
03/31→04/06
·
Other
Elevator 3-4 - Adjust & Inspect
ELV-540 Elevator 3-4 - Adjust & Inspect Elevator 3-4
-
03/31→04/06
·
Other
Elevator 5-6 - Adjust & Inspect
ELV-630 Elevator 5-6 - Adjust & Inspect Elevator 5-6
-
03/31→04/02
13
Ceilings
MEPF Inspections in Soffits
13B-F-N2-150 Floor 13 - MEPF Inspections in Soffits Floor 13 A Overhead Roughs
-
03/31→04/06
3B
Inspections/QC
Stocking
SC3B-N3-F-570 Floor 3B - Stocking Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
03/31→04/01
9
Data
Floor 9 N9501 - Clean I. T. Room
TEL-9-290 Floor 9 N9501 - Clean I. T. Room Telecom Room Lv-9 N9501
-
04/01→04/07
1
Data
N1503 - Integrate & Test I. T. Systems
TEL-1-210 Floor 1 - N1503 - Integrate & Test I. T. Systems Telecom Room Lv-1 N1503
-
04/01→04/05
10A
Ceilings
Install Balance of Ceiling Tile
10A-F-N1-1290 Floor 10A - Install Balance of Ceiling Tile Floor 10A East Final Finishes
-
04/01→04/12
12A
Flooring/Finishes
Paint Prime & First Coat
12A-F-N1-1090 Floor 12A - Paint Prime & First Coat Floor 12 A East Final Finishes
-
Thu 04/01
13
Data
N13505 - Install I. T. Rooms Doors
TEL-13-230 Floor 13 - N13505 - Install I. T. Rooms Doors Telecom Room Lv-13 N13505
-
04/01→04/02
6
HVAC/Mechanical
Start-up Check Out - AHU 5-2
AHU5-2-1050 Start-up Check Out - AHU 5-2 6th Floor AHU 5-2
-
04/01→04/07
8
Data
Floor 8 N8503 - Integrate & Test I. T. Systems
TEL-8-300 Floor 8 N8503 - Integrate & Test I. T. Systems Telecom Room Lv-8 N8503
-
04/01→04/07
8
Data
Floor 8 N8504 - Integrate & Test I. T. Systems
TEL-8-330 Floor 8 N8504 - Integrate & Test I. T. Systems Telecom Room Lv-8 N8504
-
04/02→04/07
1A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
SC1A-N2-F-320 Floor 1A - Building Specialties (incl. Curtain Track) Floor 1A SC 1.N1 Final Finishes
-
04/02→04/15
1A
Electrical
Electrical Wall Fixtures/Devices
SC1A-N2-F-380 Floor 1A - Electrical Wall Fixtures/Devices Floor 1A SC 1.N1 Final Finishes
-
04/02→04/15
1A
Plumbing
Med Gas Trim
SC1A-N2-F-520 Floor 1A - Med Gas Trim Floor 1A SC 1.N1 Final Finishes
-
04/02→04/13
1A
Flooring/Finishes
Signage
SC1A-N2-F-390 Floor 1A - Signage Floor 1A SC 1.N1 Final Finishes
-
04/02→04/05
4
Data
Complete Fire Alarm Pre-test Punch List Items
COM4-400 4th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 4 Testing/Commissioning/Life Safety
-
04/02→04/05
4
Inspections/QC
Test Fire Smoke Dampers
COM4-440 4th Floor - Test Fire Smoke Dampers Floor 4 Testing/Commissioning/Life Safety
-
04/02→04/22
7
Inspections/QC
Gilbane Functional/Pre-Inspections
P7-1050 Floor 7 - Gilbane Functional/Pre-Inspections Floor 7 Clean & Punch-Out
-
04/02→04/08
9
Data
Floor 9 N9501 - Load Rack I. T. Equipment
TEL-9-320 Floor 9 N9501 - Load Rack I. T. Equipment Telecom Room Lv-9 N9501
-
04/05→04/09
1
HVAC/Mechanical
Test & Balance (AHU 1-1)
COM1-1055 1st Floor - Test & Balance (AHU 1-1) Floor 1 Testing/Commissioning/Life Safety
-
04/05→04/06
3
Inspections/QC
Final Test Doors
COM3-400 3rd Floor- Final Test Doors Floor 3 Testing/Commissioning/Life Safety
-
04/05→04/09
4B
HVAC/Mechanical
4th Floor 4B - Test & Balance (AHU 4-4,4-5)
COM4-4075 4th Floor 4B - Test & Balance (AHU 4-4,4-5) Floor 4 Testing/Commissioning/Life Safety
-
04/05→04/09
5
HVAC/Mechanical
5th 5A Floor - Test & Balance (AHU 5-2, 5-3)
COM5-5055 5th 5A Floor - Test & Balance (AHU 5-2, 5-3) Floor 5 Testing/Commissioning/Life Safety
-
04/05→04/06
6
HVAC/Mechanical
Start-up Check Out - AHU 5-3
AHU5-3-1050 Start-up Check Out - AHU 5-3 6th Floor AHU 5-3
-
04/05→04/30
9
Inspections/QC
Gilbane/Contractor Punch-list
9-P-1010 Floor 9 - Gilbane/Contractor Punch-list Floor 9 Clean & Punch-Out
-
04/05→04/16
9B
Inspections/QC
Load Equipment
9B-F-N2-1360 Floor 9B - Load Equipment West 9B West Final Finishes
-
04/06→04/12
10A
Other
Construction Clean
10A-F-N1-1330 Floor 10A - Construction Clean Floor 10A East Final Finishes
-
Tue 04/06
4
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 4A
COM4-410 4th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 4A Floor 4 Testing/Commissioning/Life Safety
-
04/06→04/12
5
Data
Floor 5 N5501 - Integrate & Test I. T. Systems
TEL-5-500 Floor 5 N5501 - Integrate & Test I. T. Systems Telecom Room Lv-5 N5501
-
04/06→04/12
9A
Other
Final Clean
9A-F-N1-1380 Floor 9A - Final Clean Floor 9A East Final Finishes 9A
-
04/07→04/13
3B
Other
Final Clean
SC3B-N3-F-580 Floor 3B - Final Clean Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
Wed 04/07
4
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 4B
COM4-420 4th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 4B Floor 4 Testing/Commissioning/Life Safety
-
04/07→04/08
6
HVAC/Mechanical
Start-up Check Out - AHU 5-4
AHU5-4-1050 Start-up Check Out - AHU 5-4 6th Floor AHU 5-4
-
Thu 04/08
4
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 47C
COM4-510 4th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 47C Floor 4 Testing/Commissioning/Life Safety
-
04/08→05/05
5
Inspections/QC
Gilbane/Contractor Punch-list
5-1500 Floor 5 - Gilbane/Contractor Punch-list Floor 5 Clean & Punch-Out
-
04/09→05/06
13
Drywall/Framing
Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits
13B-F-N2-160 Floor 13 - Batt Insulation & Hang Drywall Bottom - Walls, Ceilings, Soffits Floor 13 A Final Finishes
-
Fri 04/09
4
Inspections/QC
Final Test Flows & Tampers
COM4-490 4th Floor - Final Test Flows & Tampers Floor 4 Testing/Commissioning/Life Safety
-
04/09→04/12
6
HVAC/Mechanical
Start-up Check Out - AHU 5-5
AHU5-5-1050 Start-up Check Out - AHU 5-5 6th Floor AHU 5-5
-
04/09→04/15
9
Data
Floor 9 N9501 - Integrate & Test I. T. Systems
TEL-9-330 Floor 9 N9501 - Integrate & Test I. T. Systems Telecom Room Lv-9 N9501
-
04/12→04/16
·
Inspections/QC
Bridge - 100% AHCA Inspection
BRIDGE-490 Bridge - 100% AHCA Inspection New Bridge
-
04/12→04/14
1
Inspections/QC
Pre-Test Fire Smoke Dampers
COM1-150 1st Floor - Pre-Test Fire Smoke Dampers Floor 1 Testing/Commissioning/Life Safety
-
04/12→04/30
3
Inspections/QC
Gilbane/Contractor Punch-list
3-P-1010 Floor 3 - Gilbane/Contractor Punch-list Floor-3 Clean & Punch-Out
-
04/12→04/16
4
Inspections/QC
Pre-Test Doors/Final Test Doors
COM4-430 4th Floor - Pre-Test Doors/Final Test Doors Floor 4 Testing/Commissioning/Life Safety
-
04/12→04/13
4B
Inspections/QC
Owner Pre AHCA
SC4B-N3-F-580 Floor 4B - Owner Pre AHCA Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
04/13→04/26
10A
Inspections/QC
Load Equipment
10A-F-N1-1350 Floor 10A - Load Equipment Floor 10A East Final Finishes
-
04/13→04/26
12A
Electrical
Electrical Wall Fixtures/Devices
12A-F-N1-1310 Floor 12A - Electrical Wall Fixtures/Devices Floor 12 A East Final Finishes
-
04/13→04/26
12A
Ceilings
Install Ceiling Grid
12A-F-N1-1100 Floor 12A - Install Ceiling Grid Floor 12 A East Final Finishes
-
04/13→04/19
5
HVAC/Mechanical
5th 5B Floor - Test & Balance (AHU - 5-4,5-5)
COM5-5065 5th 5B Floor - Test & Balance (AHU - 5-4,5-5) Floor 5 Testing/Commissioning/Life Safety
-
04/13→04/15
5
Inspections/QC
Pre-Test Fire Smoke Dampers
COM5-550 5th Floor - Pre-Test Fire Smoke Dampers Floor 5 Testing/Commissioning/Life Safety
-
04/13→04/15
5
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 5A
COM5-560 5th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 5A Floor 5 Testing/Commissioning/Life Safety
-
04/13→04/14
6
HVAC/Mechanical
Start-up Check Out - AHU 6-1
AHU6-1-1050 Start-up Check Out - AHU 6-1 6th Floor AHU 6-1
-
04/14→05/11
2
Inspections/QC
Gilbane/Contractor Punch-list
2-P-1010 Floor 2 - Gilbane/Contractor Punch-list Floor 2 Clean & Punch-Out
-
04/14→04/20
3B
Inspections/QC
100% AHCA For Areas (A, B & C)
SC3B-N3-F-590 Floor 3B - 100% AHCA For Areas (A, B & C) Floor 3B SC 3.N3 (7 OR's) Framing & Interior Roughs
-
04/14→04/20
4B
Inspections/QC
Stocking
SC4B-N3-F-590 Floor 4B - Stocking Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
04/15→04/16
1
Data
Complete Fire Alarm Pre-test Punch List Items
COM1-100 1st Floor - Complete Fire Alarm Pre-test Punch List Items Floor 1 Testing/Commissioning/Life Safety
-
04/15→05/10
1
Inspections/QC
Gilbane Functional/Pre-Inspections
1-P-1050 Floor 1 - Gilbane Functional/Pre-Inspections Lv-1 Clean & Punch-Out
-
04/15→04/16
1
Inspections/QC
Test Fire Smoke Dampers
COM1-140 1st Floor - Test Fire Smoke Dampers Floor 1 Testing/Commissioning/Life Safety
-
04/15→04/28
12A
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
12A-F-N1-1120 Floor 12A - HVAC Drops & Diffusers/Grid Floor 12 A East Final Finishes
-
04/15→05/05
6
Inspections/QC
Gilbane Functional/Pre-Inspections
6-P-1000 Floor 6 - Gilbane Functional/Pre-Inspections Floor 6 Clean & Punch-Out
-
04/15→04/16
6
HVAC/Mechanical
Start-up Check Out - AHU 6-3
AHU6-3-1050 Start-up Check Out - AHU 6-3 6th Floor AHU 6-3
-
04/16→04/22
1A
Other
Construction Clean
SC1A-N2-F-440 Floor 1A - Construction Clean Floor 1A SC 1.N1 Final Finishes
-
04/16→04/20
5
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 5B
COM5-570 5th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 5B Floor 5 Testing/Commissioning/Life Safety
-
Mon 04/19
1
Inspections/QC
Final Test Flows & Tampers
COM1-190 1st Floor - Final Test Flows & Tampers Floor 1 Testing/Commissioning/Life Safety
-
Mon 04/19
1
Inspections/QC
Final Test Horns, Strobes, Pulls 1A
COM1-110 1st Floor - Final Test Horns, Strobes, Pulls 1A Floor 1 Testing/Commissioning/Life Safety
-
04/19→05/07
10
Inspections/QC
Floor 10 N10501 - Terminate & Test IT Systems Cabling
TEL-10-280 Floor 10 N10501 - Terminate & Test IT Systems Cabling Telecom Room Lv-10 N10501
-
04/19→04/20
10
Data
Floor 10 N10504 - Clean I. T. Room
TEL-10-270 Floor 10 N10504 - Clean I. T. Room Telecom Room Lv-10 N10504
-
04/19→04/28
12B
Fire/Sprinkler
Fire Stopping/Labeling
12B-F-N2-1070 Floor 12B - Fire Stopping/Labeling Floor 12 B West Final Finishes
-
04/19→04/30
3
Inspections/QC
CEP Floor 3 - Gilbane/Contractor Punch-list
PN-3-3010 CEP Floor 3 - Gilbane/Contractor Punch-list CEP 3rd Flr Clean & Punch-Out
-
Mon 04/19
4
Inspections/QC
Final Test Doors
COM4-500 4th Floor - Final Test Doors Floor 4 Testing/Commissioning/Life Safety
-
04/19→04/21
6
Inspections/QC
Pre-Test Fire Smoke Dampers
COM6-650 6th Floor - Pre-Test Fire Smoke Dampers Floor 6 Testing/Commissioning/Life Safety
-
04/19→04/20
9
HVAC/Mechanical
Start-up Check Out (AHU 9-1)
9-M-170 Start-up Check Out (AHU 9-1) Floor 9 Mechanical Space N9503
-
04/19→04/20
9B
Inspections/QC
Owner Pre AHCA For Areas (A & B)
9B-F-N2-1370 Floor 9B - Owner Pre AHCA For Areas (A & B) West 9B West Final Finishes
-
Tue 04/20
1
Inspections/QC
Final Test Horns, Strobes, Pulls 1B
COM1-120 1st Floor - Final Test Horns, Strobes, Pulls 1B Floor 1 Testing/Commissioning/Life Safety
-
04/20→05/03
12B
Drywall/Framing
Finish Drywall
12B-F-N2-1080 Floor 12B - Finish Drywall Floor 12 B West Final Finishes
-
04/20→04/26
5
HVAC/Mechanical
5th 5C Floor - Test & Balance (AHU 5-1)
COM5-5075 5th 5C Floor - Test & Balance (AHU 5-1) Floor 5 Testing/Commissioning/Life Safety
-
04/21→04/27
10
Data
Floor 10 N10504 - Load Rack I. T. Equipment
TEL-10-300 Floor 10 N10504 - Load Rack I. T. Equipment Telecom Room Lv-10 N10504
-
04/21→04/22
10
HVAC/Mechanical
Start-up Check Out (AHU 10-1)
10-M-140 Start-up Check Out (AHU 10-1) Floor 10 Mechanical Space N10503
-
04/21→04/28
12A
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
12A-F-N1-1140 Floor 12A - Drop Borders & Trade Cuts Ceiling Tiles Floor 12 A East Final Finishes
-
04/21→05/18
13
Drywall/Framing
Finish Drywall
13B-F-N2-180 Floor 13 - Finish Drywall Floor 13 A Final Finishes
-
04/21→04/27
4B
Other
Final Clean
SC4B-N3-F-600 Floor 4B - Final Clean Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
04/21→04/22
5
Data
Complete Fire Alarm Pre-test Punch List Items
COM5-500 5th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 5 Testing/Commissioning/Life Safety
-
04/21→04/23
5
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 5C
COM5-620 5th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 5C Floor 5 Testing/Commissioning/Life Safety
-
04/21→04/22
5
Inspections/QC
Test Fire Smoke Dampers
COM5-540 5th Floor - Test Fire Smoke Dampers Floor 5 Testing/Commissioning/Life Safety
-
04/21→04/23
9
Inspections/QC
Pre-Test Fire Smoke Dampers
COM9-950 9th Floor - Pre-Test Fire Smoke Dampers Floor 9 Testing/Commissioning/Life Safety
-
04/21→04/23
9
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 9A
COM9-960 9th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 9A Floor 9 Testing/Commissioning/Life Safety
-
04/21→04/27
9
HVAC/Mechanical
Test & Balance (AHU 9-1)
COM9-9055 9th Floor - Test & Balance (AHU 9-1) Floor 9 Testing/Commissioning/Life Safety
-
04/21→04/27
9B
Inspections/QC
Stocking
9B-F-N2-1380 Floor 9B - Stocking West 9B West Final Finishes
-
04/22→04/23
6
Data
Complete Fire Alarm Pre-test Punch List Items
COM6-600 6th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 6 Testing/Commissioning/Life Safety
-
04/22→04/23
6
Inspections/QC
Test Fire Smoke Dampers
COM6-640 6th Floor - Test Fire Smoke Dampers Floor 6 Testing/Commissioning/Life Safety
-
04/23→04/27
10
Inspections/QC
Pre-Test Fire Smoke Dampers
COM10-1050 10th Floor - Pre-Test Fire Smoke Dampers Floor 10 Testing/Commissioning/Life Safety
-
04/23→04/27
10
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 10A
COM10-1060 10th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 10A Floor 10 Testing/Commissioning/Life Safety
-
04/23→04/29
10
HVAC/Mechanical
Test & Balance (AHU 10-1)
COM10-1055 10th Floor - Test & Balance (AHU 10-1) Floor 10 Testing/Commissioning/Life Safety
-
04/23→05/20
11
Inspections/QC
Gilbane Functional/Pre-Inspections
11-P-1050 Floor 11 - Gilbane Functional/Pre-Inspections Floor 11 Clean & Punch-Out
-
04/23→04/26
11
HVAC/Mechanical
Start-up Check Out (AHU 11-1)
11-M-140 Start-up Check Out (AHU 11-1) Floor 11 Mechanical Space N11503
-
04/23→05/06
1A
Inspections/QC
Load Equipment
SC1A-N2-F-460 Floor 1A - Load Equipment Floor 1A SC 1.N1 Final Finishes
-
04/23→05/20
7
Inspections/QC
Gilbane/Contractor Punch-list
P7-1010 Floor 7 - Gilbane/Contractor Punch-list Floor 7 Clean & Punch-Out
-
04/26→04/28
12
Other
Temporary Cooling Floor 12
TEMP-12 Temporary Cooling Floor 12 Temporary Cooling
-
04/26→05/21
4
Inspections/QC
Gilbane Functional/Pre-Inspections
4-P-1050 Floor 4 - Gilbane Functional/Pre-Inspections Floor-4 Clean & Punch-Out
-
Mon 04/26
5
Inspections/QC
Pre-Test Flows & Tampers
COM5-580 5th Floor - Pre-Test Flows & Tampers Floor 5 Testing/Commissioning/Life Safety
-
Mon 04/26
6
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 6A
COM6-610 6th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 6A Floor 6 Testing/Commissioning/Life Safety
-
04/26→04/28
9
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 9B
COM9-970 9th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 9B Floor 9 Testing/Commissioning/Life Safety
-
04/27→05/03
10A
Inspections/QC
Stocking
10A-F-N1-1370 Floor 10A - Stocking Floor 10A East Final Finishes
-
04/27→05/03
11
HVAC/Mechanical
Test & Balance (AHU 11-1)
COM11-1155 11th Floor - Test & Balance (AHU 11-1) Floor 11 Testing/Commissioning/Life Safety
-
04/27→04/28
12
HVAC/Mechanical
Start-up Check Out (AHU 12-1)
12-M-140 Start-up Check Out (AHU 12-1) Floor 12 B Mechanical Space N12503
-
04/27→05/17
12A
Electrical
Light Fixtures in Grid
12A-F-N1-1150 Floor 12A - Light Fixtures in Grid Floor 12 A East Final Finishes
-
04/27→05/10
12A
Electrical
Remove Temp Light Fixtures
12A-F-N1-1125 Floor 12A - Remove Temp Light Fixtures Floor 12 A East Final Finishes
-
04/27→05/06
12B
Flooring/Finishes
Paint Prime & First Coat
12B-F-N2-1090 Floor 12B - Paint Prime & First Coat Floor 12 B West Final Finishes
-
Tue 04/27
5
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 5A
COM5-510 5th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 5A Floor 5 Testing/Commissioning/Life Safety
-
Tue 04/27
6
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 6B
COM6-620 6th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 6B Floor 6 Testing/Commissioning/Life Safety
-
04/28→05/04
10
Data
Floor 10 N10504 - Integrate & Test I. T. Systems
TEL-10-310 Floor 10 N10504 - Integrate & Test I. T. Systems Telecom Room Lv-10 N10504
-
04/28→04/30
10
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 10B
COM10-1070 10th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 10B Floor 10 Testing/Commissioning/Life Safety
-
04/28→04/30
12A
Fire/Sprinkler
Sprinkler Drops/Heads
12A-F-N1-1160 Floor 12A - Sprinkler Drops/Heads Floor 12 A East Final Finishes
-
04/28→05/04
4B
Inspections/QC
100% AHCA
SC4B-N3-F-610 Floor 4B - 100% AHCA Floor 4B SC 4.N3 (7 OR's) Framing & Interior Roughs
-
Wed 04/28
5
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 5B
COM5-520 5th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 5B Floor 5 Testing/Commissioning/Life Safety
-
04/28→05/11
5B
Plumbing
Install Med Gas Trim @ Booms
SC5B-N3-F-500 Floor 5B - Install Med Gas Trim @ Booms Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
Wed 04/28
6
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 6C
COM6-710 6th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 6C Floor 6 Testing/Commissioning/Life Safety
-
04/28→05/04
9B
Other
Final Clean
9B-F-N2-1390 Floor 9B - Final Clean West 9B West Final Finishes
-
04/29→05/05
12
HVAC/Mechanical
Test & Balance (AHU 12-1)
COM12-1255 12th Floor - Test & Balance (AHU 12-1) Floor 12 Testing/Commissioning/Life Safety
-
04/29→04/30
12A
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
12A-F-N1-1520 Floor 12A - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 12 A East Final Finishes
-
04/29→04/30
13A
HVAC/Mechanical
N13506 - Start-up Check Out (AHU 13-2)
13-M-210 Floor 13A - N13506 - Start-up Check Out (AHU 13-2) Floor 13 A Mechanical Space N13506
-
Thu 04/29
5
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 5C
COM5-610 5th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 5C Floor 5 Testing/Commissioning/Life Safety
-
Thu 04/29
6
Inspections/QC
Final Test Flows & Tampers
COM6-690 6th Floor - Final Test Flows & Tampers Floor 6 Testing/Commissioning/Life Safety
-
04/29→04/30
9
Data
Complete Fire Alarm Pre-test Punch List Items
COM9-900 9th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 9 Testing/Commissioning/Life Safety
-
Thu 04/29
9
Inspections/QC
Pre-Test Flows & Tampers
COM9-980 9th Floor - Pre-Test Flows & Tampers Floor 9 Testing/Commissioning/Life Safety
-
04/29→04/30
9
Inspections/QC
Test Fire Smoke Dampers
COM9-940 9th Floor - Test Fire Smoke Dampers Floor 9 Testing/Commissioning/Life Safety
-
Fri 04/30
5
Inspections/QC
Final Test Flows & Tampers
COM5-590 5th Floor - Final Test Flows & Tampers Floor 5 Testing/Commissioning/Life Safety
-
04/30→05/06
6
Inspections/QC
Pre-Test Doors/Final Test Doors
COM6-630 6th Floor - Pre-Test Doors/Final Test Doors Floor 6 Testing/Commissioning/Life Safety
-
05/03→05/04
10
Data
Complete Fire Alarm Pre-test Punch List Items
COM10-1000 10th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 10 Testing/Commissioning/Life Safety
-
Mon 05/03
10
Inspections/QC
Pre-Test Flows & Tampers
COM10-1080 10th Floor - Pre-Test Flows & Tampers Floor 10 Testing/Commissioning/Life Safety
-
05/03→05/04
10
Inspections/QC
Test Fire Smoke Dampers
COM10-1040 10th Floor - Test Fire Smoke Dampers Floor 10 Testing/Commissioning/Life Safety
-
05/03→05/14
12A
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
12A-F-N1-1190 Floor 12A - Flooring - SV Flooring + Cove Base` (FL-1) Floor 12 A East Final Finishes
-
05/03→05/04
13A
HVAC/Mechanical
N13503 - Start-up Check Out (AHU 13-1)
13-M-270 Floor 13A - N13503 - Start-up Check Out (AHU 13-1) Floor 13 A Mechanical Space N13503
-
05/03→05/05
3
Other
CEP Floor 3 - Final Clean
PN-3-3020 CEP Floor 3 - Final Clean CEP 3rd Flr Clean & Punch-Out
-
05/03→05/07
3
Inspections/QC
Owner/Design Team Punch List
3-P-1030 Floor 3 - Owner/Design Team Punch List Floor-3 Clean & Punch-Out
-
05/03→05/07
5
Inspections/QC
Pre-Test Doors/Final Test Doors
COM5-530 5th Floor - Pre-Test Doors/Final Test Doors Floor 5 Testing/Commissioning/Life Safety
-
Mon 05/03
9
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 9A
COM9-910 9th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 9A Floor 9 Testing/Commissioning/Life Safety
-
05/03→05/28
9
Inspections/QC
Gilbane Functional/Pre-Inspections
9-P-1050 Floor 9 - Gilbane Functional/Pre-Inspections Floor 9 Clean & Punch-Out
-
05/04→05/10
10A
Other
Final Clean
10A-F-N1-1380 Floor 10A - Final Clean Floor 10A East Final Finishes
-
Tue 05/04
9
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 9B
COM9-920 9th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 9B Floor 9 Testing/Commissioning/Life Safety
-
Wed 05/05
10
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 10A
COM10-1010 10th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 10A Floor 10 Testing/Commissioning/Life Safety
-
05/05→06/02
10
Inspections/QC
Gilbane Functional/Pre-Inspections
10-P-1050 Floor 10 - Gilbane Functional/Pre-Inspections Floor 10 Clean & Punch-Out
-
Wed 05/05
9
Inspections/QC
Final Test Flows & Tampers
COM9-990 9th Floor - Final Test Flows & Tampers Floor 9 Testing/Commissioning/Life Safety
-
Thu 05/06
10
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 10B
COM10-1020 10th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 10B Floor 10 Testing/Commissioning/Life Safety
-
05/06→06/03
3
Inspections/QC
CEP Floor 3 - Owner/Design Team Punch List
PN-3-3030 CEP Floor 3 - Owner/Design Team Punch List CEP 3rd Flr Clean & Punch-Out
-
05/06→06/03
5
Inspections/QC
Owner/Design Team Punch List
5-1520 Floor 5 - Owner/Design Team Punch List Floor 5 Clean & Punch-Out
-
05/06→06/03
6
Inspections/QC
Gilbane/Contractor Punch-list
6P-1010 Floor 6 - Gilbane/Contractor Punch-list Floor 6 Clean & Punch-Out
-
05/06→05/12
9
Inspections/QC
Pre-Test Doors/Final Test Doors
COM9-930 9th Floor - Pre-Test Doors/Final Test Doors Floor 9 Testing/Commissioning/Life Safety
-
Fri 05/07
10
Inspections/QC
Final Test Flows & Tampers
COM10-1090 10th Floor - Final Test Flows & Tampers Floor 10 Testing/Commissioning/Life Safety
-
05/07→05/20
12B
Ceilings
Install Ceiling Grid
12B-F-N2-1100 Floor 12B - Install Ceiling Grid Floor 12 B West Final Finishes
-
05/07→05/18
13
Fire/Sprinkler
Fire Stopping/Labeling
13B-F-N2-140 Floor 13 - Fire Stopping/Labeling Floor 13 A Final Finishes
-
05/07→05/10
1A
Inspections/QC
Owner Pre AHCA
SC1A-N2-F-470 Floor 1A - Owner Pre AHCA Floor 1A SC 1.N1 Final Finishes
-
Fri 05/07
6
Inspections/QC
Final Test Doors
COM6-700 6th Floor - Final Test Doors Floor 6 Testing/Commissioning/Life Safety
-
05/10→05/11
10
Data
Floor 10 N10501 - Clean I. T. Room
TEL-10-290 Floor 10 N10501 - Clean I. T. Room Telecom Room Lv-10 N10501
-
Mon 05/10
5
Inspections/QC
Final Test Doors
COM5-600 5th Floor - Final Test Doors Floor 5 Testing/Commissioning/Life Safety
-
05/10→05/14
5C
Inspections/QC
100% AHCA
SC5C-N1-F-560 Floor 5C - 100% AHCA Floor 5C SC 5.N1 Final Finishes
-
05/11→06/08
1
Inspections/QC
Gilbane/Contractor Punch-list
1-P-1010 Floor 1 - Gilbane/Contractor Punch-list Lv-1 Clean & Punch-Out
-
05/11→06/01
11
Inspections/QC
Floor 11 (N11504) - Terminate & Test IT Systems Cabling
TEL-11-250 Floor 11 (N11504) - Terminate & Test IT Systems Cabling Telecom Room Lv-11 N11504
-
05/11→05/13
11
Inspections/QC
Pre-Test Fire Smoke Dampers
COM11-1150 11th Floor - Pre-Test Fire Smoke Dampers Floor 11 Testing/Commissioning/Life Safety
-
05/11→05/13
11
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 11A
COM11-1160 11th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 11A Floor 11 Testing/Commissioning/Life Safety
-
05/11→05/20
12A
Data
All Low Voltage Devices In Grid
12A-F-N1-1170 Floor 12A - All Low Voltage Devices In Grid Floor 12 A East Final Finishes
-
05/11→05/17
1A
Inspections/QC
Stocking
SC1A-N2-F-480 Floor 1A - Stocking Floor 1A SC 1.N1 Final Finishes
-
05/12→05/18
10
Data
Floor 10 N10501 - Load Rack I. T. Equipment
TEL-10-320 Floor 10 N10501 - Load Rack I. T. Equipment Telecom Room Lv-10 N10501
-
05/12→06/09
2
Inspections/QC
Owner/Design Team Punch List
2-P-1030 Floor 2 - Owner/Design Team Punch List Floor 2 Clean & Punch-Out
-
05/12→05/25
5B
Data
Install Low-Voltage Trim @ Booms
SC5B-N3-F-520 Floor 5B - Install Low-Voltage Trim @ Booms Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
Thu 05/13
9
Inspections/QC
Final Test Doors
COM9-1000 9th Floor - Final Test Doors Floor 9 Testing/Commissioning/Life Safety
-
05/14→05/18
11
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 11B
COM11-1170 11th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 11B Floor 11 Testing/Commissioning/Life Safety
-
05/17→05/21
12A
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
12A-F-N1-1180 Floor 12A - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 12 A East Final Finishes
-
05/17→05/24
12B
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
12B-F-N2-1140 Floor 12B - Drop Borders & Trade Cuts Ceiling Tiles Floor 12 B West Final Finishes
-
05/17→05/21
6
Inspections/QC
100% AHCA
FL6-1160 6th Floor - 100% AHCA Foor 6 Walls - Mechanical & Electrical Rooms And Shell Space
-
05/18→05/24
12B
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
12B-F-N2-1120 Floor 12B - HVAC Drops & Diffusers/Grid Floor 12 B West Final Finishes
-
Tue 05/18
13
Milestone
Complete Drywall ◆
M670 Floor 13 - Complete Drywall Construction Milestones
-
05/18→05/24
1A
Other
Final Clean
SC1A-N2-F-490 Floor 1A - Final Clean Floor 1A SC 1.N1 Final Finishes
-
05/19→05/25
10
Data
Floor 10 N10501 - Integrate & Test I. T. Systems
TEL-10-330 Floor 10 N10501 - Integrate & Test I. T. Systems Telecom Room Lv-10 N10501
-
05/19→05/20
11
Data
Complete Fire Alarm Pre-test Punch List Items
COM11-1100 11th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 11 Testing/Commissioning/Life Safety
-
Wed 05/19
11
Inspections/QC
Pre-Test Flows & Tampers
COM11-1180 11th Floor - Pre-Test Flows & Tampers Floor 11 Testing/Commissioning/Life Safety
-
05/19→05/20
11
Inspections/QC
Test Fire Smoke Dampers
COM11-1140 11th Floor - Test Fire Smoke Dampers Floor 11 Testing/Commissioning/Life Safety
-
05/19→06/02
13
Flooring/Finishes
Paint Prime & First Coat
13B-F-N2-190 Floor 13 - Paint Prime & First Coat Floor 13 A Final Finishes
-
Fri 05/21
11
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 10A
COM11-1110 11th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 10A Floor 11 Testing/Commissioning/Life Safety
-
05/21→06/18
11
Inspections/QC
Gilbane/Contractor Punch-list
11-P-1010 Floor 11 - Gilbane/Contractor Punch-list Floor 11 Clean & Punch-Out
-
05/21→06/11
12B
Electrical
Light Fixtures in Grid
12B-F-N2-1150 Floor 12B - Light Fixtures in Grid Floor 12 B West Final Finishes
-
05/21→06/04
12B
Electrical
Remove Temp Light Fixtures
12B-F-N2-1125 Floor 12B - Remove Temp Light Fixtures Floor 12 B West Final Finishes
-
05/21→06/02
12B
Fire/Sprinkler
Sprinkler Drops/Heads
12B-F-N2-1160 Floor 12B - Sprinkler Drops/Heads Floor 12 B West Final Finishes
-
05/21→06/18
7
Inspections/QC
Owner/Design Team Punch List
P7-1030 Floor 7 - Owner/Design Team Punch List Floor 7 Clean & Punch-Out
-
Mon 05/24
11
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 10B
COM11-1120 11th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 10B Floor 11 Testing/Commissioning/Life Safety
-
05/24→06/03
12A
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
12A-F-N1-1200 Floor 12A - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 12 A East Final Finishes
-
05/24→06/21
4
Inspections/QC
Owner/Design Team Punch List
4-P-1030 Floor 4 - Owner/Design Team Punch List Floor-4 Clean & Punch-Out
-
05/24→05/28
7
Inspections/QC
100% AHCA
FL7-N1-580 Floor 7 - 100% AHCA Floor 07 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
Tue 05/25
11
Inspections/QC
Final Test Flows & Tampers
COM11-1190 11th Floor - Final Test Flows & Tampers Floor 11 Testing/Commissioning/Life Safety
-
05/25→06/04
12B
Data
All Low Voltage Devices In Grid
12B-F-N2-1170 Floor 12B - All Low Voltage Devices In Grid Floor 12 B West Final Finishes
-
05/25→05/26
12B
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
12B-F-N2-1410 Floor 12B - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 12 B West Final Finishes
-
05/26→06/02
10
Inspections/QC
Pre-Test Doors/Final Test Doors
COM10-1030 10th Floor - Pre-Test Doors/Final Test Doors Floor 10 Testing/Commissioning/Life Safety
-
05/26→06/01
11B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
11B-F-N1-1510 Floor 11B - Building Specialties (incl. Curtain Track) Floor 11B Final Finishes
-
05/26→06/02
11B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
11B-F-N1-1500 Floor 11B - Wall Crash Rails/Hand Rails/Corner Guards Floor 11B Final Finishes
-
05/26→06/09
5B
Electrical
Install Electrical Finish @ Booms
SC5B-N3-F-510 Floor 5B - Install Electrical Finish @ Booms Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
05/27→06/03
12B
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
12B-F-N2-1190 Floor 12B - Flooring - SV Flooring + Cove Base` (FL-1) Floor 12 B West Final Finishes
-
05/27→06/24
13
Ceilings
Install Ceiling Grid
13B-F-N2-200 Floor 13 - Install Ceiling Grid Floor 13 A Final Finishes
-
06/01→06/07
8
Inspections/QC
100% AHCA
FL8-N1-900 Floor 8 - 100% AHCA Floor 08 - Shell Floor (Future Inpatient Unit - 34 Beds)
-
06/01→06/28
9
Inspections/QC
Owner/Design Team Punch List
9-P-1030 Floor 9 - Owner/Design Team Punch List Floor 9 Clean & Punch-Out
-
06/02→06/22
11
Inspections/QC
Floor 11 (N11501) - Terminate & Test IT Systems Cabling
TEL-11-280 Floor 11 (N11501) - Terminate & Test IT Systems Cabling Telecom Room Lv-11 N11501
-
06/02→06/03
11
Data
Floor 11 (N11504) - Clean I. T. Room
TEL-11-270 Floor 11 (N11504) - Clean I. T. Room Telecom Room Lv-11 N11504
-
Thu 06/03
10
Inspections/QC
Final Test Doors
COM10-1100 10th Floor - Final Test Doors Floor 10 Testing/Commissioning/Life Safety
-
06/03→06/30
10
Inspections/QC
Gilbane/Contractor Punch-list
10-P-1010 Floor 10 - Gilbane/Contractor Punch-list Floor 10 Clean & Punch-Out
-
06/04→06/10
11
Data
Floor 11 (N11504) - Load Rack I. T. Equipment
TEL-11-300 Floor 11 (N11504) - Load Rack I. T. Equipment Telecom Room Lv-11 N11504
-
06/04→06/09
12A
Flooring/Finishes
Building Specialties (incl. Curtain Track)
12A-F-N1-1510 Floor 12A - Building Specialties (incl. Curtain Track) Floor 12 A East Final Finishes
-
06/04→06/17
12A
Flooring/Finishes
Ceramic Tile / Grout @ Sink
12A-F-N1-1250 Floor 12A - Ceramic Tile / Grout @ Sink Floor 12 A East Final Finishes
-
06/04→06/24
12A
Plumbing
Plumbing Trim Out
12A-F-N1-1260 Floor 12A - Plumbing Trim Out Floor 12 A East Final Finishes
-
06/04→06/10
12A
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
12A-F-N1-1220 Floor 12A - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 12 A East Final Finishes
-
06/04→06/10
12A
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
12A-F-N1-1500 Floor 12A - Wall Crash Rails/Hand Rails/Corner Guards Floor 12 A East Final Finishes
-
06/04→06/10
12B
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
12B-F-N2-1180 Floor 12B - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 12 B West Final Finishes
-
06/04→07/01
6
Inspections/QC
Owner/Design Team Punch List
6P-1030 Floor 6 - Owner/Design Team Punch List Floor 6 Clean & Punch-Out
-
06/07→06/09
12
Inspections/QC
Pre-Test Fire Smoke Dampers
COM12-1250 12th Floor - Pre-Test Fire Smoke Dampers Floor 12 Testing/Commissioning/Life Safety
-
06/07→06/09
12
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 12A
COM12-1260 12th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 12A Floor 12 Testing/Commissioning/Life Safety
-
06/08→06/28
13
HVAC/Mechanical
HVAC Drops & Diffusers/Grid
13B-F-N2-210 Floor 13 - HVAC Drops & Diffusers/Grid Floor 13 A Final Finishes
-
06/08→06/14
9B
Inspections/QC
100% AHCA For Areas (A & B)
9B-F-N2-1400 Floor 9B - 100% AHCA For Areas (A & B) West 9B West Final Finishes
-
06/09→07/07
1
Inspections/QC
Owner/Design Team Punch List
1-P-1040 Floor 1 - Owner/Design Team Punch List Lv-1 Clean & Punch-Out
-
06/10→06/14
12
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 12B
COM12-1270 12th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 12B Floor 12 Testing/Commissioning/Life Safety
-
06/10→06/16
5B
Other
Construction Clean
SC5B-N3-F-540 Floor 5B - Construction Clean Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
06/11→06/17
11
Data
Floor 11 (N11504) - Integrate & Test I. T. Systems
TEL-11-310 Floor 11 (N11504) - Integrate & Test I. T. Systems Telecom Room Lv-11 N11504
-
06/11→06/22
12B
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
12B-F-N2-1200 Floor 12B - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 12 B West Final Finishes
-
06/15→06/16
12
Data
Complete Fire Alarm Pre-test Punch List Items
COM12-1200 12th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 12 Testing/Commissioning/Life Safety
-
Tue 06/15
12
Inspections/QC
Pre-Test Flows & Tampers
COM12-1280 12th Floor - Pre-Test Flows & Tampers Floor 12 Testing/Commissioning/Life Safety
-
06/15→06/16
12
Inspections/QC
Test Fire Smoke Dampers
COM12-1240 12th Floor - Test Fire Smoke Dampers Floor 12 Testing/Commissioning/Life Safety
-
Thu 06/17
12
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 12A
COM12-1210 12th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 12A Floor 12 Testing/Commissioning/Life Safety
-
06/17→06/30
5B
Inspections/QC
Load Equipment
SC5B-N3-F-550 Floor 5B - Load Equipment Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
Fri 06/18
12
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 12B
COM12-1220 12th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 12B Floor 12 Testing/Commissioning/Life Safety
-
06/18→06/29
12A
Other
Div 10 Accessories
12A-F-N1-1290 Floor 12A - Div 10 Accessories Floor 12 A East Final Finishes
-
06/21→07/19
11
Inspections/QC
Complete Owner/Design Punch
12-P-1055120 Floor 11- Complete Owner/Design Punch Floor 11 Clean & Punch-Out
-
Mon 06/21
12
Inspections/QC
Final Test Flows & Tampers
COM12-1290 12th Floor - Final Test Flows & Tampers Floor 12 Testing/Commissioning/Life Safety
-
06/23→06/24
11
Data
Floor 11 (N11501) - Clean I. T. Room
TEL-11-290 Floor 11 (N11501) - Clean I. T. Room Telecom Room Lv-11 N11501
-
06/23→06/28
12B
Flooring/Finishes
Building Specialties (incl. Curtain Track)
12B-F-N1-1530 Floor 12B - Building Specialties (incl. Curtain Track) Floor 12 B West Final Finishes
-
06/23→07/07
12B
Flooring/Finishes
Ceramic Tile / Grout @ Sink
12B-F-N2-1250 Floor 12B - Ceramic Tile / Grout @ Sink Floor 12 B West Final Finishes
-
06/23→07/14
12B
Plumbing
Plumbing Trim Out
12B-F-N2-1260 Floor 12B - Plumbing Trim Out Floor 12 B West Final Finishes
-
06/23→06/29
12B
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
12B-F-N2-1220 Floor 12B - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 12 B West Final Finishes
-
06/23→06/29
12B
Flooring/Finishes
Wall Crash Rails/Hand Rails/Corner Guards
12B-F-N1-1520 Floor 12B - Wall Crash Rails/Hand Rails/Corner Guards Floor 12 B West Final Finishes
-
06/25→07/01
11
Data
Floor 11 (N11501) - Load Rack I. T. Equipment
TEL-11-320 Floor 11 (N11501) - Load Rack I. T. Equipment Telecom Room Lv-11 N11501
-
06/25→07/01
12A
Inspections/QC
Final OH MEPF Inspections
12A-F-N1-1270 Floor 12A - Final OH MEPF Inspections Floor 12 A East Final Finishes
-
06/25→06/28
13
Flooring/Finishes
Casework - Lower Base (For SV Flooring)` (CW-1)
13B-F-N2-300 Floor 13 - Casework - Lower Base (For SV Flooring)` (CW-1) Floor 13 A Final Finishes
-
06/25→07/09
13
Flooring/Finishes
Doors & Hardware
13B-F-N2-290 Floor 13 - Doors & Hardware Floor 13 A Final Finishes
-
06/25→07/07
13
Ceilings
Drop Borders & Trade Cuts Ceiling Tiles
13B-F-N2-230 Floor 13 - Drop Borders & Trade Cuts Ceiling Tiles Floor 13 A Final Finishes
-
06/25→07/16
13
Electrical
Light Fixtures in Grid
13B-F-N2-240 Floor 13 - Light Fixtures in Grid Floor 13 A Final Finishes
-
06/25→07/07
13
Fire/Sprinkler
Sprinkler Drops/Heads
13B-F-N2-260 Floor 13 - Sprinkler Drops/Heads Floor 13 A Final Finishes
-
06/28→07/02
12B
Inspections/QC
AHCA 80% Inspection For Areas (A & B)
12B-F-N2-1130 Floor 12B - AHCA 80% Inspection For Areas (A & B) Floor 12 B West Final Finishes
-
06/29→07/20
13
Flooring/Finishes
Ceramic Tile / Grout
13B-F-N2-330 Floor 13 - Ceramic Tile / Grout Floor 13 A Final Finishes
-
06/29→07/09
13
Flooring/Finishes
Flooring - SV Flooring + Cove Base` (FL-1)
13B-F-N2-280 Floor 13 - Flooring - SV Flooring + Cove Base` (FL-1) Floor 13 A Final Finishes
-
06/29→07/20
13
Plumbing
Plumbing Trim Out
13B-F-N2-340 Floor 13 - Plumbing Trim Out Floor 13 A Final Finishes
-
06/29→07/06
13
HVAC/Mechanical
Test & Balance (AHU 13-2)
COM13-1355 13th Floor - Test & Balance (AHU 13-2) Floor 13 Testing/Commissioning/Life Safety
-
06/30→07/14
12A
Flooring/Finishes
Doors & Hardware
12A-F-N1-1210 Floor 12A - Doors & Hardware Floor 12 A East Final Finishes
-
06/30→07/12
12A
Flooring/Finishes
Set Barn Doors At Patient Rooms
12A-F-N1-1240 Floor 12A - Set Barn Doors At Patient Rooms Floor 12 A East Final Finishes
-
06/30→07/12
12B
Flooring/Finishes
Doors & Hardware
12B-F-N2-1210 Floor 12B - Doors & Hardware Floor 12 B West Final Finishes
-
07/01→07/29
10
Inspections/QC
Owner/Design Team Punch List
10-P-1030 Floor 10 - Owner/Design Team Punch List Floor 10 Clean & Punch-Out
-
07/01→07/02
5B
Inspections/QC
Owner Pre AHCA
SC5B-N3-F-560 Floor 5B - Owner Pre AHCA Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/02→07/09
11
Data
Floor 11 (N11501) - Integrate & Test I. T. Systems
TEL-11-330 Floor 11 (N11501) - Integrate & Test I. T. Systems Telecom Room Lv-11 N11501
-
07/06→07/15
12A
Ceilings
Install Balance of Ceiling Tile
12A-F-N1-1300 Floor 12A - Install Balance of Ceiling Tile Floor 12 A East Final Finishes
-
07/06→07/12
5B
Inspections/QC
Stocking
SC5B-N3-F-570 Floor 5B - Stocking Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/08→07/28
13
Data
All Low Voltage Devices In Grid At Patient Rooms
13B-F-N2-550 Floor 13 - All Low Voltage Devices In Grid At Patient Rooms Floor 13 A Final Finishes
-
07/12→07/16
11
Inspections/QC
Pre-Test Doors/Final Test Doors
COM11-1130 11th Floor - Pre-Test Doors/Final Test Doors Floor 11 Testing/Commissioning/Life Safety
-
07/12→07/16
13
Flooring/Finishes
Flooring - All Other (LVT, Etc.)` (FL-2)
13B-F-N2-530 Floor 13 - Flooring - All Other (LVT, Etc.)` (FL-2) Floor 13 A Final Finishes
-
07/12→07/16
13
HVAC/Mechanical
Test & Balance (AHU 13-1)
COM13-1365 13th Floor - Test & Balance (AHU 13-1) Floor 13 Testing/Commissioning/Life Safety
-
07/13→07/16
12A
Flooring/Finishes
Final Paint & Wallcovering
12A-F-N1-1280 Floor 12A - Final Paint & Wallcovering Floor 12 A East Final Finishes
-
07/13→07/19
5B
Other
Final Clean
SC5B-N3-F-580 Floor 5B - Final Clean Floor 5B SC 5.N3 (7 OR's) Framing & Interior Roughs
-
07/15→07/26
12B
Other
Div 10 Accessories
12B-F-N2-1290 Floor 12B - Div 10 Accessories Floor 12 B West Final Finishes
-
07/15→07/21
12B
Inspections/QC
Final OH MEPF Inspections
12B-F-N2-1270 Floor 12B - Final OH MEPF Inspections Floor 12 B West Final Finishes
-
Mon 07/19
11
Inspections/QC
Final Test Doors
COM11-1200 11th Floor - Final Test Doors Floor 11 Testing/Commissioning/Life Safety
-
07/19→07/28
12A
Flooring/Finishes
Install Roller Shades
12A-F-N1-1320 Floor 12A - Install Roller Shades Floor 12 A East Final Finishes
-
07/19→07/28
12A
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
12A-F-N1-1110 Floor 12A - Install Special Wall Finishes (incl. Wall Protection) Floor 12 A East Final Finishes
-
07/19→07/30
12A
Flooring/Finishes
Signage
12A-F-N1-1330 Floor 12A - Signage Floor 12 A East Final Finishes
-
07/19→07/28
13
Flooring/Finishes
Casework/Countertops - All Other (After LVT, Etc.)` (CW-2)
13B-F-N2-560 Floor 13 - Casework/Countertops - All Other (After LVT, Etc.)` (CW-2) Floor 13 A Final Finishes
-
07/21→08/03
13
Other
Div 10 Accessories
13B-F-N2-370 Floor 13 - Div 10 Accessories Floor 13 A Final Finishes
-
07/21→07/27
13
Inspections/QC
Final OH MEPF Inspections
13B-F-N2-350 Floor 13 - Final OH MEPF Inspections Floor 13 A Final Finishes
-
07/22→07/26
12B
Ceilings
Install Balance of Ceiling Tile
12B-F-N2-1300 Floor 12B - Install Balance of Ceiling Tile Floor 12 B West Final Finishes
-
07/27→08/09
12B
Flooring/Finishes
Final Paint & Wallcovering
12B-F-N2-1280 Floor 12B - Final Paint & Wallcovering Floor 12 B West Final Finishes
-
07/29→08/02
13
Inspections/QC
Pre-Test Fire Smoke Dampers
COM13-1350 13th Floor - Pre-Test Fire Smoke Dampers Floor 13 Testing/Commissioning/Life Safety
-
07/29→08/02
13
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 13A
COM13-1360 13th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 13A Floor 13 Testing/Commissioning/Life Safety
-
07/29→08/04
13
Flooring/Finishes
Wall Base (After All Flooring + Casework Tops)` (FL-3)
13B-F-N2-531 Floor 13 - Wall Base (After All Flooring + Casework Tops)` (FL-3) Floor 13 A Final Finishes
-
08/02→08/06
12A
Other
Construction Clean
12A-F-N1-1340 Floor 12A - Construction Clean Floor 12 A East Final Finishes
-
08/03→08/16
12B
Electrical
Electrical Wall Fixtures/Devices
12B-F-N2-1310 Floor 12B - Electrical Wall Fixtures/Devices Floor 12 B West Final Finishes
-
08/03→08/05
13
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 13B North
COM13-1370 13th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 13B North Floor 13 Testing/Commissioning/Life Safety
-
08/05→08/18
13
Flooring/Finishes
Final Paint & Wallcovering
13B-F-N2-360 Floor 13 - Final Paint & Wallcovering Floor 13 A Final Finishes
-
08/06→08/09
13
Data
Complete Fire Alarm Pre-test Punch List Items
COM13-1300 13th Floor - Complete Fire Alarm Pre-test Punch List Items Floor 13 Testing/Commissioning/Life Safety
-
08/06→08/10
13
Data
Pre-Test Horns, Strobes, Pulls, Fire Alarm 13B South
COM13-1420 13th Floor - Pre-Test Horns, Strobes, Pulls, Fire Alarm 13B South Floor 13 Testing/Commissioning/Life Safety
-
08/06→08/09
13
Inspections/QC
Test Fire Smoke Dampers
COM13-1340 13th Floor - Test Fire Smoke Dampers Floor 13 Testing/Commissioning/Life Safety
-
08/09→08/20
12A
Inspections/QC
Load Equipment
12A-F-N1-1350 Floor 12A - Load Equipment Floor 12 A East Final Finishes
-
08/09→08/30
13
Inspections/QC
AHCA 80% Inspection
13B-F-N2-220 Floor 13 - AHCA 80% Inspection Floor 13 A Final Finishes
-
08/10→08/19
12B
Flooring/Finishes
Install Roller Shades
12B-F-N2-1320 Floor 12B - Install Roller Shades Floor 12 B West Final Finishes
-
08/10→08/19
12B
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
12B-F-N2-1110 Floor 12B - Install Special Wall Finishes (incl. Wall Protection) Floor 12 B West Final Finishes
-
08/10→08/19
12B
Flooring/Finishes
Set Barn Doors At Patient Rooms
12B-F-N2-1240 Floor 12B - Set Barn Doors At Patient Rooms Floor 12 B West Final Finishes
-
08/10→08/23
12B
Flooring/Finishes
Signage
12B-F-N2-1330 Floor 12B - Signage Floor 12 B West Final Finishes
-
Wed 08/11
13
Inspections/QC
Pre-Test Flows & Tampers
COM13-1380 13th Floor - Pre-Test Flows & Tampers Floor 13 Testing/Commissioning/Life Safety
-
08/12→08/25
13
Electrical
Electrical Wall Fixtures/Devices
13B-F-N2-380 Floor 13 - Electrical Wall Fixtures/Devices Floor 13 A Final Finishes
-
Thu 08/12
13
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 13A
COM13-1310 13th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 13A Floor 13 Testing/Commissioning/Life Safety
-
Fri 08/13
13
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 13B
COM13-1320 13th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 13B Floor 13 Testing/Commissioning/Life Safety
-
Mon 08/16
13
Data
Final Test Horns, Strobes, Pulls, Fire Alarm 13C
COM13-1410 13th Floor - Final Test Horns, Strobes, Pulls, Fire Alarm 13C Floor 13 Testing/Commissioning/Life Safety
-
08/16→08/25
13
Flooring/Finishes
Signage
13B-F-N2-400 Floor 13 - Signage Floor 13 A Final Finishes
-
08/17→09/07
12
Inspections/QC
N12504 - Terminate & Test IT Systems Cabling
TEL-12-250 Floor 12 - N12504 - Terminate & Test IT Systems Cabling Telecom Room Lv-12 N12504
-
Tue 08/17
13
Inspections/QC
Final Test Flows & Tampers
COM13-1390 13th Floor - Final Test Flows & Tampers Floor 13 Testing/Commissioning/Life Safety
-
08/19→08/30
13
Flooring/Finishes
Install Roller Shades
13B-F-N2-390 Floor 13 - Install Roller Shades Floor 13 A Final Finishes
-
08/19→09/09
13
Flooring/Finishes
Install Special Wall Finishes (incl. Wall Protection)
13B-F-N2-250 Floor 13 - Install Special Wall Finishes (incl. Wall Protection) Floor 13 A Final Finishes
-
08/23→08/27
12A
Inspections/QC
Stocking
12A-F-N1-1370 Floor 12A - Stocking Floor 12 A East Final Finishes
-
08/24→08/30
12B
Other
Construction Clean
12B-F-N2-1340 Floor 12B - Construction Clean Floor 12 B West Final Finishes
-
08/26→09/16
13
Inspections/QC
N13505 - Terminate & Test IT Systems Cabling
TEL-13-250 Floor 13 - N13505 - Terminate & Test IT Systems Cabling Telecom Room Lv-13 N13505
-
08/30→09/03
12A
Other
Final Clean
12A-F-N1-1380 Floor 12A - Final Clean Floor 12 A East Final Finishes
-
Mon 08/30
13
Milestone
AHCA 80% Inspection Complete ◆
M680 Floor 13 - AHCA 80% Inspection Complete Construction Milestones
-
08/30→09/13
13
Ceilings
Install Balance of Ceiling Tile
13B-F-N2-410 Floor 13 - Install Balance of Ceiling Tile Floor 13 A Final Finishes
-
08/30→09/02
13
Other
Install Operable Partition
13B-F-N2-480 Floor 13 - Install Operable Partition Floor 13 A Final Finishes
-
08/31→09/28
12
Inspections/QC
Gilbane Functional/Pre-Inspections
12-P-1050 Floor 12 - Gilbane Functional/Pre-Inspections Floor 12 Clean & Punch-Out
-
08/31→09/14
12B
Inspections/QC
Load Equipment
12B-F-N2-1350 Floor 12B - Load Equipment Floor 12 B West Final Finishes
-
09/08→09/28
12
Inspections/QC
N12501 - Terminate & Test IT Systems Cabling
TEL-12-280 Floor 12 - N12501 - Terminate & Test IT Systems Cabling Telecom Room Lv-12 N12501
-
09/08→09/09
12
Data
N12504 - Clean I. T. Room
TEL-12-270 Floor 12 - N12504 - Clean I. T. Room Telecom Room Lv-12 N12504
-
09/10→09/16
12
Data
N12504 - Load Rack I. T. Equipment
TEL-12-300 Floor 12 - N12504 - Load Rack I. T. Equipment Telecom Room Lv-12 N12504
-
09/14→09/27
13
Other
Construction Clean
13B-F-N2-420 Floor 13 - Construction Clean Floor 13 A Final Finishes
-
09/15→09/16
12B
Inspections/QC
Owner Pre AHCA For Areas (A & B)
12B-F-N2-1360 Floor 12B - Owner Pre AHCA For Areas (A & B) Floor 12 B West Final Finishes
-
09/17→09/23
12
Data
N12504 - Integrate & Test I. T. Systems
TEL-12-310 Floor 12 - N12504 - Integrate & Test I. T. Systems Telecom Room Lv-12 N12504
-
09/17→09/23
12B
Inspections/QC
Stocking
12B-F-N2-1370 Floor 12B - Stocking Floor 12 B West Final Finishes
-
09/17→10/07
13
Inspections/QC
N13501 - Terminate & Test IT Systems Cabling
TEL-13-280 Floor 13 - N13501 - Terminate & Test IT Systems Cabling Telecom Room Lv-13 N13501
-
09/17→09/20
13
Data
N13505 - Clean I. T. Room
TEL-13-270 Floor 13 - N13505 - Clean I. T. Room Telecom Room Lv-13 N13505
-
09/21→09/27
13
Data
N13505 - Load Rack I. T. Equipment
TEL-13-300 Floor 13 - N13505 - Load Rack I. T. Equipment Telecom Room Lv-13 N13505
-
09/24→09/30
12B
Other
Final Clean
12B-F-N2-1380 Floor 12B - Final Clean Floor 12 B West Final Finishes
-
09/28→10/25
13
Inspections/QC
Gilbane Functional/Pre-Inspections
13-P-1040 Floor 13 - Gilbane Functional/Pre-Inspections Floor 13 Clean & Punch-Out
-
09/28→10/18
13
Inspections/QC
Load Equipment
13B-F-N2-430 Floor 13 - Load Equipment Floor 13 A Final Finishes
-
09/28→10/04
13
Data
N13505 - Integrate & Test I. T. Systems
TEL-13-310 Floor 13 - N13505 - Integrate & Test I. T. Systems Telecom Room Lv-13 N13505
-
09/29→10/26
12
Inspections/QC
Gilbane/Contractor Punch-list
12-P-1010 Floor 12 - Gilbane/Contractor Punch-list Floor 12 Clean & Punch-Out
-
09/29→09/30
12
Data
N12501 - Clean I. T. Room
TEL-12-290 Floor 12 - N12501 - Clean I. T. Room Telecom Room Lv-12 N12501
-
10/01→10/07
12
Data
N12501 - Load Rack I. T. Equipment
TEL-12-320 Floor 12 - N12501 - Load Rack I. T. Equipment Telecom Room Lv-12 N12501
-
10/08→10/14
12
Data
N12501 - Integrate & Test I. T. Systems
TEL-12-330 Floor 12 - N12501 - Integrate & Test I. T. Systems Telecom Room Lv-12 N12501
-
10/08→10/11
13
Data
N13501 - Clean I. T. Room
TEL-13-290 Floor 13 - N13501 - Clean I. T. Room Telecom Room Lv-13 N13501
-
10/12→10/18
13
Data
N13501 - Load Rack I. T. Equipment
TEL-13-320 Floor 13 - N13501 - Load Rack I. T. Equipment Telecom Room Lv-13 N13501
-
10/15→10/21
12
Inspections/QC
Pre-Test Doors/Final Test Doors
COM12-1230 12th Floor - Pre-Test Doors/Final Test Doors Floor 12 Testing/Commissioning/Life Safety
-
10/19→10/25
13
Data
N13501 - Integrate & Test I. T. Systems
TEL-13-330 Floor 13 - N13501 - Integrate & Test I. T. Systems Telecom Room Lv-13 N13501
-
10/19→10/22
13
Inspections/QC
Owner Pre AHCA
13B-F-N2-440 Floor 13 - Owner Pre AHCA Floor 13 A Final Finishes
-
Fri 10/22
12
Inspections/QC
Final Test Doors
COM12-1300 12th Floor - Final Test Doors Floor 12 Testing/Commissioning/Life Safety
-
10/25→10/29
12B
Inspections/QC
100% AHCA For Areas (A & B)
12B-F-N2-1390 Floor 12B -100% AHCA For Areas (A & B) Floor 12 B West Final Finishes
-
10/25→11/05
13
Inspections/QC
Stocking
13B-F-N2-450 Floor 13 - Stocking Floor 13 A Final Finishes
-
10/26→11/01
1
Inspections/QC
Pre-Test Doors/Final Test Doors
COM1-130 1st Floor - Pre-Test Doors/Final Test Doors Floor 1 Testing/Commissioning/Life Safety
-
10/26→11/23
13
Inspections/QC
Gilbane/Contractor Punch-list
13-P-1010 Floor 13 - Gilbane/Contractor Punch-list Floor 13 Clean & Punch-Out
-
10/26→11/01
13
Inspections/QC
Pre-Test Doors/Final Test Doors
COM13-1330 13th Floor - Pre-Test Doors/Final Test Doors Floor 13 Testing/Commissioning/Life Safety
-
10/27→11/02
12
Inspections/QC
Owner/Design Team Punch List
12-P-1030 Floor 12 - Owner/Design Team Punch List Floor 12 Clean & Punch-Out
-
Tue 11/02
1
Inspections/QC
Final Test Doors
COM1-200 1st Floor - Final Test Doors Floor 1 Testing/Commissioning/Life Safety
-
Tue 11/02
13
Inspections/QC
Final Test Doors
COM13-1400 13th Floor - Final Test Doors Floor 13 Testing/Commissioning/Life Safety
-
11/08→11/22
13
Other
Final Clean
13B-F-N2-460 Floor 13 - Final Clean Floor 13 A Final Finishes
-
11/23→12/01
13
Inspections/QC
100% AHCA
13B-F-N2-470 Floor 13 - 100% AHCA Floor 13 A Final Finishes
-
11/24→12/23
13
Inspections/QC
Owner/Design Team Punch List
13-P-1030 Floor 13 - Owner/Design Team Punch List Floor 13 Clean & Punch-Out
-
12/02→12/08
1A
Inspections/QC
100% AHCA
SC1A-N2-F-500 Floor 1A - 100% AHCA Floor 1A SC 1.N1 Final Finishes
-
Fri 12/31
·
Milestone
Final Substantial Completion - Incl. Commissioning & Inspections ◆
M330 Final Substantial Completion - Incl. Commissioning & Inspections Construction Milestones
-
Fri 12/31
·
Milestone
Owner Start Facility / Staff Training ◆
M480 Owner Start Facility / Staff Training Construction Milestones
No activities match these filters.
Building timeline…
No activities match these filters.